Turner Access Higher Safety Total Access
Total Access Ethentic Chipmunk Data
Chipmunk Data Turner Access Ethentic

CONVEYOR COLLAPSE DURING INSTALLATION WORKS

Principal contractor site coordination failed to protect workman

Three construction companies have been fined after a workman was crushed by a falling section of conveyor at the Sleaford Renewable Energy plant on Boston Road on 14 February 2013.

Michael Doyle, a 49-year-old employee of Derby-based Shaw Group UK Ltd, who suffered multiple injuries including four cracked vertebrae, broken ribs, a punctured lung and broken ankle. He has not returned to work since.

Lincoln Magistrates’ Court heard  yesterday (12 March) that Shaw Group UK Ltd had been engaged by Burmeister and Wain Energy (BWE) to install a boiler and associated equipment , including a conveyor system to carry large straw bales.

BWE was one of two Danish companies, the other being Burmeister and Wain Scandinavian Contractor (BWSC), which formed a consortium to design and build the centre to burn straw and wood to create electricity and provide heat for local authority buildings.

Shaw Group UK Ltd lifted three conveyor sections to a slope leading to the boiler and placed on a platform at the bottom of the slope. Skates were bolted to the front and rear legs which helped keep the section of conveyor on rails as it was dragged up the slope by manual winches set up at the top.

In order to fix the sections of conveyor in place workers needed to remove the skates and used jacks to raise the legs enough to take the skates off and then lower the legs down onto the rail.

This was carried out successfully on the first three sections but as the jacks were released, on the lower legs of the fourth and final section, one side lowered faster than the other and the conveyor swung towards two workers before violently swinging the other way and turning on its side trapping Mr Doyle.

Safety failings by all three companies

Shaw Group UK Ltd produced a risk assessment and a plan for the installation but did not consider removal of the skates from the legs of the conveyor sections or the manual winching of the load up the slope. The document was sent to BWE for checking but the company did not notice the omission.

The lifting operation using jacks was not carried out safely and none of the three defendants was managing or monitoring the work in a way that would ensure its safety.

The investigation also found that BWSC failed in its responsibility as Principal Contractor to ensure work was properly assessed and co-ordinated between the many contractors on site.

  • Shaw Group UK Ltd of Derby, was fined a total of £17,350 and ordered to pay costs of £1,710 after pleading guilty to breaching Regulation 3(1) of the Management of Health and Safety at Work Regulations 1999; Regulation 8(1)(c) of the Lifting Operations and Lifting Equipment Regulations 1998; and Regulation 13(2) of the Construction (Design and Management ) Regulations 2007.
  • Burmeister and Wain Scandinavian Contractor, of Denmark, was fined £4,670 and ordered to pay costs of £1,710 after pleading guilty to breaching Section 3(1) of the Health and Safety at Work etc Act 1974.
  • Burmeister and Wain Energy, of Denmark, was fined £5,350 and ordered to pay costs of £1,710 after admitting a breach of Regulation 13(2) of the Construction (Design and Management) Regulations 2007.

Speaking after the hearing, HSE inspector Martin Giles said:

“This was a large site with multiple contractors and up to 300 people working at any one time. Although there was a series of site rules set out in a construction phase plan, BWSC’s management of the site was poor as each of the main contractors ran their own areas of the site as they desired and were able to set additional rules. This led to different procedures being followed and a lack of control over temporary works.

The failure to ensure work was carried out safely on the slope was symptomatic of more general failures which were the responsibility of  principal contractor BWSC in setting the rules, procedures and checks needed to manage a large site. These failures put all the workers on site at risk.

BWE specified the use of skates for installing the conveyor system but removing them required adequate risk assessment. Although the company had read the assessment and method statement produced by Shaw Group it made no comment on it and did not approve it before it was implemented. BWE should have picked up on that document’s failures and asked Shaw Group to re-evaluate before work was allowed to begin.

Shaw Group UK Ltd’s risk assessment was flawed, and its management and monitoring of the task was not sufficient to identify potential problems and stop the work in the four days before Mr Doyle was hurt. The actual method of work followed by its employees was unsafe and led to Mr Doyle’s injuries when the load overturned.”

Latest Construction Health and Safety News

REVERSING EXCAVATOR CRUSHED WORKMAN

Lack of management system to segregate pedestrians and vehicles

Read the rest of this article »

Posted on 21st September 2017

CLIENT FINED £2.5 MILLION AFTER CONTRACTOR DEATH

Fatal fall through roof leaves client responsible for massive fine

Read the rest of this article »

Posted on 21st September 2017

HSE ENFORCEMENT WEEKLY UPDATE 20th SEPT 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 20th September 2017

NEW EDGE PROTECTION INSTALLATION TRAINING

Trade body launches CSCS backed edge protection installer qualification

Read the rest of this article »

Posted on 18th September 2017

GOVERNMENT CALLS FOR ACTION ON ILL-HEALTH

Business leaders accept charge of inaction on work-related ill-health

Read the rest of this article »

Posted on 18th September 2017

FIRM FAILED TO ENFORCE FORK LIFT SEAT BELT USE

Operator suffered fatal crush injuries after FLT overturned

Read the rest of this article »

Posted on 18th September 2017

DIRECTOR AND FOREMAN JAILED OVER FATAL FALL

Failure to act on HSE advice ended in gross negligence manslaughter

Read the rest of this article »

Posted on 18th September 2017

PRISON SENTENCE FOR ROOFING CONTRACTOR

Council H&S officers reported dangerous roof work to HSE

Read the rest of this article »

Posted on 14th September 2017

HSE ENFORCEMENT WEEKLY UPDATE 14th SEPT 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 14th September 2017

LADDER STANDARDS MOVE UP A RUNG OR TWO

Ladder Association guide to fundamental changes in ladder standard

Read the rest of this article »

Posted on 12th September 2017

SILICA (RCS) DUST LIMIT – THE ONLY WAY IS DOWN?

US regulator cuts RCS exposure standard to half UK limit

Read the rest of this article »

Posted on 12th September 2017

SAFE2TORCH – REDUCING FLAT ROOF FIRE RISK

Industry body seeks to reduce ‘torch’ triggered fires at design stage

Read the rest of this article »

Posted on 8th September 2017

FIRM AND DIRECTOR SENTENCED OVER GAS RISK

Poorly planned extension prevented effective gas venting

Read the rest of this article »

Posted on 7th September 2017

£1 MILLION CLIENT FINE FOLLOWS FATAL FALL

Electrician died after fall from step ladder provided by client

Read the rest of this article »

Posted on 7th September 2017

HSE ENFORCEMENT WEEKLY UPDATE 6th SEPT 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 7th September 2017

HAVS HEALTH CHECK PROMPTS HSE PROSECUTION

Assessment of vibration exposure and control measures found wanting

Read the rest of this article »

Posted on 7th September 2017

HSE LUNG DISEASE SUMMIT TARGETS SILICA DUST (RCS)

Regulator starts major initiative on lung disease in construction

Read the rest of this article »

Posted on 1st September 2017

HSE COST RECOVERY NOW “FULLY INDEPENDENT”

hselogo1New Fee for Intervention disputes procedure now in place

Read the rest of this article »

Posted on 1st September 2017

CLIENT FINED AS CDM 2015 PRINCIPAL CONTRACTOR

Failure by client to appoint attracts PC duties by default

Read the rest of this article »

Posted on 30th August 2017

JOINER PARALYSED AFTER FALL THROUGH JOISTS

Fall prevention and risk minimisation measures not taken

Read the rest of this article »

Posted on 30th August 2017

HSE ENFORCEMENT WEEKLY UPDATE 30th AUG 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 30th August 2017

COMPLAINT COSTS CONTRACTOR £145,000 IN FINES

HSE prosecute CDM 2015 Principal Contractor over risk without injury

Read the rest of this article »

Posted on 29th August 2017

HSE ENFORCEMENT WEEKLY UPDATE 23rd AUG 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 23rd August 2017

HSE CONSTRUCTION FATALITY RECORDS: Q1 2017/18

Latest HSE fatality records reveal four (4) deaths in first three months

Read the rest of this article »

Posted on 23rd August 2017

HSE ON SILICA DUST (RCS): RISK MANAGEMENT UPDATE

New guidance available on key HSE Construction Sector priority

Read the rest of this article »

Posted on 23rd August 2017
Turner Access Chipmunk Data
Total Access Ethentic
Higher Safety Turner Access