• Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    TEMPORARY WORKS: HSE FREQUENTLY ASKED QUESTIONS

    HSE provide answers to basic temporary works issues 

    “Temporary works” are “engineered solutions” used to support or protect an existing structure or the permanent works during construction, or to support an item of plant or equipment, or the vertical sides or side-slopes of an excavation, or to provide access. The construction of most types of permanent works will require the use of some form of temporary works.

    Temporary works is defined in BS5975: 2008 “Code of practice for temporary works procedures and the permissible stress design of falsework” as “(those) parts of the works that allow or enable construction of, protect, support or provide access to, the permanent works and which might or might not remain in place at the completion of the works”.

    Examples of temporary works include, but are not limited to:

    • Earthworks – trenches, excavations, temporary slopes and stockpiles. Structures – formwork, falsework, propping, façade retention, needling, shoring, edge protection, scaffolding, temporary bridges, site hoarding and signage, site fencing, cofferdams.
    • Equipment/plant foundations – tower crane bases, supports, anchors and ties for construction hoists and mast climbing work platforms (MCWPs), groundworks to provide suitable locations for plant erection, e.g. mobile cranes and piling rigs.

    HSE has now issued answers to a range of Frequently Asked Questions regarding “temporary works” which are repeated below.

    More detailed information on Management of Temporary Works is also available. 

    **************************

     

    TEMPORARY WORKS – HSE FREQUENTLY ASKED QUESTIONS

     

    What are permanent works?

    Permanent works are the parts of a construction project that will be used and remain in position for a long time – e.g. 60 years. This includes buildings and structures such as bridges, roads, retaining walls, etc. The construction of most types of permanent works will require the use of some form of temporary works.

    What are temporary works?

    Temporary works (TW) are the parts of a construction project that are needed to enable the permanent works to be built. Usually the TW are removed after use – e.g. access scaffolds, props, shoring, excavation support, falsework and formwork, etc. Sometimes the TW is incorporated into the permanent works – e.g. haul road foundations and crane or piling platforms may be used for hardstanding or road foundations.

    Are temporary works different to permanent works?

    It is very important that the same degree of care and attention is given to the design and construction of temporary works (TW) as to the design and construction of the permanent works. As TW may be in place for only a short while there is a tendency to assume they are less important. This is incorrect. Lack of care with design, selection, assembly, etc leaves TW liable to fail or collapse. This places people at risk of injury and can cause the project to be delayed.

    Can I organise the temporary works myself?

    The person organising the temporary works needs to be aware of the problems that can occur at each stage of the process and how to prevent these. They need to coordinate design, selection of equipment, appointment of contractors, supervision of work, checking completion, authorisation to load and removal. Unless this is done in a thorough and systematic way problems are likely to occur. If you take this on yourself you must ensure each part of the process is correctly carried out.

    Do I have to appoint a ‘temporary works coordinator’ (TWC)?

    British Standard 5975 sets out one way of managing temporary works (TW) that has been found to work well on medium and large projects and uses the job title Temporary Works Coordinator (TWC). There is no legal requirement to use this job title or the BS recommended process, but you should remember that BS5975 provides an industry consensus view on what is considered to be good practice. The legal requirement is that the party in control must ensure that work is allocated and carried out in a manner that does not create unacceptable risk of harm to workers or members of the public. On projects with relatively simple TW needs, you may choose not to appoint a TWC. However, you must still make sure that TW are properly managed to ensure safety.

    Do I need to provide calculations for every temporary works situation?

    Where the situation is small scale and straightforward there may be a “standard solution” provided for the temporary works (TW). These include, for example, use of a tower or system scaffold for access; design of a basic access scaffold to a standard configuration using existing data from tables; selection of a trench box to support a 2m excavation in firm, dry ground. In each of these cases the person organising the TW will need to assess the ground to be sure it is suitable for the equipment involved, and check that any assumptions made in the calculations for the standard solution are valid for this particular situation and the conditions on site. On a simple job the supplier’s data will allow an experienced person to consider the necessary issues without further calculation.

    Propping using standard equipment such as screw props (‘Acrows’) needs careful consideration. To select the type, size, number and decide spacing, information is needed about the loads that will act on the props. This will include the wall above and the additional load from any other floor or roof beams etc that enter the wall above or close to the opening. Even with proprietary equipment, the support system must be worked out by a person who knows the correct methods of assessing the loads and designing the support arrangement. Failure of TW is often found to result from the loadings being underestimated; and in particular where loadings from the sides are not considered.

    Can all structural engineers design temporary works?

    No. Temporary works (TW) can be very sensitive to how they are used and are easily affected by other work taking place nearby. For these reasons the TW designer needs TW training and experience.

    If I get a structural engineer to design the temporary works will they be the project TWC?

    No. Coordinating the temporary works (TW) is not automatically the responsibility of the engineer carrying out the design work. Coordination is a much wider role that includes planning where and when TW will be needed and ensuring that they are correctly installed, used, checked and maintained. Some design engineers may be happy to be additionally contracted to act as project Temporary Works Coordinator.

    Latest Construction Health and Safety News

    BULK BAG COLLAPSE CAUSED BY UNSAFE STACKING

    Bulk bag collapsed onto workman when struck by fork lift

    Read the rest of this article »

    Posted on 9th December 2019

    INTERLOCKED GUARD NOT WORKING TO ISOLATE POWER

    Two workmen seriously injured when plant started unexpectedly

    Read the rest of this article »

    Posted on 9th December 2019

    STREET FURNITURE RISK TO PUBLIC FINED £1.4M

    Council prosecuted following injury to child playing on hinged bollard

    Read the rest of this article »

    Posted on 9th December 2019

    WORKMEN SUFFER SERIOUS BURNS FROM CABLE STRIKE

    Assessment and system of work failed to appreciate electrical risk

    Read the rest of this article »

    Posted on 29th November 2019

    LADDERS WERE INAPPROPRIATE FOR WORK ON ROOF

    Workman paralysed after falling whilst installing roof ladder

    Read the rest of this article »

    Posted on 28th November 2019

    FIRM FAILED TO MANAGE EXHAUST VENTILATION

    HSE enforcement notices on wood dust and welding fume ignored

    Read the rest of this article »

    Posted on 27th November 2019

    RECALCITRANT DIRECTOR BARRED FROM OFFICE

    Dangerous telehandler used despite earlier fatality and enforcement

    Read the rest of this article »

    Posted on 25th November 2019

    DIRECTOR HID UNSAFE WORKING PRACTICES FROM HSE

    Workers exposed to sprayed paints containing asthma causing isocyantes

    Read the rest of this article »

    Posted on 25th November 2019

    JAIL TERM FOR CONTRACTOR CAUSING GAS RISK

    Roofer sentenced after work caused carbon monoxide release

    Read the rest of this article »

    Posted on 22nd November 2019

    UNSTABLE STAIRCASE COLLAPSE DURING REFURB WORK

    Workman not informed of staircase hazard suffered serious injury

    Read the rest of this article »

    Posted on 22nd November 2019

    UNUSED SEAT BELT WAS “COMMON PRACTICE” ON SITE

    Overturning dumper truck caused death of operators at spoil heap

    Read the rest of this article »

    Posted on 22nd November 2019

    SELECTED NEWS POSTED RECENTLY ON TWITTER

    PP Construction Safety logo and link to home page [1]Links to other construction health and safety related news reports

    Read the rest of this article »

    Posted on 18th November 2019

    HSE LOOK TO LOCAL AUTHORITIES FOR CDM SUPPORT

    Council Inspectors focus on CDM client duties – asbestos, fragility and RCS

    Read the rest of this article »

    Posted on 14th November 2019

    VERBAL WARNING OF DANGER IS NO DEFENCE

    Hand of female worker entangled in modified metal drilling rig

    Read the rest of this article »

    Posted on 14th November 2019

    UNDERGROUND CABLE STRIKE CAUSES 50% BURNS

    Workman seriously injured using hand-held breaker to excavate post holes

    Read the rest of this article »

    Posted on 14th November 2019

    HSE WELDING FUME REVISED GUIDANCE PUBLISHED

    New research evidence on cancer link prompts revision on welding fume

    Read the rest of this article »

    Posted on 14th November 2019

    VIBRATION MANAGEMENT FAILINGS FINED £600,000

    Vital health surveillance, tool replacement and management found wanting

    Read the rest of this article »

    Posted on 14th November 2019

    HSE ENFORCEMENT DATABASE LATEST UPDATE

    hselogo1View current online register of HSE prosecutions and enforcement notices

    Read the rest of this article »

    Posted on 31st October 2019

    DEVELOPER AND DIRECTOR PUT PUBLIC AT RISK

    Demolition undertaken without surveys and effective safety precautions

    Read the rest of this article »

    Posted on 28th October 2019

    BY-PASSING MACHINE INTERLOCK FINED £1.275 MILLION

    Trapped key safety system failed to prevent access to conveyor danger

    Read the rest of this article »

    Posted on 24th October 2019

    HSE LOSES PATIENCE WITH ERRANT CONTRACTOR

    Roofing firm fined £30,000 over failure to manage work at height risks

    Read the rest of this article »

    Posted on 24th October 2019

    TRUSS ERECTION LACKED INTERNAL FALL PROTECTION

    Carpenter fell and injured whilst falling with roof truss

    Read the rest of this article »

    Posted on 24th October 2019

    WORKMAN FELL HEAD FIRST THROUGH ROOFLIGHT

    Fragile roof dangers not assessed and properly controlled

    Read the rest of this article »

    Posted on 24th October 2019

    STRUCTURAL SAFETY BODY LATEST NEWSLETTER

    CROSS publishes reports and expert comment on a range of issues

    Read the rest of this article »

    Posted on 18th October 2019

    HSE RISK REDUCTION THROUGH DESIGN AWARD

    Regulator seeks to promote hazard avoidance and risk minimisation

    Read the rest of this article »

    Posted on 18th October 2019
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data