• Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    OLYMPIC STADIUM CONSTRUCTORS PRAISED FOR PERFORMANCE

    Stadium on time, under budget and with an exemplary safety record 

    The last piece of turf has been laid today on the Olympic Stadium’s field of play, marking the completion of construction on the flagship venue. 

    Construction started on the Olympic Stadium three years ago and has been completed “on time, under budget and with an exemplary safety record“. Over 240 UK businesses won contracts for construction of the Stadium and over 5250 people worked on the project. 

    ODA chairman John Armitt praised the design and construction team led by Sir Robert McAlpine saying:

    “The Olympic Stadium has been finished on time and under budget. To complete a complicated project such as this in less than three years is testament to the skill and professionalism of the UK construction industry. I would like to thank the Team Stadium consortium and all of the workers for their hard work and commitment.”

    Secretary of State for Culture, Olympics, Media and Sport Jeremy Hunt said:

    “The Olympic Stadium is the stunning centrepiece of the Olympic Park. Hundreds of businesses from across the UK have been involved in its creation. This is another landmark day for the London 2012 project and shows that Britain is at the forefront of the construction world.”

    Construction facts and figures
    • Construction started in May 2008 and has been completed in just under three years.
    • Design and construction team led by Sir Robert McAlpine
    • Over 5250 people have worked on the project over the past three years with the operatives workforce peaking at 650
    • Over 240 businesses, from Devon to Scotland, have worked on the construction of the Stadium.
    • More than 5,000 reinforced concrete columns were installed into the ground, up to 20m deep, to provide the foundations to support the Stadium structure
    • 112 steel rakers and 12,000 pre-cast concrete terracing units hold the spectator seating in place
    • Roof compression truss is made up of 28 steel sections, each one is 15m high by 30m long and weigh 85 tonne. A 1,350-tonne super lift crane was assembled in the field of play to lift them into place between January and July in 2009.
    • Cable net roof provides the correct conditions for athletes on the field of play and covering two-thirds of spectators. The roof is covered by 112 panels of white material, totalling 25,000 m². The fabric was fitted by a team of 23 expert abseilers.
    • Stadium is lit by 532 individual floodlights housed in 14 towers. The top of the towers reach 70m above the field of play.
    • 14 lighting tower weigh 34 tonnes each and are 28m high. They were lifted into place by a 650 tonne crane over a period of 14 days in March 2010.
    • 700 rooms and spaces within the Stadium, including changing rooms and toilets. The fit-out work has required15,000sqm of plasterboard, 140,000 blocks to create walls, 11km of pipes for drainage, 338km of power cables plus 33km of other data systems cabling and 12km of ventilation ducts.
    • Turf for the field of play was grown in Scunthorpe and was laid over a period of three days in March 2011.
    • Track will be laid later this year to allow for LOCOG to carry out temporary overlay work which may need cranes and so could damage the track if it was laid now.
    • Black and white spectator seats were designed in the UK and manufactured in a factory in Luton. They were fitted between May and December 2010.
    • Toilets for spectators are spread out across 32 separate buildings on the podium level and are all now functional.

    Latest Construction Health and Safety News

    CONSTRUCTION SAFETY NEWS – END OF NEW CONTENT

    The addition of content on this website ceased on 17th April 2020.

    Material posted before this date can be found by clicking on our SEARCH NEWS DATABASE function.

    Posted on 3rd May 2020

    HSE WARN OF NEED FOR RPE FACE FIT TEST AND CHECK

    Incorrectly fitted RPE will not protect the wearer from dangers to health

    Read the rest of this article »

    Posted on 16th April 2020

    CORONA VIRUS: LATEST SITE OPERATING PROCEDURES

    Industry Bodies publish risk management guidance Version 3

    Read the rest of this article »

    Posted on 15th April 2020

    TOWER CRANE OUT OF SERVICE SAFETY ALERT

    Important advice from Construction Plant-hire Association and HSE

    Read the rest of this article »

    Posted on 30th March 2020

    FRAGILE ROOF REPLACEMENT PUT WORKERS IN DANGER

    Measures to prevent falling from or through the roof were missing

    Read the rest of this article »

    Posted on 30th March 2020

    WORKMAN FELL FROM EDGE OF MEZZANINE FLOOR

    Edge protection was absent and workman untrained for the task

    Read the rest of this article »

    Posted on 30th March 2020

    HSE PLAN AND CONSTRUCTION PRIORITIES 2020/21

    Appointed CDM 2015 Principal Designers remain focus of HSE inspections

    Read the rest of this article »

    Posted on 30th March 2020

    COVID-19 ADVICE & GUIDANCE FOR CONSTRUCTION

    BuildUK support industry with advice, guidance and information

    Read the rest of this article »

    Posted on 30th March 2020

    LATEST HSE CONVICTIONS AND NOTICES REGISTERS

    hselogo1View current online HSE registers of prosecution convictions and notices

    Read the rest of this article »

    Posted on 30th March 2020

    POORLY DESIGNED SCHOOL GATE CRUSHED CHILD

    Sliding gate over-run mechanism proved insufficiently robust

    Read the rest of this article »

    Posted on 9th March 2020

    POWER GENERATOR PROSECUTED OVER UNSAFE SYSTEM

    Maintenance workers seriously injured when energy suddenly released

    Read the rest of this article »

    Posted on 2nd March 2020

    CEILING BELOW SAVES WORKMAN IN ROOFLIGHT FALL

    Roofworker fell through roof after stepping on fragile rooflight

    Read the rest of this article »

    Posted on 2nd March 2020

    INEXPERIENCED WORKER FELL THROUGH OPENING

    No physical protection or warning of opening and fragile covering

    Read the rest of this article »

    Posted on 29th February 2020

    CDM PRINCIPAL DESIGNER IN COURT OVER FIRE RISK

    Designers and contractor prosecuted for risk management failings

    Read the rest of this article »

    Posted on 29th February 2020

    PRISON SENTENCE FOR RECALCITRANT DIRECTOR

    Prohibition and improvement notices ignored and danger persisted

    Read the rest of this article »

    Posted on 26th February 2020

    TEMPORARY WORKS HOARDING FELL ON PEDESTRIAN

    Member of the public struck when site fence collapsed suddenly

    Read the rest of this article »

    Posted on 26th February 2020

    CHILD FATALLY INJURED BY UNSECURED POLE

    Pole stored on embankment moved and trapped boy against fencing

    Read the rest of this article »

    Posted on 26th February 2020

    OWNER RESPONSE TO HSE INSPECTION ENDED IN COURT

    Police uphold HSE right to inspect without threats, aggression or abuse

    Read the rest of this article »

    Posted on 24th February 2020

    HSE TARGETING WELDING FUME CANCER RISK

    Inspections to enforce improved controls required by new risk evidence

    Read the rest of this article »

    Posted on 24th February 2020

    CONTRACTOR FAILED TO REPLACE MISSING PROTECTION

    Painter and decorator fractured hip in fall from landing

    Read the rest of this article »

    Posted on 18th February 2020

    RISK OF DERMATITIS SUFFICIENT FOR PROSECUTION

    Company failed to implement controls and surveillance required by COSHH

    Read the rest of this article »

    Posted on 18th February 2020

    COSHH FAILINGS CAUSE ASTHMA AND PROVE COSTLY

    Uncontrolled exposure to isocyanates during paint spraying operations

    Read the rest of this article »

    Posted on 18th February 2020

    POLICE EMPLOYEE SHOCKED BY DATA CABLE WORK

    South Wales Force fined over electric shock from ceiling void cable

    Read the rest of this article »

    Posted on 18th February 2020

    COLLAPSE OF PUMP SET TRAPPED WORKMAN

    Unsafe system of work transferring from pallet to a raised platform

    Read the rest of this article »

    Posted on 18th February 2020

    MODIFIED PODIUM STEPS CAUSE FALL FROM HEIGHT

    Firm failed to select and correctly assemble with necessary training

    Read the rest of this article »

    Posted on 14th February 2020
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data