• Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    CDM REGULATIONS 2015: TEMPORARY WORKS PD GUIDE

    New industry guidance for CDM project Principal Designers

    The Temporary Works Forum (TWf) has published new guidance on the role of the CDM 2015 Principal Designer with respect to temporary works see below.

    Businesses undertaking temporary works design are covered by the definition of ‘designer’ under CDM 2015. The business appointed Principal Designer (PD) must ensure that all other designers comply with their CDM 2015.

    The PD must also ensure cooperation between designers (both permanent and temporary works) and the PD role continues into the construction phase when design work is carried out.

    The TWf believes that many designers may be more familiar with permanent works design issues than temporary works. The new Information Sheet seeks to provide guidance which it hopes will prove useful to Principal Designers and the wider UK construction industry.

     

     

    HSE Explanation of what TW includes:

    Temporary works is a widely used expression in the construction industry for an “engineered solution” used to support or protect an existing structure or the permanent works during construction, or to support an item of plant or equipment, or the vertical sides or side-slopes of an excavation, or to provide access. The construction of most types of permanent works will require the use of some form of temporary works.

    Temporary works is defined in BS5975: 2008 “Code of practice for temporary works procedures and the permissible stress design of falsework” as “(those) parts of the works that allow or enable construction of, protect, support or provide access to, the permanent works and which might or might not remain in place at the completion of the works”.

    Examples of temporary works include, but are not limited to:

    Earthworks – trenches, excavations, temporary slopes and stockpiles. Structures – formwork, falsework, propping, façade retention, needling, shoring, edge protection, scaffolding, temporary bridges, site hoarding and signage, site fencing, cofferdams.

    Equipment/plant foundations – tower crane bases, supports, anchors and ties for construction hoists and mast climbing work platforms (MCWPs), groundworks to provide suitable locations for plant erection, e.g. mobile cranes and piling rigs. Further information on temporary works design principles and the consequences and causes of failure are set out in Appendix 1.”

     

    Latest Construction Health and Safety News

    DEATH EXPOSED MINIMAL MEWP MAINTENANCE

    Court told about “almost complete” lack of MEWP maintenance

    Read the rest of this article »

    Posted on 21st June 2018

    CONTRACTOR FAILED TO IDENTIFY ASBESTOS PRESENCE

    ACMs disturbed during works and firm failed to take suitable actions

    Read the rest of this article »

    Posted on 21st June 2018

    FALL THROUGH ROOF ON LOCAL COUNCIL BUILDING

    Fragile rooflight fractured when workman ‘misplaced footing’

    Read the rest of this article »

    Posted on 21st June 2018

    YOUNG WORKER POSED SPECIAL RISK TO CONTROL

    Conviction highlights duty to young persons and the vulnerable

    Read the rest of this article »

    Posted on 21st June 2018

    TOWER DEFECTS AND UNSAFE SYSTEM CAUSED DEATH

    Maintenance supervisor fell to his death through roof opening

    Read the rest of this article »

    Posted on 21st June 2018

    UK MAJOR FINED £1/2m OVER HAVS RISK FAILURES

    Danger caused by poor management of vibrating hand tool risk

    Read the rest of this article »

    Posted on 21st June 2018

    HSE ENFORCEMENT WEEKLY UPDATE 20th JUNE 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 20th June 2018

    DIRECTOR FAILED COMPLY WITH HSE PROHIBITION

    Precautions not taken to prevent excavation collapse and falling

    Read the rest of this article »

    Posted on 11th June 2018

    SCAFFOLD NOT TO INDUSTRY STANDARD OR DESIGN

    Specialist and contractor in court over unsafe work at height

    Read the rest of this article »

    Posted on 7th June 2018

    ROAD WORKER RUN OVER BY ROAD ROLLER

    Reversing alarm not working and warning light not fitted

    Read the rest of this article »

    Posted on 5th June 2018

    CLIENT AND SURVEYOR FINED OVER ASBESTOS SURVEY

    Refurbishment and demolition asbestos survey proved inadequate

    Read the rest of this article »

    Posted on 5th June 2018

    FATALITY: ROAD WORKER DRAGGED ALONG ROAD

    Night shift worker loses life when struck by road sweeping vehicle

    Read the rest of this article »

    Posted on 3rd June 2018

    CDM PRINCIPAL DESIGNERS AVOID HSE ENFORCEMENT

    Regulator enforcement database reveals few notices involve CDM PDs

    Read the rest of this article »

    Posted on 3rd June 2018

    PROPERTY MANAGERS FINED WITH CONTRACTOR

    Defendants failed to check for asbestos during soffit replacement works

    Read the rest of this article »

    Posted on 29th May 2018

    EXCAVATION CAUSED RETAINING WALL COLLAPSE

    Precautions not taken to secure stability of free-standing wall

    Read the rest of this article »

    Posted on 29th May 2018

    OVERHEAD CABLE STRIKE FIRM FINED £500,000+

    Inadequate system caused risk of harm despite lack of worker injury

    Read the rest of this article »

    Posted on 29th May 2018

    CDM 2015 PRINCIPAL DESIGNER FINED OVER FIRE RISK

    PD and PC failed to comply with CDM 2015 responsibilities

    Read the rest of this article »

    Posted on 23rd May 2018

    SENTENCING GUIDELINES UNDER THE MICROSCOPE

    Lawyer argues guidelines undermine reduction in ‘regulatory burden’

    Read the rest of this article »

    Posted on 23rd May 2018

    PANEL STRUCK WORKMAN DURING LIFTING OPERATION

    Third party contractor falls victim of poor lift planning

    Read the rest of this article »

    Posted on 21st May 2018

    DIRECTOR LED HAZARDOUS WORK AT HEIGHT

    Three occasions when work lacked suitable and sufficient precautions

    Read the rest of this article »

    Posted on 21st May 2018

    RISK ASSESSED BUT CONTROLS FOUND WANTING

    Joiner fell through unprotected opening on roof of new building

    Read the rest of this article »

    Posted on 21st May 2018

    RIBA CRITICAL OF HACKITT REVIEW FINAL REPORT

    High rise residential review dismissed as “major missed opportunity”

    Read the rest of this article »

    Posted on 21st May 2018

    CONSTRUCTION SECTOR DEATHS: THE ‘BIG THREE’

    HSE in-year fatalities for 2017/18 may indicate upward trend

    Read the rest of this article »

    Posted on 16th May 2018

    SCAFFOLDING SITE ACCIDENTS AT RECORD LOW

    NASC Annual Report reveals all time low in 2017 incidents

    Read the rest of this article »

    Posted on 14th May 2018

    DUMPER TRUCK HAND-BRAKE NOT MAINTAINED

    Workman injured when pinned against stack of concrete blocks

    Read the rest of this article »

    Posted on 14th May 2018
    Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data