• Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    FIRMS FINED HEAVILY OVER STUDENT FIRE RISK

    Senior fire officers found “blatant disregard” for law and resident safety

    Fines totalling £670,000 have been imposed over ‘potentially catastrophic’ fire safety failings at Leeds student flats in September 2016.

    Leeds Crown Court heard how Trinity Halls on Woodhouse Street had only one available fire escape which was compromised due to combustible materials, putting 27 students at serious risk.

    The court heard the students had moved into the building on the upper ground floor while other floors were still under construction. There were a string of other failures which contributed to the significant risk including lack of appropriate fire alarms and detection, exposed timber framing, the storage of flammable items on stairwells and no markings indicating fire escape routes.

    Lack of alarms and detection

    The court heard that a lack of fire alarms and detection within the building meant that in the event of a fire, students would not have had early warning to evacuate the building and upon evacuation, some students would have had to travel 35m to the nearest fire escape, almost double the recommended limit of 18m.

    Judge Mairs described the situation as having the “potential for catastrophe.”

    The failings came to light in September 2016 after a concerned father called West Yorkshire Fire and Rescue Service (WYFRS) to report the building. He had been dropping his daughter off to live there, but became concerned by the state of the premises and would not let his daughter stay.

    WYFRS inspectors attended the building and discovered breaches in legislation. Inspectors issued a prohibition order meaning students had to vacate the property.

    • Trinity Developments Ltd – the owners of the building, admitted four safety breaches of failing to: make a suitable and sufficient fire risk assessment; take precautions to make sure the premises were safe from risk of fire;  provide appropriate fire detection and alarm system and provide an adequate number of fire escape routes and exits. The defendant was fined £160,000.
    • Niche Homes Ltd – contracted to manage and let the property, also admitted the same four breaches and were fined £60,000.
    • APP Construction Ltd – who were contracted to design and build the property, admitted one charge of failing to provide an adequate number of fire escape routes and exits and were fined £450,000.

    The companies were all offered credit in court for their early guilty pleas. Acceptable safety measures are now in place at the building.

    High culpability for obvious risks

    Judge Mairs said that all the companies had “high culpability” and that “the risks were so obvious that a member of the public spotted them – so they should have been obvious to the companies involved.”

    Following the sentencing Chris Kemp, Senior Fire Protection Manager for West Yorkshire Fire and Rescue Service, said:

    “This case demonstrates the importance those responsible for building construction, development and occupation have in understanding their duties and acting responsibly to take account of the safety of the people they are responsible for.

    As Judge Mairs highlighted, the dangers and risks found at Trinity Halls were so obvious anyone without a technical fire safety background could identify them. The conditions that were found on site were such that some of our senior officers have not seen such blatant disregard for the law and the safety of residents in 28 years.”

    Latest Construction Health and Safety News

    TOWER CRANE OUT OF SERVICE SAFETY ALERT

    Important advice from Construction Plant-hire Association and HSE

    Read the rest of this article »

    Posted on 30th March 2020

    FRAGILE ROOF REPLACEMENT PUT WORKERS IN DANGER

    Measures to prevent falling from or through the roof were missing

    Read the rest of this article »

    Posted on 30th March 2020

    WORKMAN FELL FROM EDGE OF MEZZANINE FLOOR

    Edge protection was absent and workman untrained for the task

    Read the rest of this article »

    Posted on 30th March 2020

    HSE PLAN AND CONSTRUCTION PRIORITIES 2020/21

    Appointed CDM 2015 Principal Designers remain focus of HSE inspections

    Read the rest of this article »

    Posted on 30th March 2020

    COVID-19 ADVICE & GUIDANCE FOR CONSTRUCTION

    BuildUK support industry with advice, guidance and information

    Read the rest of this article »

    Posted on 30th March 2020

    LATEST HSE CONVICTIONS AND NOTICES REGISTERS

    hselogo1View current online HSE registers of prosecution convictions and notices

    Read the rest of this article »

    Posted on 30th March 2020

    POORLY DESIGNED SCHOOL GATE CRUSHED CHILD

    Sliding gate over-run mechanism proved insufficiently robust

    Read the rest of this article »

    Posted on 9th March 2020

    POWER GENERATOR PROSECUTED OVER UNSAFE SYSTEM

    Maintenance workers seriously injured when energy suddenly released

    Read the rest of this article »

    Posted on 2nd March 2020

    CEILING BELOW SAVES WORKMAN IN ROOFLIGHT FALL

    Roofworker fell through roof after stepping on fragile rooflight

    Read the rest of this article »

    Posted on 2nd March 2020

    INEXPERIENCED WORKER FELL THROUGH OPENING

    No physical protection or warning of opening and fragile covering

    Read the rest of this article »

    Posted on 29th February 2020

    CDM PRINCIPAL DESIGNER IN COURT OVER FIRE RISK

    Designers and contractor prosecuted for risk management failings

    Read the rest of this article »

    Posted on 29th February 2020

    PRISON SENTENCE FOR RECALCITRANT DIRECTOR

    Prohibition and improvement notices ignored and danger persisted

    Read the rest of this article »

    Posted on 26th February 2020

    TEMPORARY WORKS HOARDING FELL ON PEDESTRIAN

    Member of the public struck when site fence collapsed suddenly

    Read the rest of this article »

    Posted on 26th February 2020

    CHILD FATALLY INJURED BY UNSECURED POLE

    Pole stored on embankment moved and trapped boy against fencing

    Read the rest of this article »

    Posted on 26th February 2020

    OWNER RESPONSE TO HSE INSPECTION ENDED IN COURT

    Police uphold HSE right to inspect without threats, aggression or abuse

    Read the rest of this article »

    Posted on 24th February 2020

    HSE TARGETING WELDING FUME CANCER RISK

    Inspections to enforce improved controls required by new risk evidence

    Read the rest of this article »

    Posted on 24th February 2020

    CONTRACTOR FAILED TO REPLACE MISSING PROTECTION

    Painter and decorator fractured hip in fall from landing

    Read the rest of this article »

    Posted on 18th February 2020

    RISK OF DERMATITIS SUFFICIENT FOR PROSECUTION

    Company failed to implement controls and surveillance required by COSHH

    Read the rest of this article »

    Posted on 18th February 2020

    COSHH FAILINGS CAUSE ASTHMA AND PROVE COSTLY

    Uncontrolled exposure to isocyanates during paint spraying operations

    Read the rest of this article »

    Posted on 18th February 2020

    POLICE EMPLOYEE SHOCKED BY DATA CABLE WORK

    South Wales Force fined over electric shock from ceiling void cable

    Read the rest of this article »

    Posted on 18th February 2020

    COLLAPSE OF PUMP SET TRAPPED WORKMAN

    Unsafe system of work transferring from pallet to a raised platform

    Read the rest of this article »

    Posted on 18th February 2020

    MODIFIED PODIUM STEPS CAUSE FALL FROM HEIGHT

    Firm failed to select and correctly assemble with necessary training

    Read the rest of this article »

    Posted on 14th February 2020

    SCHOOL LACKED SAFE SYSTEM FOR ROOF RETRIEVAL

    Workman fell from roof whilst retrieving shoe of pupil

    Read the rest of this article »

    Posted on 11th February 2020

    ARM OF WORKMAN AMPUTATED IN CONVEYOR

    Major construction materials supplier fined heavily over unsafe system

    Read the rest of this article »

    Posted on 11th February 2020

    CONCRETE BLOCK PLANT GUARDING BREACHED

    Sections of machinery perimeter safety fencing missing for months

    Read the rest of this article »

    Posted on 11th February 2020
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data