Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    CDM REGULATIONS 2015: DESIGNER RISK AVOIDANCE

    What CDM 2015 designers must do when preparing or modifying designs

    On 6th April 2015 the primary duty and objective of designers under the CDM Regulations remains substantively unchanged namely to, eliminate, reduce or control risk through design. However, the duty will become more absolute and demanding in terms of the risk avoidance actions required.

    The CDM Regulation 2007 designer duty is qualified and allows the designer to take “due account of other relevant design considerations”. This critical qualification has been removed from CDM 2015 making it easier for the regulator to allege a ‘material breach’ of statute. This might thereby trigger a prosecution, enforcement notice or a Fee for Intervention invoice in respect of the designer.

    The qualification is partially reinstated in that the HSE CDM 2015 Legal Guidance refers to ‘other factors’ which may influence the design e.g. cost, fitness for purpose, aesthetics and environmental impact.

    However, the qualification, such as it is, is now relegated to Guidance status whereas breaches of law will be determined by reference to the wording of the Regulations and not the Guidance.

    More effort required using same means

    Does this really matter?

    The change may be important in terms of the degree of effort required to meet the objective (risk avoidance) but should have little impact on the means designers adopt to comply and avoid risk through design.

    The CDM 2007 Approved Code (ACOP) set out the actions required of designers. From 6th April 2015 this ACOP is withdrawn and replaced by the HSE Legal Guidance L153.

    The practical guidance for designers is included at paras 75-93 of L153 and the key points are set out below.

    Eliminating, reducing or controlling foreseeable risks through design

    When preparing or modifying designs, a designer must take account of the General Principles of Prevention, and the Pre-Construction Information, with the aim, as far as Reasonably Practicable, of eliminating foreseeable risks.

    Where this is not possible designers must take reasonably practicable steps to reduce the risks or control them through the design process, and provide information about the remaining risks to other dutyholders.

    HSE stress that designing is a process that often continues throughout the project and the following questions should be considered when design is carried out:

    • Can the problem (or hazard) be removed altogether? E.g. air con plant on a roof moved to ground level, so that work at height is not required for either installation or maintenance?;
    • How can risks be reduced or controlled so that harm is unlikely or the potential consequences less serious? E.g. place the air con plant within a building on the roof, or provide a barrier around the entire roof?

    If risks cannot be eliminated the designer should apply the principles below in deciding how to reduce or control the remaining risks – if possible, in the following order:

    1. Risk provide a less risky option e.g. switch to using components which are lighter in weight to reduce musculoskeletal disorders;
    2. Exposure – make provisions so that the work can be organised to reduce exposure to hazards e.g. provision for traffic routes so that barriers can be provided between pedestrians and traffic; and
    3. Information – ensure that those responsible for planning and managing the work are given the information needed to manage remaining risks e.g. information about loads that will be particularly heavy or elements of the building that could become unstable. This can be achieved through providing key information on drawings or within models e.g. Building Information Modelling (BIM).

    The designer is expected to do:

    “as much as is reasonable at the time the design is prepared. Hazards that cannot be addressed at the initial stage of a project may need to be reviewed later on during detailed design. On projects involving more than one contractor, the Principal Designer will lead in managing the review process. “

    General Principles of Prevention (GPP)

    The GPP provide the framework within which designers must consider their designs and any potential risks to health or safety which may affect workers, members of the public, those who may maintain or clean the building or use the building as a workplace.

    Designs prepared for places of work also need to comply with the Workplace (Health, Safety and Welfare) Regulations 1992 so designs need to take account of factors such as lighting and the layout of traffic routes.

    The HSE Guidance states at paras 83-84:

    “Health and safety risks need to be considered alongside other factors that influence the design such as cost, fitness for purpose, aesthetics and environmental impact. Working with contractors (including principal contractors) involved in the project can assist in identifying the potential risks and ways in which they may be controlled.

    Once the risks have been considered and taken into account, the level of detail in the information provided to those who need it should be proportionate to the risks remaining. Insignificant risks can usually be ignored, as can those arising from routine construction activities, unless the design worsens or significantly alters these risks”

    Further HSE information on risk avoidance

    The HSE Legal Guidance L153 states that further information on eliminating, reducing or controlling foreseeable risks is available on the HSE construction web pages Are You A Designer

    This section of the website is currently (23 March 2015) based on CDM 2007 and will presumably be update before 6th April 2015.

    The CDM Red, Amber and Green Lists (RAGs) at Annex E of the CITB Guidance are practical aides to designers on what to eliminate/avoid, and what to encourage and are unlikely to change.

    CDM 2015 Information and Templates

    See CDM 2015 Survey Results for the findings of our CDM 2015 Five Minute Online Survey.

    We have published a great deal of further information and templates designed to support Clients, Designers, Principal Designers/Contractors and Contractors in meeting their duties under CDM Regulations 2015.

     

    Latest Construction Health and Safety News

    WORKMAN FELL FROM UNSECURED LADDER

    Industrial cladding company failed to assess and control WAH

    Read the rest of this article »

    Posted on 18th January 2019

    SCAFFOLDER FELL THROUGH FRAGILE ROOFLIGHT

    Fall through roof leaves workman with life-changing injuries

    Read the rest of this article »

    Posted on 18th January 2019

    ARM DRAGGED INTO CONVEYOR BELT DANGER

    Workman seriously injured on first day at work in quarry

    Read the rest of this article »

    Posted on 16th January 2019

    ROOF TRUSSES TOPPLED TRAPPING WORKMAN

    Principal contractor failed to plan, manage and monitor project

    Read the rest of this article »

    Posted on 16th January 2019

    SCAFFOLDING AWARENESS TRAINING FOR ALL

    CISRS set to target painters, bricklayers, electricians and plumbers

    Read the rest of this article »

    Posted on 16th January 2019

    HSE ENFORCEMENT DATABASE REMAINS OFFLINE

    hselogo1Access to HSE prosecutions and notices register mysteriously unavailable

    Read the rest of this article »

    Posted on 15th January 2019

    POOR LIFT MAINTENANCE CLAIMED LIFE OF CHILD

    Affordable housing business and contractor fined over £1.5m

    Read the rest of this article »

    Posted on 15th January 2019

    NEW CPA CRANE SAFETY GUIDANCE ISSUED

    Guide covers use of mobile lifting appliances beside railways

    Read the rest of this article »

    Posted on 14th January 2019

    RIBA CONDEMNS RISKIER PROCUREMENT OUTCOMES

    Holistic focus on safety is required and not just cost cutting

    Read the rest of this article »

    Posted on 8th January 2019

    DIRECTOR JAILED OVER PAINT STRIPPER ILLEGAL SALE

    Banned and restricted chemicals sold contrary to legal requirements

    Read the rest of this article »

    Posted on 5th January 2019

    CLIENT FAILED TO PROCURE ASBESTOS SURVEY

    Demolition work released large quantities of asbestos fibres

    Read the rest of this article »

    Posted on 2nd January 2019

    LIVE WORKING IGNITED CLOTHES OF ELECTRICIAN

    Spanner came into contact with live terminal causing life-changing burns

    Read the rest of this article »

    Posted on 31st December 2018

    WORKMEN FELL FROM ‘BIN’ ATTACHED TO EXCAVATOR

    Premature removal of scissor lift prompted unsafe system of work

    Read the rest of this article »

    Posted on 31st December 2018

    MANY SITES FAIL HSE HEALTH RISK CONTROL TEST

    HSE Construction site ‘blitz’ finds breaches at 43% of site visits

    Read the rest of this article »

    Posted on 31st December 2018

    MAKESHIFT FALL ARREST SYSTEM CAUGHT ON CAMERA

    Contactors fined for using harness not attached to suitable anchor

    Read the rest of this article »

    Posted on 31st December 2018

    HYDRAULIC RAM SEVERED HAND OF WORKMAN

    Major contractor failed to follow own policies and procedures

    Read the rest of this article »

    Posted on 31st December 2018

    ALL WORK AREAS NOT INCLUDED IN ASBESTOS SURVEY

    Company fined after asbestos containing materials were released

    Read the rest of this article »

    Posted on 31st December 2018

    FESTIVE GREETINGS TO ALL OUR READERS

    Read the rest of this article »

    Posted on 18th December 2018

    POSITIVE STORY ON FRAGILE SURFACE HAZARDS

    Major roofing contractor testifies to working from below roof

    Read the rest of this article »

    Posted on 18th December 2018

    LEISURE CENTRE USER FELL ILL AFTER SHOWER USE

    Legionella risk assessment and control measures found wanting

    Read the rest of this article »

    Posted on 18th December 2018

    STONE CUTTING MACHINE GUARDS FAILED HSE TEST

    Precautions taken following HSE enforcement fell into disuse

    Read the rest of this article »

    Posted on 18th December 2018

    ROOFWORK CREATED CARBON MONOXIDE RISK

    Falling rubble damaged and blocked home chimney flue

    Read the rest of this article »

    Posted on 18th December 2018

    HSE SAFETY ALERT: TOWER CRANE BRAKES

    Collapse of tower crane jib in high winds prompts HSE warning

    Read the rest of this article »

    Posted on 11th December 2018

    VISITING ENGINEER CRUSHED BY SCAFFOLD TUBES

    Principal contractor “signed off” contractor storage arrangements

    Read the rest of this article »

    Posted on 11th December 2018

    CONCRETE EJECTED BY PUMPING UNIT CLAIMED LIFE

    Company and director failed to train and supervise pumping operations

    Read the rest of this article »

    Posted on 5th December 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic