    CDM 2015 PRINCIPAL DESIGNER FINED OVER FIRE RISK

    PD and PC failed to comply with CDM 2015 responsibilities

    A Principal Designer and Principal Contractor have both been sentenced after serious breaches of their health and safety duties under CDM 2015 in 2016.

    Exeter Magistrates heard that concern was raised about the lack of health and safety controls on a large timber frame extension project at a residential home in Exmouth.

    HSE inspectors visited the site and found numerous health and safety breaches including:

    • Risk – uncontrolled high-risk activities putting workers at risk of death, serious injuries or ill health including falls from height, fire, slips and trips and poorly controlled wood dust.
    • Management – a “total disregard” for health and safety and site management; and
    • Fire – risk of fire spread associated with the construction of a timber frame extension adjoining an existing building where physically and/or mentally impaired residents of the home were put at risk of injury or death due to the possibility of fire spreading into the home.

    Further HSE investigation revealed that the work was not properly planned, nor appropriately supervised or carried out in a safe manner.

    Third party risk not considered

    The CDM Principal Contractor was required to control how the work was carried out and to ensure that the work would be completed safely. The CDM Principal Designer failed during the pre-construction phase to consider the risk of fire spread to the vulnerable nearby residents.

    • Coast & Country Construction Limited – of Concord Road, Exmouth did not attend court but were found guilty in their absence to breaching Section 2 (1) and 3 (1) of the Health and Safety at Work etc Act 1974, and have been fined £150,000 and ordered to pay costs of £6,039.
    • Paul Humphries Architects Ltd – of Salterton Road, Exmouth pleaded guilty to breaching Regulation 11 (1) and 11 (3) of the Construction (Design and Management) Regulations 2015, and have been fined £20,000 and ordered to pay costs of £6,039.

    CDM 2015 Regulation 11(1) requires that the PD must plan, manage and monitor the pre-construction phase and coordinate matters relating to health and safety during the pre-construction phase to ensure that, so far as is reasonably practicable, the project is carried out without risks to health or safety. In fulfilling this duty the PD must identify and eliminate or control foreseeable risks to the health or safety of any person carrying out or liable to be affected by construction work.

    Speaking after the hearing HSE inspector Nicole Buchanan said

    “Those in control of work have a responsibility to devise safe methods of working and to provide the necessary information, instruction and training to their workers in the safe system of working.

    Companies should be aware that HSE will not hesitate to take enforcement action against those that fail to control workplace risks appropriately.”

    Comment

    This prosecution will be added to the HSE online register of prosecution cases in 9 weeks time. The case is probably the first involving the prosecution of an appointed Principal Designer.

     

    Latest Construction Health and Safety News

    CHILD INJURED BY WALL COLLAPSE INCIDENT

    Council failed to carry out “intelligence led” condition inspections

    Read the rest of this article »

    Posted on 18th February 2019

    BOTTLE JACK SUPPORT FAILED TO PREVENT DEATH

    Director sentenced alongside company over death of engineer

    Read the rest of this article »

    Posted on 18th February 2019

    TEMPORARY WORKS FAILURES CAUSED FATAL FALL

    Platform not designed and system for installation and inspection inadequate

    Read the rest of this article »

    Posted on 18th February 2019

    SOLVENT IGNITED DURING FLOOR CLEANING WORKS

    Flammable solvent fire fought with water spreading fire further

    Read the rest of this article »

    Posted on 13th February 2019

    INEVITABLE COLLAPSE OF SCAFFOLD ON TO SCHOOL

    Scaffold not designed or installed to withstand foreseeable loads

    Read the rest of this article »

    Posted on 13th February 2019

    HSE ENFORCEMENT WEEKLY UPDATE 13th FEB 2019

    hselogo1Latest online register of prosecutions and enforcement notices

    Read the rest of this article »

    Posted on 13th February 2019

    OIL DRUM EXPLODED DURING HOT CUTTING WORK

    Firm fined £400k after drum lid ejected causing loss of leg

    Read the rest of this article »

    Posted on 12th February 2019

    ROOFLIGHT FALL ON NUCLEAR POWER SITE

    Energy generating company and maintenance contractor fined

    Read the rest of this article »

    Posted on 12th February 2019

    DIRECTOR PROSECUTED AFTER 6METRE ROOF FALL

    Untrained worker fell through rooflight in fragile asbestos roof

    Read the rest of this article »

    Posted on 12th February 2019

    HSE ALERT: MILD STEEL WELDING CANCER RISK

    HSE announces enforcement action change based on new cancer evidence

    Read the rest of this article »

    Posted on 11th February 2019

    LORRY MOUNTED LIFTING OPERATION PROVED FATAL

    Steel staircase toppled from vehicle after sling snagged

    Read the rest of this article »

    Posted on 7th February 2019

    DIRECTOR AND BUSINESS IN COURT OVER DEATH

    Scaffold not priced for on domestic roof-line refurbishment work

    Read the rest of this article »

    Posted on 6th February 2019

    FRAGILE ROOFLIGHT HAZARD PROTECTION MISSING

    Two businesses prosecuted after a worker fell through a fragile rooflight

    Read the rest of this article »

    Posted on 5th February 2019

    STRUCTURAL SAFETY BODY LATEST NEWSLETTER

    CROSS publishes reports and expert comment on a range of issues

    Read the rest of this article »

    Posted on 4th February 2019

    FINGERS CRUSHED BY METAL FOLDING MACHINE

    Steel cladding firm fined £600k over failure guard access to danger

    Read the rest of this article »

    Posted on 4th February 2019

    ASBESTOS ILLEGALLY REMOVED AFTER SURVEY

    Surveyor pricing asbestos work found contractor jumped the gun

    Read the rest of this article »

    Posted on 4th February 2019

    SITE DUMPER PRECAUTIONS FAILED TO PREVENT DEATH

    Contractor fined £600k for poor management of vehicle/people interface

    Read the rest of this article »

    Posted on 4th February 2019

    BUILDER EXPOSED RESIDENTS TO POISONING HAZARD

    Prison term for builder who put three at risk from carbon monoxide

    Read the rest of this article »

    Posted on 4th February 2019

    POOR SEPARATION OF VEHICLES AND PEDESTRIANS

    Logistics company fined £150,000 after driver suffers serious injuries

    Read the rest of this article »

    Posted on 4th February 2019

    £1MILLION FINE OVER VEHICLE RISK MANAGEMENT

    Death of workman exposed uncontrolled vehicle manoeuvring

    Read the rest of this article »

    Posted on 25th January 2019

    ACCREDITATION IS ONLY ONE WAY TO CONFIDENCE

    HSE publishes guidance on demonstrating CDM 2015 competence

    Read the rest of this article »

    Posted on 24th January 2019

    PRECAUTIONS ON PAPER LACKING IN PRACTICE

    Fatal fall through opening in concrete slab during work with breaker

    Read the rest of this article »

    Posted on 24th January 2019

    HSE TARGETS HEALTH ON LONDON PROJECTS

    Regulator starts inspection ‘blitz’ on construction sites

    Read the rest of this article »

    Posted on 23rd January 2019

    WORKMAN FELL FROM UNSECURED LADDER

    Industrial cladding company failed to assess and control WAH

    Read the rest of this article »

    Posted on 18th January 2019

    SCAFFOLDER FELL THROUGH FRAGILE ROOFLIGHT

    Fall through roof leaves workman with life-changing injuries

    Read the rest of this article »

    Posted on 18th January 2019
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic