    HSE HIGHLIGHT CROSSRAIL H&S INNOVATION

    Drilling rig improved control of three key health hazards

    HSE has shared a case study on how Crossrail’s used an innovative approach to provide a safe and healthy working environment for drill operatives.

    The Crossrail team recognised early on in the project that innovation and the use and development of new technology had the potential to manage the risks posed by such a project.

    Championing innovation from the top of the organisation was instrumental to the changes they wanted to make and funding was provided. Everyone was involved and encouraged to bring forward new and innovative ideas.

    See the Crossrail Learning Legacy Website for further details health and safety innovation on the project.

    Vibration, manual handling and silica dust reduced

    Crossrail faced the challenge of fitting of supporting bracketry for the electrical cable management systems, overhead power and firefighting systems within the railway tunnel environment which required the drilling of some 250,000 holes.

    A bespoke automated drilling rig was developed, which provided multiple drilling points to create service connection holes. The rig improved productivity and reduced the risk from hand arm vibration, manual handling and exposure to respirable crystalline silica (RCS) dust.

    The rig was designed and constructed to be capable of drilling 16 holes at a time, working through 250 metres of tunnel on each shift. Supporting data suggests that undertaking the same operation manually would complete some 30 metres a shift.

    HSE commented that:

    “This equipment was a wonderful example of collaborative working across the Crossrail project environment, linking client, designers and contractor’s delivery teams, who contributed valuable time and resources into making the rig a success.

    There is no doubt that the process and schedule benefits will provide some element of commercial saving but the relevance in terms of improving health and safety in the workplace provided the inspiration for engineers on the project and we hope can inspire others in the future to demonstrate that innovative thinking can effectively align health, safety, cost and schedule benefits.”

     

    Latest Construction Health and Safety News

    CONCRETE EJECTED BY PUMPING UNIT CLAIMED LIFE

    Company and director failed to train and supervise pumping operations

    Read the rest of this article »

    Posted on 5th December 2018

    HSE ENFORCEMENT WEEKLY UPDATE 5th DEC 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 5th December 2018

    REFRESHED GUIDANCE ON FITNESS TO OPERATE PLANT

    Construction plant medical fitness Good Practice Guide

    Read the rest of this article »

    Posted on 4th December 2018

    MAJOR CONTRACTOR & LUL USED UNSAFE SYSTEM

    Work method to eliminate moving vehicle hazard not adopted

    Read the rest of this article »

    Posted on 4th December 2018

    OVERTURNING LORRY CAUSED DEATH OF DRIVER

    Groundworks project stockpiling arrangements not properly managed

    Read the rest of this article »

    Posted on 3rd December 2018

    FORTH BRIDGE LIFTING OPERATION NOT PLANNED

    Major project PC failed to plan, supervise and carry out lift safely

    Read the rest of this article »

    Posted on 3rd December 2018

    DEVELOPER FAILED ON ASBESTOS ASSESSMENT

    HSE inspection revealed refurb works without asbestos survey

    Read the rest of this article »

    Posted on 28th November 2018

    POST DRIVER HAMMER CRUSHED HAND OF WORKMAN

    Unsafe system of work for vehicle crash barrier installation

    Read the rest of this article »

    Posted on 28th November 2018

    WORKER FELL FROM LOFT THROUGH CEILING

    Major house builder lacked understanding of loft fragile surfaces risk

    Read the rest of this article »

    Posted on 28th November 2018

    NEW SITE DUMPER SAFETY GUIDANCE ISSUED

    Construction plant sector concerns prompts CPA consults on draft

    Read the rest of this article »

    Posted on 28th November 2018

    CCTV INSTALLER FELL THROUGH FRAGILE ROOFLIGHT

    Contractor failed to properly plan and control the risks

    Read the rest of this article »

    Posted on 28th November 2018

    VISITOR DIED FALLING INTO CONCEALED BASEMENT

    Contractor failed to protect basement void on domestic project

    Read the rest of this article »

    Posted on 28th November 2018

    RACKING FALL REVEALED UNSAFE SYSTEM OF WORK

    European firm fined £300,000 after UK sub-contractor employee fell

    Read the rest of this article »

    Posted on 18th November 2018

    FAILURE TO ACT ON VIBRATION AND SILICA HAZARDS

    Worker health put at risk during stripping of furnace lining

    Read the rest of this article »

    Posted on 18th November 2018

    MAJOR FM FIRM FAILED TO MAINTAIN BACK-UP POWER

    Power loss at laboratory site created potential risk from biological agents

    Read the rest of this article »

    Posted on 18th November 2018

    IGNORING HSE PROHIBITIONS COST FIRM £250,000

    CDM 2015 and work at height requirements repeatedly breached

    Read the rest of this article »

    Posted on 16th November 2018

    ROOF COLLAPSED UNDER EXCESS LOADING

    Director and company fined over roof design failures

    Read the rest of this article »

    Posted on 11th November 2018

    FORK LIFT OVERTURNED IN SCAFFOLDING YARD

    Untrained operator suffered life changing crush injuries

    Read the rest of this article »

    Posted on 10th November 2018

    STRUCTURAL SAFETY ALERT: EFFECTS OF SCALE

    SCOSS issues alert after concerns disclosed over ‘large structures’

    Read the rest of this article »

    Posted on 7th November 2018

    ASBESTOS EXPOSED BY UNTRAINED WORKERS

    Contractor failed to act properly despite HSE intervention

    Read the rest of this article »

    Posted on 7th November 2018

    GAS MAIN STRIKE REPAIR CAUSED SEVERE BURNS

    Contractor excavator damage to gas pipe ends in £1.2m fine

    Read the rest of this article »

    Posted on 7th November 2018

    REBAR FELL FROM FLT IN UNSAFE LIFTING OPERATION

    Multiple fractures caused by inappropriate use of fork lift

    Read the rest of this article »

    Posted on 7th November 2018

    POORLY PLANNED LIFT DISMANTLE INJURED WORKMAN

    Counterweight or suspension rope struck worker in lift shaft

    Read the rest of this article »

    Posted on 1st November 2018

    CONSTRUCTION INJURY AND ILL-HEALTH 2017/18

    hselogo1Fatal injury rate in long term decline whilst ill-health trend flat lining

    Read the rest of this article »

    Posted on 1st November 2018

    DUMPER DRIVEN INTO OPEN UNGUARDED EXCAVATION

    Contractor fined over absence of suitable excavation / dumper precautions

    Read the rest of this article »

    Posted on 1st November 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic