    HSE INVOICE OVER £4M IN FEES FROM CONSTRUCTION

    hselogo1Inspection charges rise by 26% whilst HSE enforcement notices fall

    Information requested from the HSE Fee for Intervention (FFI) team has revealed that the total value of FFI invoices issued in the construction sector has increased by over a quarter (26%) during the last 12 months of recorded data.

    The HSE Enforcement Database shows that during the same period the number of Enforcement Notices issued by HSE construction sector groups has fallen by 13%.

    Notices of Contravention

    HSE issue invoices following a written Notice of Contravention sent to duty holders regarding ‘material breaches’ of the law found by HSE inspectors. We have analysed the HSE invoice data on the basis of the last three full year invoice ‘runs’ as follows:

    April 2013 – March 2014 – 6960 invoices issued with a total value of £2,545,474. The average value of invoices issued is £366.

    April 2014 – March 2015 – 6075 invoices issued with a total value of £3,1116,234. This represents a 21% increase in the total value of invoices issued over the previous period. The average value of invoices issued is £513 representing a 29% increase.

    April 2015 – March 2016 – 6990 invoices issued with a total value of £4,220,972. This represents a 26% increase in the total value of invoices issued over the previous period. The average value of invoices issued is £604 representing 15% increase.

    The data show that both total invoice value and average invoice value in the construction sector have increased significantly since April 2013.

    Enforcement Notices

    We have interrogated the HSE Enforcement Notices database over the same period which shows that the number of enforcement notices issued in the construction sector has fallen.

    April 2013 – March 2014 – the database shows 3625 prohibition and improvement notices issued by HSE construction teams.

    April 2014 – March 2015 – the database shows 3244 prohibition and improvement notices issued by HSE construction teams. This represents a 11% fall in the number of notices issued.

    April 2015 – March 2016 – the database shows 2713 prohibition and improvement notices issued by HSE construction teams. This represents a 13% fall in the number of notices issued.

    Comment

    The data suggest that the HSE Notice of Contravention and consequent inspection fee forms an increasingly important mechanism for HSE in securing compliance and improved standards of health and safety in the construction sector.

    This is occurring at a time when use of formal Enforcement Notices (improvement and prohibition) is declining in the sector.

    It is possible that many dutyholders may find this development preferable. Notices of contravention and the FFI invoice data is not published in respect of individual organisations. However, details of the HSE enforcement notices served on specific duty holders is published on the HSE website, can be viewed by potential clients and used in contractor selection processes.

    Latest Construction Health and Safety News

    CONSTRUCTION SAFETY NEWS – END OF NEW CONTENT

    The addition of content on this website ceased on 17th April 2020.

    Material posted before this date can be found by clicking on our SEARCH NEWS DATABASE function.

    Posted on 3rd May 2020

    HSE WARN OF NEED FOR RPE FACE FIT TEST AND CHECK

    Incorrectly fitted RPE will not protect the wearer from dangers to health

    Read the rest of this article »

    Posted on 16th April 2020

    CORONA VIRUS: LATEST SITE OPERATING PROCEDURES

    Industry Bodies publish risk management guidance Version 3

    Read the rest of this article »

    Posted on 15th April 2020

    TOWER CRANE OUT OF SERVICE SAFETY ALERT

    Important advice from Construction Plant-hire Association and HSE

    Read the rest of this article »

    Posted on 30th March 2020

    FRAGILE ROOF REPLACEMENT PUT WORKERS IN DANGER

    Measures to prevent falling from or through the roof were missing

    Read the rest of this article »

    Posted on 30th March 2020

    WORKMAN FELL FROM EDGE OF MEZZANINE FLOOR

    Edge protection was absent and workman untrained for the task

    Read the rest of this article »

    Posted on 30th March 2020

    HSE PLAN AND CONSTRUCTION PRIORITIES 2020/21

    Appointed CDM 2015 Principal Designers remain focus of HSE inspections

    Read the rest of this article »

    Posted on 30th March 2020

    COVID-19 ADVICE & GUIDANCE FOR CONSTRUCTION

    BuildUK support industry with advice, guidance and information

    Read the rest of this article »

    Posted on 30th March 2020

    LATEST HSE CONVICTIONS AND NOTICES REGISTERS

    hselogo1View current online HSE registers of prosecution convictions and notices

    Read the rest of this article »

    Posted on 30th March 2020

    POORLY DESIGNED SCHOOL GATE CRUSHED CHILD

    Sliding gate over-run mechanism proved insufficiently robust

    Read the rest of this article »

    Posted on 9th March 2020

    POWER GENERATOR PROSECUTED OVER UNSAFE SYSTEM

    Maintenance workers seriously injured when energy suddenly released

    Read the rest of this article »

    Posted on 2nd March 2020

    CEILING BELOW SAVES WORKMAN IN ROOFLIGHT FALL

    Roofworker fell through roof after stepping on fragile rooflight

    Read the rest of this article »

    Posted on 2nd March 2020

    INEXPERIENCED WORKER FELL THROUGH OPENING

    No physical protection or warning of opening and fragile covering

    Read the rest of this article »

    Posted on 29th February 2020

    CDM PRINCIPAL DESIGNER IN COURT OVER FIRE RISK

    Designers and contractor prosecuted for risk management failings

    Read the rest of this article »

    Posted on 29th February 2020

    PRISON SENTENCE FOR RECALCITRANT DIRECTOR

    Prohibition and improvement notices ignored and danger persisted

    Read the rest of this article »

    Posted on 26th February 2020

    TEMPORARY WORKS HOARDING FELL ON PEDESTRIAN

    Member of the public struck when site fence collapsed suddenly

    Read the rest of this article »

    Posted on 26th February 2020

    CHILD FATALLY INJURED BY UNSECURED POLE

    Pole stored on embankment moved and trapped boy against fencing

    Read the rest of this article »

    Posted on 26th February 2020

    OWNER RESPONSE TO HSE INSPECTION ENDED IN COURT

    Police uphold HSE right to inspect without threats, aggression or abuse

    Read the rest of this article »

    Posted on 24th February 2020

    HSE TARGETING WELDING FUME CANCER RISK

    Inspections to enforce improved controls required by new risk evidence

    Read the rest of this article »

    Posted on 24th February 2020

    CONTRACTOR FAILED TO REPLACE MISSING PROTECTION

    Painter and decorator fractured hip in fall from landing

    Read the rest of this article »

    Posted on 18th February 2020

    RISK OF DERMATITIS SUFFICIENT FOR PROSECUTION

    Company failed to implement controls and surveillance required by COSHH

    Read the rest of this article »

    Posted on 18th February 2020

    COSHH FAILINGS CAUSE ASTHMA AND PROVE COSTLY

    Uncontrolled exposure to isocyanates during paint spraying operations

    Read the rest of this article »

    Posted on 18th February 2020

    POLICE EMPLOYEE SHOCKED BY DATA CABLE WORK

    South Wales Force fined over electric shock from ceiling void cable

    Read the rest of this article »

    Posted on 18th February 2020

    COLLAPSE OF PUMP SET TRAPPED WORKMAN

    Unsafe system of work transferring from pallet to a raised platform

    Read the rest of this article »

    Posted on 18th February 2020

    MODIFIED PODIUM STEPS CAUSE FALL FROM HEIGHT

    Firm failed to select and correctly assemble with necessary training

    Read the rest of this article »

    Posted on 14th February 2020
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data