Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    HSE DEMOLITION INCIDENT CASE STUDIES

    Regulator advice focuses on underlying causes of recent demo incidents

    Twelve brief Case Studies on demolition incidents have been released by HSE which are reproduced below.

    The regulator is urging those involved in demolition projects to consider the scenarios and ask themselves if they could mitigate for these “common lapses in judgement or process”. If not, the HSE advice is to review their own processes with a particular focus on thorough planning, management and control of demolition and refurbishment work.

    The HSE initiative is prompted by the raised public profile of the demolition industry “by the recent airing of the Channel 5 documentary – When Demolitions Go Wrong, which has focused on the impact of incidents but not the underlying causes.”

    HSE has looked at the learning points from incidents that have occurred during demolition and significant refurbishment works and has collected the case studies which cover a range of incidents, some of which resulted in death or serious injury and others which could easily have led to single or multiple casualties.

    In all cases, even where there were no casualties, HSE stress that additional commercial costs often exceeded any potential saving resulting from shortcuts.

     

    DEMOLITION CASE STUDIES

     

    • Case Study 1 – Failure to provide sufficient pre-demolition information by client: A contract to demolish high rise residential blocks built of large precast panels used a ground based high reach demolition machine.  The client provided little information on the building structure to the contractor. Structural connection between panels had been poorly designed, poorly built and had deteriorated further during the life of the building.  Lack of adequate information (and lack of adequate survey or assessment prior to work starting) led to a premature collapse of multiple floors across several bays during demolition works. Fortunately, because the high reach machine was large enough, as was the exclusion zone, there were no injuries. However, the project was substantially delayed while the incident was investigated, and remedial action taken.  This type of building often needs panel connections to be stiffened and floors propped to a formal design prior to demolition.
    • Case Study 2 – Contractor competence. Basement extension work poorly designed and executed: A community building used daily by a local playgroup had a new basement dug out by tunnelling underneath the building across the full perimeter.  Support was provided by a couple of Acrows and the sides of the excavation were not shored up while underpinning was carried out in stages.  The contractor believed he was working in solid rock but in reality, it was loose shale.  Emergency works to prop the cavern and save the building made further work extremely difficult.  This caused the contractor to go out of business.  All excavations and especially where they are beneath or close to existing structures need to be meticulously designed and carried out which allows the cost of temporary works to be factored in and understood from an early stage.
    • Case Study 3 – Contractor competence. Approved sequence not followed causing collapse: The method statement for construction of a rear extension called for a new strip concrete foundation along the full length of the existing property to be installed in 1 metre sections, to avoid undermining existing foundations.  The builder decided it would be quicker to dig the full length of the trench in one go.  The existing building collapsed into the excavation injuring several workers.  The method statement should have been followed but other types of foundation could have been considered – including short bored piles or pads and a ground level ring beam.
    • Case Study 4 – Failure to correctly assess existing structure: Demolition workers assessed the form of construction of a single storey, concrete slab roofed building on the hoof and decided that because the soffit was flat and unjointed that the roof must have been cast in-situ and would be reinforced in both directions.  They punched a hole in one wall for plant access and were working inside when several of the precast, reinforced concrete roof planks hinged down killing one of them.  The punched hole had removed its bearing.  The soffit was smooth because it had been plastered with grey gypsum and the roof felting masked the upper surface.  Simple further checks and clues would have revealed the form of construction.  Cast in-situ slabs are not necessarily fully reinforced in both directions and in some cases suspended slabs are not reinforced at all.  Simple equipment is available to check for the presence and direction of steel reinforcement.  Safe intrusive methods of checking are also available – such as core drilling or limited breakout – e.g. from a tower scaffold.  Where possible, machine demolition from the ground and an exclusion zone is preferred and where this isn’t possible designed back-propping could have reduced the risk of wholesale failure.
    • Case Study 5 – Temporary load on existing structure not assessed: Demolition temporary works design considered mobile plant loadings on suspended reinforced concrete floor slabs but did not consider the rubble ramps that the contractor intended to use to allow plant to track down onto each floor in turn.  The contractor didn’t realise the rubble ramp hadn’t been assessed.  The floor became overloaded and collapsed progressively taking out floors below resulting in fatal and major injuries.  Had the task been fully assessed the need for back-propping or floor to floor transfer by crane would have been obvious.
    • Case Study 6 – Failure to consider implications of removing cross walls: A large brick building was being converted into flats. Neither the designer nor the contractor considered the effect of proposed alterations to the existing structure.  All internal walls and floors were removed in one go leaving the brick shell and roof in place.  The internal cross walls and floor joists had been providing support to the external walls which were now too long to resist wind loading without movement.  The building collapsed while the site was closed and before new walls and floors could be installed.  The permanent works designer should have considered the effect of necessary demolition work.  In some cases, designing a phased sequence of installing new walls and floors before removing old ones can be used to ensure stability is maintained throughout the process.  An alternative approach is formal design and early installation of extensive temporary works to provide support.
    • Case Study 7 – Support provided by non-loadbearing elements: All structural works on a masonry building were stopped due to concern about its stability.  The contractor took out some window frames they thought were non-structural.  These were providing sufficient fortuitous support to hold up a gable wall which collapsed causing other parts of the building to collapse.  Several were killed and injured.  Older buildings may need a designed internal and/or external structural scaffold or steel frame to hold them up while structural refurbishment is carried out.
    • Case Study 8 – Load bearing elements removed during soft strip: Timber sheathing panels were removed during soft stripping of a single storey timber frame school building that was being demolished.  The building, including the roof collapsed onto workers who were still inside.  No one had checked or realised that the plywood panels were structural and were bracing the timber frame.  Once they were removed the building was no longer stable.  Fortunately, only minor injuries resulted.  A proper survey of the structure would have identified the form of construction and the lack of separate bracing.
    • Case Study 9 – Agreed sequence not followed causing scaffold collapse: A large sheeted scaffold screen incorporating access platforms was designed and erected to encase a building.  The sheeting prevented dust and debris falling into surrounding public areas while the building was demolished floor by floor by small excavators.  The scaffold was supposed to be dismantled progressively as each floor was demolished.  It was not.  The wind got up and the sail effect overloaded ties into the remains of the building.  These failed and the scaffold collapsed onto a town centre public road.  Fortunately, the Fire Service had been called to reports of the scaffold moving and had been able to evacuate the area so there were no casualties.  Demolition work should have been halted at the right stage until the scaffold contractor had attended to reduce the height of the scaffold.
    • Case Study 10 – Existing structure overloaded by removed materials: A refurbishment contractor created openings in internal walls to a prepared design but stored the bricks on a suspended timber floor for reuse.  The floor became overloaded and collapsed injuring several workers.  In some instances, materials can be stored close to point of use in order to minimise manual handling.  In other situations, this can overload the structure.  A temporary works engineer would have been able to advise on how much load the floor could take and how to place load to minimise risk.
    • Case Study 11 – Designer instructions not clear & contractor too keen: A building contractor was engaged to construct an extension to an occupied old people’s home.  The architect specified that foundations should be dug down to competent ground and then agreed with local Building Control.  The contractor tried to excavate foundation trenches but could not find competent ground, so he excavated an unsupported foundation pit with the intention of using formwork to create the strip foundation.  When he reached 4 metres depth he found competent ground.  His efforts to prop and stabilise a cast iron 250mm diameter live water main that he found at the edge of his excavation were somewhat haphazard but fortunately the main did not fail – if it had the existing building shallow foundations would have been washed out, adding to risk of rapid collapse of the occupied building.  The local water supplier discovered what was going on and the excavation was concrete filled as emergency works.  The architect should have been mindful that the building was occupied and given a clearer specification.  A soil survey could have been commissioned to check conditions which would have suggested a range of alternative foundation options – including bored mini piles or a raft.  Risk to residents, delays and high additional cost could have been avoided.
    • Case Study 12 – Unchecked change to system of work caused collapse: A cinema was being demolished and the workers decided to speed up the job by toppling long span roof trusses to the ground instead of lifting them down as per the method statement.  This caused a section of concrete roof slab to move and topple the upper masonry storey which in turn pushed the perimeter scaffold away from the building, so it overturned and fell across a high street.  Vehicles and members of the public were trapped beneath it. It stopped just short of a supermarket plate glass window completely blocking the road.  By sheer luck no fatalities or major injuries resulted.  The planned and designed sequence of work must always be followed unless changes are fully assessed and agreed by the design team.

    Latest Construction Health and Safety News

    ASBESTOS REMOVED WITHOUT SURVEY OR CONTROLS

    Client fined over failure to commission refurb and demo survey

    Read the rest of this article »

    Posted on 15th July 2019

    ‘VICTORIAN’ SAFETY AND FATIGUE BEHIND RAIL DEATH

    Investigation report links zero hours contracts to hazardous fatigue

    Read the rest of this article »

    Posted on 13th July 2019

    MPS EXAMINE CONSTRUCTION RESPIRATORY HEALTH

    Parliamentary group calls for evidence on the impact of worker silicosis

    Read the rest of this article »

    Posted on 12th July 2019

    UNSAFE LIFTING OPERATION TRAPPED WORKMAN

    Sling failure and inadequate lifting plan resulted in leg amputation

    Read the rest of this article »

    Posted on 12th July 2019

    HSE ENFORCEMENT DATABASE LATEST UPDATE

    hselogo1View current online register of HSE prosecutions and enforcement notices

    Read the rest of this article »

    Posted on 11th July 2019

    TIMBER FRAME FIRM FAILED ON FIRE AND FALLING

    House builder fined after routine HSE site inspection

    Read the rest of this article »

    Posted on 11th July 2019

    FIRM FAILED TO ACT ON SILICA DUST RISK

    Cutting of paving flags exposed workers to respirable crystalline silica

    Read the rest of this article »

    Posted on 11th July 2019

    POST GRENFELL BUILDING SAFETY SYSTEM REVIEW

    Structural safety body seek support for key reporting role

    Read the rest of this article »

    Posted on 11th July 2019

    OVERCOME BY CUTTING IN CONFINED SPACE

    Construction worker suffered carbon monoxide poisoning

    Read the rest of this article »

    Posted on 8th July 2019

    APPRENTICE OVERCOME BY CHEMICAL VAPOUR

    Stripping operations lacked ventilation controls, RPE and training

    Read the rest of this article »

    Posted on 8th July 2019

    DEBRIS FROM DEMOLITION SITE NOT RESTRAINED

    Loss assessor on adjacent property injured by stray waste

    Read the rest of this article »

    Posted on 8th July 2019

    WORKMAN FELL FROM UNGUARDED FLAT ROOF

    Basic work at height management systems and training absent

    Read the rest of this article »

    Posted on 8th July 2019

    CONSTRUCTION FATALITIES FALL TO RECORD LOW

    hselogo1HSE release final annual workplace fatality figures 2018/19

    Read the rest of this article »

    Posted on 3rd July 2019

    FEMALE WORKER SCALPED AND BADLY INJURED

    Wood product manufacturer fined £466,000 over rotating shaft danger

    Read the rest of this article »

    Posted on 2nd July 2019

    TOWER SCAFFOLD FALL CAUSED LONG-TERM DAMAGE

    Principal Contractor director and two firms sentenced after worker fall

    Read the rest of this article »

    Posted on 2nd July 2019

    MISSING PEDESTRIAN BARRIER TRIGGERED DEATH

    Workman walked from building into path of moving lorry

    Read the rest of this article »

    Posted on 26th June 2019

    WORKMAN SURVIVED 9M FLAT ROOF FALL

    Suitable and sufficient edge protection not provided

    Read the rest of this article »

    Posted on 26th June 2019

    PRISON SENTENCE FOR IGNORING HSE PROHIBITION

    Roofing contractor sentenced over unsafe working at height

    Read the rest of this article »

    Posted on 15th June 2019

    FIRM FAILED ON SILICA RISK MANAGEMENT

    Dust exhaust ventilation, RPE and health surveillance all absent

    Read the rest of this article »

    Posted on 14th June 2019

    WOMAN DIED TRAPPED IN POWERED ROLLER DOOR

    Firm did not check the operation of the safety sensors

    Read the rest of this article »

    Posted on 12th June 2019

    HSE TO HELP DITCH ‘UNNECESSARY PAPERWORK’

    Board considers forthcoming HSE guidance on navigating H&S rules

    Read the rest of this article »

    Posted on 12th June 2019

    SCAFFOLDER DIED IN FALL THROUGH FRAGILE ROOF

    Contractor given prison term and main contractor fined

    Read the rest of this article »

    Posted on 12th June 2019

    ENERGY BUSINESS FINED OVER LIFTING FATALITY

    Firm failed to train in lorry mounted crane remote control risk

    Read the rest of this article »

    Posted on 12th June 2019

    MAJOR FIRM FINED £800K OVER LIFTING ERRORS

    Workman injured by falling heavy expanded polystyrene block

    Read the rest of this article »

    Posted on 7th June 2019

    NEW APPROACH TO HIGHWAYS HEALTH AND SAFETY

    Highways England launches ‘Home Safe and Well’ strategy

    Read the rest of this article »

    Posted on 5th June 2019
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic