    CDM PRINCIPAL DESIGNER IN COURT OVER FIRE RISK

    Designers and contractor prosecuted for risk management failings

    Three companies have been prosecuted for failing to take adequate precautions against fire risk during construction of a timber frame extension to a sheltered accommodation residential home in Pershore, Worcestershire.

    Worcester Crown Court heard that in the months leading up to October 2017 the appointed designers and contractors were working on the project which involved the installation of the timber frame three-storey construction with a timber frame link extension to an occupied sheltered accommodation residential home.

    Adequate fire prevention controls were not in place thereby putting members of the public at risk.

    Major fire risks not avoided by design and management

    HSE investigators found that the defendants failed to fulfil their respective duties to plan, manage and monitor construction work in a manner that prevents risks from fire and protects persons who may be affected by the project.

    The risks should have been prevented by designing out the major fire risks and implementing a plan to incorporate measures to minimise the residual fire risk during the construction phase in accordance with industry good practice.

    • E Manton Limited – the project Principal Contractor of Birmingham Business Park, Birmingham pleaded guilty to breaching Section 3 (1) of the Health and Safety at Work Act 1974 was fined £26,000 and ordered to pay costs of £6,944.
    • MTE (Leicester) Limited – the timber frame Designer, manufacturer and installer of Sunningdale Road, Leicester pleaded guilty to breaching Section 3 (1) of the Health and Safety at Work Act 1974 was fined £20,000 and ordered to pay costs of £6,413.
    • Thornton–Firkin LLP – the project Principal Designer of Newhall Street, Birmingham pleaded guilty to breaching Section 3 (1) of the Health and Safety at Work Act 1974 and was fined £8,000 and ordered to pay costs of £7,133.

    Speaking after the hearing, HSE inspector Christopher Gregory said:

    ”These cases highlight the need for all duty-holders to take proactive action to ensure they are not putting workers and others at risk from foreseeable fire risks by taking reasonably practicable actions, in accordance with industry standards, to comply with their duties under the respective regulations. Fire kills and members of the public have a right to be protected”.

     

    Latest Construction Health and Safety News

    CONSTRUCTION SAFETY NEWS – END OF NEW CONTENT

    The addition of content on this website ceased on 17th April 2020.

    Material posted before this date can be found by clicking on our SEARCH NEWS DATABASE function.

    Posted on 3rd May 2020

    HSE WARN OF NEED FOR RPE FACE FIT TEST AND CHECK

    Incorrectly fitted RPE will not protect the wearer from dangers to health

    Read the rest of this article »

    Posted on 16th April 2020

    CORONA VIRUS: LATEST SITE OPERATING PROCEDURES

    Industry Bodies publish risk management guidance Version 3

    Read the rest of this article »

    Posted on 15th April 2020

    TOWER CRANE OUT OF SERVICE SAFETY ALERT

    Important advice from Construction Plant-hire Association and HSE

    Read the rest of this article »

    Posted on 30th March 2020

    FRAGILE ROOF REPLACEMENT PUT WORKERS IN DANGER

    Measures to prevent falling from or through the roof were missing

    Read the rest of this article »

    Posted on 30th March 2020

    WORKMAN FELL FROM EDGE OF MEZZANINE FLOOR

    Edge protection was absent and workman untrained for the task

    Read the rest of this article »

    Posted on 30th March 2020

    HSE PLAN AND CONSTRUCTION PRIORITIES 2020/21

    Appointed CDM 2015 Principal Designers remain focus of HSE inspections

    Read the rest of this article »

    Posted on 30th March 2020

    COVID-19 ADVICE & GUIDANCE FOR CONSTRUCTION

    BuildUK support industry with advice, guidance and information

    Read the rest of this article »

    Posted on 30th March 2020

    LATEST HSE CONVICTIONS AND NOTICES REGISTERS

    hselogo1View current online HSE registers of prosecution convictions and notices

    Read the rest of this article »

    Posted on 30th March 2020

    POORLY DESIGNED SCHOOL GATE CRUSHED CHILD

    Sliding gate over-run mechanism proved insufficiently robust

    Read the rest of this article »

    Posted on 9th March 2020

    POWER GENERATOR PROSECUTED OVER UNSAFE SYSTEM

    Maintenance workers seriously injured when energy suddenly released

    Read the rest of this article »

    Posted on 2nd March 2020

    CEILING BELOW SAVES WORKMAN IN ROOFLIGHT FALL

    Roofworker fell through roof after stepping on fragile rooflight

    Read the rest of this article »

    Posted on 2nd March 2020

    INEXPERIENCED WORKER FELL THROUGH OPENING

    No physical protection or warning of opening and fragile covering

    Read the rest of this article »

    Posted on 29th February 2020

    CDM PRINCIPAL DESIGNER IN COURT OVER FIRE RISK

    Designers and contractor prosecuted for risk management failings

    Read the rest of this article »

    Posted on 29th February 2020

    PRISON SENTENCE FOR RECALCITRANT DIRECTOR

    Prohibition and improvement notices ignored and danger persisted

    Read the rest of this article »

    Posted on 26th February 2020

    TEMPORARY WORKS HOARDING FELL ON PEDESTRIAN

    Member of the public struck when site fence collapsed suddenly

    Read the rest of this article »

    Posted on 26th February 2020

    CHILD FATALLY INJURED BY UNSECURED POLE

    Pole stored on embankment moved and trapped boy against fencing

    Read the rest of this article »

    Posted on 26th February 2020

    OWNER RESPONSE TO HSE INSPECTION ENDED IN COURT

    Police uphold HSE right to inspect without threats, aggression or abuse

    Read the rest of this article »

    Posted on 24th February 2020

    HSE TARGETING WELDING FUME CANCER RISK

    Inspections to enforce improved controls required by new risk evidence

    Read the rest of this article »

    Posted on 24th February 2020

    CONTRACTOR FAILED TO REPLACE MISSING PROTECTION

    Painter and decorator fractured hip in fall from landing

    Read the rest of this article »

    Posted on 18th February 2020

    RISK OF DERMATITIS SUFFICIENT FOR PROSECUTION

    Company failed to implement controls and surveillance required by COSHH

    Read the rest of this article »

    Posted on 18th February 2020

    COSHH FAILINGS CAUSE ASTHMA AND PROVE COSTLY

    Uncontrolled exposure to isocyanates during paint spraying operations

    Read the rest of this article »

    Posted on 18th February 2020

    POLICE EMPLOYEE SHOCKED BY DATA CABLE WORK

    South Wales Force fined over electric shock from ceiling void cable

    Read the rest of this article »

    Posted on 18th February 2020

    COLLAPSE OF PUMP SET TRAPPED WORKMAN

    Unsafe system of work transferring from pallet to a raised platform

    Read the rest of this article »

    Posted on 18th February 2020

    MODIFIED PODIUM STEPS CAUSE FALL FROM HEIGHT

    Firm failed to select and correctly assemble with necessary training

    Read the rest of this article »

    Posted on 14th February 2020
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data