Turner Access Higher Safety Total Access
Total Access Ethentic Chipmunk Data
Chipmunk Data Turner Access Ethentic

CDM REGULATIONS 2015: RECORDING BY DESIGNERS

New guidance puts added emphasis on ‘significant risk’ information

The CDM Regulations 2015 made few changes to the substantive legal requirements placed on design organisations. When preparing or modifying designs the designer must eliminate, reduce and make risks easier to control.

The regulations and guidance are ‘light’ on what designers should record concerning these actions. There is no requirement in the regulations for a “design risk assessment” or “design risk register” although relevant information for inclusion in the pre-construction information or health and safety file must be passed to others.

Previous designer guidance remains relevant

The CDM 2007 ACOP contained some helpful words for designers considering what to record, namely:

“Designers are not legally required to keep records of the process through which they achieve a safe design, but it can be useful to record why certain key decisions were made. Brief records of the points considered, the conclusions reached, and the basis for those conclusions, can be very helpful when designs are passed from one designer to another. This will reduce the likelihood of important decisions being reversed by those who may not fully understand the implications of doing so”

The CDM 2007 ACOP went on to warn designers that:

“Too much paperwork is as bad as too little, because the useless hides the necessary. Large volumes of paperwork listing generic hazards and risks, most of which are well known to contractors and others who use the design are positively harmful, and suggest a lack of competence on the part of the designer.”

Until recently HSE also published Frequently Asked Questions for CDM Designers on the HSE Website. There is no reason why these FAQs should not be used to guide designers under CDM 2015.

Current guidance for designers

The HSE CDM 2015 Legal Guidance is less helpful on what to record and focuses more on what information should be provided to others.

The guidance states that designers must provide information to the Principal Designer and other dutyholders using or implementing the design about ‘significant risks’ associated with the design that cannot be eliminated. This information will form part of the pre-construction information.

Significant risks are defined as:

“not necessarily those that involve the greatest risks, but those (including health risks) that are not likely to be obvious, are unusual, or likely to be difficult to manage effectively”

Designers are advised to agree with the PD the arrangements for sharing information to avoid omissions or duplicated effort. Those who need the information should be given it at the right time. The CDM 2015 guidance goes on to add:

“Depending on the nature and extent of design work, there may be a need to carry out design reviews. Reviews enable the project team to focus on health and safety matters alongside other key aspects of the project.

This can be done as part of the normal design process. The need for such reviews is likely to continue throughout the project although their frequency and the level of detail covered should remain proportionate to the scale and complexity of the design work.”

CDM 2015 Information and Templates

See CDM 2015 Survey Results for the findings of our CDM 2015 Five Minute Online Survey.

We have published a great deal of further information and templates designed to support Clients, Designers, Principal Designers/Contractors and Contractors in meeting their duties under CDM Regulations 2015.

Latest Construction Health and Safety News

UPDATED SCAFFOLDING DESIGN E-GUIDE RELEASED

NASC launches enhanced TG20:13 eGuide scaffold design tool

Read the rest of this article »

Posted on 14th August 2017

NASC LAUNCH FREE TO DOWNLOAD GUIDANCE

Access and scaffolding guides now open to members and non-members

Read the rest of this article »

Posted on 14th August 2017

HSE ENFORCEMENT WEEKLY UPDATE 9th AUGUST 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 11th August 2017

NEW GUIDANCE ON UNINTENDED PLANT MOVEMENT

Industry Plant Safety Group highlights hazards and key control measures

Read the rest of this article »

Posted on 11th August 2017

SCAFFOLD COLLAPSE CAUSED BY LACK OF TIES

Falling structure narrowly misses passerby and lands on parked cars

Read the rest of this article »

Posted on 11th August 2017

HSE ENFORCEMENT WEEKLY UPDATE 2nd AUG 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 2nd August 2017

TRAINING IN CIRCULAR SAW USE FOUND WANTING

Joinery firm failures end in serious hand injury and £230,000 fine

Read the rest of this article »

Posted on 31st July 2017

HSE ENFORCEMENT WEEKLY UPDATE 26th JULY 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 31st July 2017

WALL COLLAPSE CLAIMED LIFE OF WORKMAN

Failed to identify risks associated with free standing walls

Read the rest of this article »

Posted on 31st July 2017

WORKMAN FELL DURING WELDING WORK AT HEIGHT

Ladder access to water tank top was insecure and slipped when used

Read the rest of this article »

Posted on 31st July 2017

CCTV INSTALLER FELL BETWEEN FLOOR JOISTS

Principal Contractor and CCTV specialist failed to plan and manage risk

Read the rest of this article »

Posted on 31st July 2017

FACTORY APPRENTICE FELL DURING GUTTER CLEANING

Young workman stepped back and fell 9m through fragile rooflight

Read the rest of this article »

Posted on 31st July 2017

CROSS RAIL JV CONTRACTORS FINED OVER FATALITY

Firm prosecuted after concrete fall death and two other tunnel incidents

Read the rest of this article »

Posted on 31st July 2017

CONTRACTORS FAILED TO REVIEW ASBESTOS SURVEY

Major companies fined £1,000,000 plus over asbestos risk during refurb

Read the rest of this article »

Posted on 31st July 2017

MAJOR CONTRACTORS LAUNCH H&S ALERT SYSTEM

Build UK members share information for effective prevention of harm

Read the rest of this article »

Posted on 19th July 2017

HSE ENFORCEMENT WEEKLY UPDATE 19th JULY 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 19th July 2017

STRUCTURAL SAFETY BODY LATEST NEWSLETTER

SCOSS publishes reports and expert comment on a range of issues

Read the rest of this article »

Posted on 18th July 2017

SAFE SYSTEM DEVISED BUT NOT IMPLEMENTED

Workman injured by goods falling from double-decked trailer

Read the rest of this article »

Posted on 18th July 2017

PREVENTION PLANNING REQUIRED FOR FRAGILE RISK

Fall arrest safety netting not used to mitigate fall consequences

Read the rest of this article »

Posted on 17th July 2017

MANAGEMENT OF FORMWORK NOT UP TO THE MARK

Erector fell 3m after access scaffold board failed under load

Read the rest of this article »

Posted on 17th July 2017

VIBRATION UNCONTROLLED & WORKERS UNINFORMED

Engineering firm fined £120,000 over hand-arm vibration risk

Read the rest of this article »

Posted on 14th July 2017

HSE ENFORCEMENT WEEKLY UPDATE 12th JULY 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 12th July 2017

SCAFFOLDER WAS UNTRAINED AND UNSUPERVISED

Contractor and director failed to train injured workman to CISRC scheme

Read the rest of this article »

Posted on 10th July 2017

WORKPLACE MANSLAUGHTER OUTCOMES SET TO RISE

Guidelines target gross negligence with serious disregard and cost-cutting

Read the rest of this article »

Posted on 7th July 2017

WORKMAN BURNT CLEANING WITH FLAMMABLE LIQUIDS

Flammable substance and unprotected electrical equipment trigger flash fire

Read the rest of this article »

Posted on 7th July 2017
Turner Access Chipmunk Data
Total Access Ethentic
Higher Safety Turner Access