• Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    HSE DEMOLITION INCIDENT CASE STUDIES

    Regulator advice focuses on underlying causes of recent demo incidents

    Twelve brief Case Studies on demolition incidents have been released by HSE which are reproduced below.

    The regulator is urging those involved in demolition projects to consider the scenarios and ask themselves if they could mitigate for these “common lapses in judgement or process”. If not, the HSE advice is to review their own processes with a particular focus on thorough planning, management and control of demolition and refurbishment work.

    The HSE initiative is prompted by the raised public profile of the demolition industry “by the recent airing of the Channel 5 documentary – When Demolitions Go Wrong, which has focused on the impact of incidents but not the underlying causes.”

    HSE has looked at the learning points from incidents that have occurred during demolition and significant refurbishment works and has collected the case studies which cover a range of incidents, some of which resulted in death or serious injury and others which could easily have led to single or multiple casualties.

    In all cases, even where there were no casualties, HSE stress that additional commercial costs often exceeded any potential saving resulting from shortcuts.

     

    DEMOLITION CASE STUDIES

     

    • Case Study 1 – Failure to provide sufficient pre-demolition information by client: A contract to demolish high rise residential blocks built of large precast panels used a ground based high reach demolition machine.  The client provided little information on the building structure to the contractor. Structural connection between panels had been poorly designed, poorly built and had deteriorated further during the life of the building.  Lack of adequate information (and lack of adequate survey or assessment prior to work starting) led to a premature collapse of multiple floors across several bays during demolition works. Fortunately, because the high reach machine was large enough, as was the exclusion zone, there were no injuries. However, the project was substantially delayed while the incident was investigated, and remedial action taken.  This type of building often needs panel connections to be stiffened and floors propped to a formal design prior to demolition.
    • Case Study 2 – Contractor competence. Basement extension work poorly designed and executed: A community building used daily by a local playgroup had a new basement dug out by tunnelling underneath the building across the full perimeter.  Support was provided by a couple of Acrows and the sides of the excavation were not shored up while underpinning was carried out in stages.  The contractor believed he was working in solid rock but in reality, it was loose shale.  Emergency works to prop the cavern and save the building made further work extremely difficult.  This caused the contractor to go out of business.  All excavations and especially where they are beneath or close to existing structures need to be meticulously designed and carried out which allows the cost of temporary works to be factored in and understood from an early stage.
    • Case Study 3 – Contractor competence. Approved sequence not followed causing collapse: The method statement for construction of a rear extension called for a new strip concrete foundation along the full length of the existing property to be installed in 1 metre sections, to avoid undermining existing foundations.  The builder decided it would be quicker to dig the full length of the trench in one go.  The existing building collapsed into the excavation injuring several workers.  The method statement should have been followed but other types of foundation could have been considered – including short bored piles or pads and a ground level ring beam.
    • Case Study 4 – Failure to correctly assess existing structure: Demolition workers assessed the form of construction of a single storey, concrete slab roofed building on the hoof and decided that because the soffit was flat and unjointed that the roof must have been cast in-situ and would be reinforced in both directions.  They punched a hole in one wall for plant access and were working inside when several of the precast, reinforced concrete roof planks hinged down killing one of them.  The punched hole had removed its bearing.  The soffit was smooth because it had been plastered with grey gypsum and the roof felting masked the upper surface.  Simple further checks and clues would have revealed the form of construction.  Cast in-situ slabs are not necessarily fully reinforced in both directions and in some cases suspended slabs are not reinforced at all.  Simple equipment is available to check for the presence and direction of steel reinforcement.  Safe intrusive methods of checking are also available – such as core drilling or limited breakout – e.g. from a tower scaffold.  Where possible, machine demolition from the ground and an exclusion zone is preferred and where this isn’t possible designed back-propping could have reduced the risk of wholesale failure.
    • Case Study 5 – Temporary load on existing structure not assessed: Demolition temporary works design considered mobile plant loadings on suspended reinforced concrete floor slabs but did not consider the rubble ramps that the contractor intended to use to allow plant to track down onto each floor in turn.  The contractor didn’t realise the rubble ramp hadn’t been assessed.  The floor became overloaded and collapsed progressively taking out floors below resulting in fatal and major injuries.  Had the task been fully assessed the need for back-propping or floor to floor transfer by crane would have been obvious.
    • Case Study 6 – Failure to consider implications of removing cross walls: A large brick building was being converted into flats. Neither the designer nor the contractor considered the effect of proposed alterations to the existing structure.  All internal walls and floors were removed in one go leaving the brick shell and roof in place.  The internal cross walls and floor joists had been providing support to the external walls which were now too long to resist wind loading without movement.  The building collapsed while the site was closed and before new walls and floors could be installed.  The permanent works designer should have considered the effect of necessary demolition work.  In some cases, designing a phased sequence of installing new walls and floors before removing old ones can be used to ensure stability is maintained throughout the process.  An alternative approach is formal design and early installation of extensive temporary works to provide support.
    • Case Study 7 – Support provided by non-loadbearing elements: All structural works on a masonry building were stopped due to concern about its stability.  The contractor took out some window frames they thought were non-structural.  These were providing sufficient fortuitous support to hold up a gable wall which collapsed causing other parts of the building to collapse.  Several were killed and injured.  Older buildings may need a designed internal and/or external structural scaffold or steel frame to hold them up while structural refurbishment is carried out.
    • Case Study 8 – Load bearing elements removed during soft strip: Timber sheathing panels were removed during soft stripping of a single storey timber frame school building that was being demolished.  The building, including the roof collapsed onto workers who were still inside.  No one had checked or realised that the plywood panels were structural and were bracing the timber frame.  Once they were removed the building was no longer stable.  Fortunately, only minor injuries resulted.  A proper survey of the structure would have identified the form of construction and the lack of separate bracing.
    • Case Study 9 – Agreed sequence not followed causing scaffold collapse: A large sheeted scaffold screen incorporating access platforms was designed and erected to encase a building.  The sheeting prevented dust and debris falling into surrounding public areas while the building was demolished floor by floor by small excavators.  The scaffold was supposed to be dismantled progressively as each floor was demolished.  It was not.  The wind got up and the sail effect overloaded ties into the remains of the building.  These failed and the scaffold collapsed onto a town centre public road.  Fortunately, the Fire Service had been called to reports of the scaffold moving and had been able to evacuate the area so there were no casualties.  Demolition work should have been halted at the right stage until the scaffold contractor had attended to reduce the height of the scaffold.
    • Case Study 10 – Existing structure overloaded by removed materials: A refurbishment contractor created openings in internal walls to a prepared design but stored the bricks on a suspended timber floor for reuse.  The floor became overloaded and collapsed injuring several workers.  In some instances, materials can be stored close to point of use in order to minimise manual handling.  In other situations, this can overload the structure.  A temporary works engineer would have been able to advise on how much load the floor could take and how to place load to minimise risk.
    • Case Study 11 – Designer instructions not clear & contractor too keen: A building contractor was engaged to construct an extension to an occupied old people’s home.  The architect specified that foundations should be dug down to competent ground and then agreed with local Building Control.  The contractor tried to excavate foundation trenches but could not find competent ground, so he excavated an unsupported foundation pit with the intention of using formwork to create the strip foundation.  When he reached 4 metres depth he found competent ground.  His efforts to prop and stabilise a cast iron 250mm diameter live water main that he found at the edge of his excavation were somewhat haphazard but fortunately the main did not fail – if it had the existing building shallow foundations would have been washed out, adding to risk of rapid collapse of the occupied building.  The local water supplier discovered what was going on and the excavation was concrete filled as emergency works.  The architect should have been mindful that the building was occupied and given a clearer specification.  A soil survey could have been commissioned to check conditions which would have suggested a range of alternative foundation options – including bored mini piles or a raft.  Risk to residents, delays and high additional cost could have been avoided.
    • Case Study 12 – Unchecked change to system of work caused collapse: A cinema was being demolished and the workers decided to speed up the job by toppling long span roof trusses to the ground instead of lifting them down as per the method statement.  This caused a section of concrete roof slab to move and topple the upper masonry storey which in turn pushed the perimeter scaffold away from the building, so it overturned and fell across a high street.  Vehicles and members of the public were trapped beneath it. It stopped just short of a supermarket plate glass window completely blocking the road.  By sheer luck no fatalities or major injuries resulted.  The planned and designed sequence of work must always be followed unless changes are fully assessed and agreed by the design team.

    Latest Construction Health and Safety News

    CONTRACTOR FAILED TO REPLACE MISSING PROTECTION

    Painter and decorator fractured hip in fall from landing

    Read the rest of this article »

    Posted on 18th February 2020

    RISK OF DERMATITIS SUFFICIENT FOR PROSECUTION

    Company failed to implement controls and surveillance required by COSHH

    Read the rest of this article »

    Posted on 18th February 2020

    COSHH FAILINGS CAUSE ASTHMA AND PROVE COSTLY

    Uncontrolled exposure to isocyanates during paint spraying operations

    Read the rest of this article »

    Posted on 18th February 2020

    POLICE EMPLOYEE SHOCKED BY DATA CABLE WORK

    South Wales Force fined over electric shock from ceiling void cable

    Read the rest of this article »

    Posted on 18th February 2020

    COLLAPSE OF PUMP SET TRAPPED WORKMAN

    Unsafe system of work transferring from pallet to a raised platform

    Read the rest of this article »

    Posted on 18th February 2020

    MODIFIED PODIUM STEPS CAUSE FALL FROM HEIGHT

    Firm failed to select and correctly assemble with necessary training

    Read the rest of this article »

    Posted on 14th February 2020

    SCHOOL LACKED SAFE SYSTEM FOR ROOF RETRIEVAL

    Workman fell from roof whilst retrieving shoe of pupil

    Read the rest of this article »

    Posted on 11th February 2020

    ARM OF WORKMAN AMPUTATED IN CONVEYOR

    Major construction materials supplier fined heavily over unsafe system

    Read the rest of this article »

    Posted on 11th February 2020

    CONCRETE BLOCK PLANT GUARDING BREACHED

    Sections of machinery perimeter safety fencing missing for months

    Read the rest of this article »

    Posted on 11th February 2020

    FATAL FUEL TANK EXPLOSION DURING CUTTING

    Companies failed to meet known, established and clear standards

    Read the rest of this article »

    Posted on 10th February 2020

    FIRMS FINED HEAVILY OVER STUDENT FIRE RISK

    Senior fire officers found “blatant disregard” for law and resident safety

    Read the rest of this article »

    Posted on 3rd February 2020

    ROOFER SURVIVED OVER 6M FALL FROM ROOF EDGE

    Replacement of asbestos cement roof lacked proper planning

    Read the rest of this article »

    Posted on 3rd February 2020

    CLIENT & BUILDER ACCOUNT FOR ASBESTOS FAILINGS

    Asbestos survey identified ACMs which were removed without controls

    Read the rest of this article »

    Posted on 30th January 2020

    UNSAFE USE OF SKIP LIFTER CAUSED FATALITY

    Fork lift being lifted on to vehicle fell when winch wire failed under load

    Read the rest of this article »

    Posted on 30th January 2020

    HSE CONVICTIONS DATABASE LATEST UPDATE

    hselogo1View current online HSE register of prosecution convictions and notices

    Read the rest of this article »

    Posted on 30th January 2020

    OVERHEAD CABLE STRUCK BY TIPPER TRUCK

    Company failed to report strike to HSE and take action on earlier incident

    Read the rest of this article »

    Posted on 30th January 2020

    CAMBRIDGE COLLEGE ASBESTOS BLUNDERS

    Survey absent and asbestos awareness training not provided

    Read the rest of this article »

    Posted on 30th January 2020

    HSE TO OVERSEE NEW BUILDING SAFETY REGIME

    Government to deliver biggest change in building safety for a generation

    Read the rest of this article »

    Posted on 21st January 2020

    CONTRACTS MANAGER HANDED TWO YEAR PRISON TERM

    Safety fall arrest netting would have saved life of deceased workman

    Read the rest of this article »

    Posted on 15th January 2020

    WORKER FATALLY INJURED BY CONCRETE BEAM

    Lifting operation not properly planned, managed and supervised

    Read the rest of this article »

    Posted on 15th January 2020

    TREE FELLING OPERATIONS LACKED DEFINED COMMS

    Workman struck by falling tree inside “normal” exclusion zone

    Read the rest of this article »

    Posted on 14th January 2020

    CONTRACTOR ARRESTED OVER WELFARE FAILINGS

    Recalcitrant sole trader failed to attend court hearing

    Read the rest of this article »

    Posted on 14th January 2020

    MAJOR DEMOLITION CONTRACTOR FINED £500,000

    Collapse of concrete slab caused death of worker and excavator fall

    Read the rest of this article »

    Posted on 14th January 2020

    FALL FROM LADDER WHILST CARRYING BUCKET

    Contractor failed to provide basic safe lifting aids

    Read the rest of this article »

    Posted on 14th January 2020

    FAILURE TO COMPLY WITH HSE NOTICE PROVES COSTLY

    Director given suspended jail term and company fined £60,000

    Read the rest of this article »

    Posted on 14th January 2020
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data