    FALL ON BLOCK AND BEAM FLOORING SYSTEM

    Contractors failed to respond to planned fall protection problems

    A District Judge at Leeds Magistrates’ Court has heard how, on 13 March 2013, an employee of contractor Rhino Precast Ltd. was laying a concrete block and beam floor to a new mezzanine level. Whilst the workman was carrying out this work he fell through to the floor below, breaking his tibia and fibula.

    HSE investigators found the contractor failed to adequately plan the work and had continued to work on site after it became clear the fall protection provided could not be deployed.

    Basic planning and safeguards not in place

    The investigation also found that principal contractor, DD Porter Limited, failed to plan, manage and monitor the work. Both companies were prosecuted and sentenced as follows:

    • Rhino Precast Ltd – of Ossett, West Yorkshire pleaded guilty to breaching Regulation 4(1) of the Work at Height Regulations 2005. The company was fined £33,750 and ordered to pay costs of £2,758.00.
    • DD Porter Limited – of Halifax, West Yorkshire pleaded guilty to breaching Regulation 22(1) of The Construction (Design & Management) Regulations 2007. The company was fined £100,000 and ordered to pay costs of £2,575.20.

    Speaking after the hearing, HSE inspector Neil Hope-Collins said:

    “Falls from height remain one of the most common causes of work related fatalities in this country and the risks associated with working at height are well-known.

    This serious incident could have been avoided if basic planning and safe guards had been put in place and it highlights the importance of the principal contractor in both the planning process and in monitoring the work being carried out.

    Companies should be aware that HSE will not hesitate to take appropriate enforcement action against those that fall below the required standards.”

    Latest Construction Health and Safety News

    HSE ENFORCEMENT WEEKLY UPDATE 25th SEPT 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 25th September 2018

    HSE SEEKS CONSTRUCTION ‘DUST BUSTER’ PARTNERS

    Regulator uses social media to raise dust dangers and using right controls

    Read the rest of this article »

    Posted on 24th September 2018

    MAJOR HOMES BUSINESS EXPOSED PUBLIC TO RISK

    Residential property refurb project created carbon monoxide danger

    Read the rest of this article »

    Posted on 24th September 2018

    HSE CONSTRUCTION DUST CONTROL ‘BLITZ’ STARTS

    Regulator inspections will check health taken as seriously as safety

    Read the rest of this article »

    Posted on 20th September 2018

    FLOOR CONSTRUCTION SYSTEM OF WORK UNSAFE

    Welder fell 3m from mezzanine area through purlin openings

    Read the rest of this article »

    Posted on 20th September 2018

    WORKER SUFFERS FATAL BURNS IN OXYGEN RICH AREA

    Sparks from angle grinder ignited clothing of workman in confined space

    Read the rest of this article »

    Posted on 19th September 2018

    RIBA PUBLISH DRAFT POST GRENFELL FIRE SAFETY PLAN

    Architects institute consults on ‘golden thread of fire safety information’

    Read the rest of this article »

    Posted on 19th September 2018

    MAJOR UK CONTRACTORS HIT BY MAJOR FINES

    Firms ordered to pay over £3m after foot trapped in rotating ‘screw’

    Read the rest of this article »

    Posted on 19th September 2018

    DRIVER DIED TRAPPED BETWEEN TRAILER AND VEHICLE

    Firm fined £1.5 million over failure to assess coupling operations

    Read the rest of this article »

    Posted on 14th September 2018

    ACTUAL SYSTEM OF WORK WAS OPPOSITE OF RAMS

    Workman fell 4m through fragile asbestos roof sheet

    Read the rest of this article »

    Posted on 13th September 2018

    CDM PRINCIPAL DESIGNER FUNCTION MISUNDERSTOOD?

    Consultants claim CDM 2015 design risk management has ‘gone backwards’

    Read the rest of this article »

    Posted on 8th September 2018

    RISK ASSESSED PRECAUTIONS NOT IMPLEMENTED

    Action not paperwork essential to prevent fall during lifting operation

    Read the rest of this article »

    Posted on 7th September 2018

    CROSSRAIL PUBLISH BEST PRACTICE H&S GUIDES

    Sharing major project best practice can leave a lasting legacy

    Read the rest of this article »

    Posted on 5th September 2018

    SCHOOL STAFF LACKED ASBESTOS AWARENESS TRAINING

    Council fined £200k over asbestos flue and gasket rope failures

    Read the rest of this article »

    Posted on 5th September 2018

    INCIDENT: MEWP OVERTURN IN CITY CENTRE

    Images show aftermath of mobile elevating platform collapse

    Read the rest of this article »

    Posted on 5th September 2018

    SAFETY ALERT: DEFECTIVE SCAFFOLD COUPLER

    National Access and Scaffolding Confederation issues warning

    Read the rest of this article »

    Posted on 31st August 2018

    DEMOLISHING INTERNAL WALL REVEALED ASBESTOS

    Firm lacked survey and asbestos management plan for premises

    Read the rest of this article »

    Posted on 31st August 2018

    NEW HEALTH AND SAFETY TEST FOR ARCHITECTS

    RIBA raise the bar for members on design risk management and ‘life safety’

    Read the rest of this article »

    Posted on 31st August 2018

    POWER BUSINESSES FAILED ON LIFTING OPERATION

    Panel fell on workman during turbine maintenance project

    Read the rest of this article »

    Posted on 31st August 2018

    MAJOR INFRASTRUCTURE FIRM COMMITS TO ZERO HARM

    Behaviours to deliver zero lost time injury incident rate by 2021

    Read the rest of this article »

    Posted on 31st August 2018

    MANAGING TOWER CRANE FALLING OBJECT RISK

    CPA issues new technical information note

    Read the rest of this article »

    Posted on 31st August 2018

    POST EXPLOSION ASBESTOS WORK WAS UNSAFE

    Asbestos cement panels removed and cut with power tools

    Read the rest of this article »

    Posted on 31st August 2018

    FALL THROUGH UNFLOORED FACTORY ROOF SPACE

    Non-routine tasks require assessment and clear risk controls

    Read the rest of this article »

    Posted on 31st August 2018

    SEVENTH LONDON CYCLIST DEATH DURING 2018

    Building products vehicle involved in death of Queens doctor

    Read the rest of this article »

    Posted on 17th August 2018

    MAJOR CONTRACTOR FAILED TO SUPERVISE LIFT

    Errors whilst lifting pre-cast concrete blocks fined £600,000

    Read the rest of this article »

    Posted on 14th August 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic