Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    MAJOR PLAYER FAILED TO FOLLOW TW PROCEDURES

    Collapse of rebar structure caused by inadequate temporary works support

    Costain Ltd and Bell Formwork Services Ltd have been prosecuted after a rebar structure collapsed on a Birmingham project in November 2012 causing two workers to fall from a scissor-lift. The defendants were involved in construction of a concrete tank at a new pumping station and water treatment site.

    Birmingham Magistrates heard today (2 Feb) that two steel fixers were working at 5m above ground in separate scissor-lifts when reinforcing bar structure collapsed knocking over both scissor-lifts with the operators still inside.

    One workman remained in the platform when it landed and crashed into a nearby support frame. He suffered bruising and pain in his leg and shoulder. His colleague was propelled from the platform and suffered bruises to his head, legs and body. Three other workers on the ground took cover and avoided injury.

    HSE investigators identified that the steel reinforcement was unstable due to its size, “slenderness” of the steel and the weight of the steel at a high level. Temporary support should have been in place every 7m whereas only two support frames were used at 8.3m spacing leaving an 8m section unsupported.

    Principal contractor Costain Limited failed to “plan, manage or monitor” the work properly despite being aware of the risk and the need for temporary support. A similar collapse had taken place in March of the same year at another site.

    Temporary works require equal care and attention

    The Principal Contractor failed to apply their own temporary works management arrangements which would have included a series of checks. There was “no managerial level supervision or monitoring during these early stages of the work”.

    Costain Ltd of Vanwell Business Park, Maidenhead, Berkshire, pleaded guilty to breaching the Construction (Design and Management) Regulations 2007, and were fined £15,000 and ordered to pay costs of £1,980.

    Bell Formwork Services Ltd of Pinchbeck Road, Spalding, pleaded guilty to a separate breach of the same regulations and was fined £15,000 and ordered to pay £1,851 costs.

    Speaking after the hearing, HSE inspector Luke Messenger said:

    “This was a serious incident and considering the size and weight of the wall, and the height from which the scissor-lifts overturned, it is extremely fortunate that no serious or even fatal injuries occurred.

    Construction and related companies need to ensure that the same degree of care and attention is given to the design and construction of temporary structures as it is to the design and construction of permanent works. Everything must be properly planned so it can be carried out safely by their staff.

    Both companies were experienced in their industry and should have done better.”

    Latest Construction Health and Safety News

    WORKMAN FELL FROM UNSECURED LADDER

    Industrial cladding company failed to assess and control WAH

    Read the rest of this article »

    Posted on 18th January 2019

    SCAFFOLDER FELL THROUGH FRAGILE ROOFLIGHT

    Fall through roof leaves workman with life-changing injuries

    Read the rest of this article »

    Posted on 18th January 2019

    ARM DRAGGED INTO CONVEYOR BELT DANGER

    Workman seriously injured on first day at work in quarry

    Read the rest of this article »

    Posted on 16th January 2019

    ROOF TRUSSES TOPPLED TRAPPING WORKMAN

    Principal contractor failed to plan, manage and monitor project

    Read the rest of this article »

    Posted on 16th January 2019

    SCAFFOLDING AWARENESS TRAINING FOR ALL

    CISRS set to target painters, bricklayers, electricians and plumbers

    Read the rest of this article »

    Posted on 16th January 2019

    HSE ENFORCEMENT DATABASE REMAINS OFFLINE

    hselogo1Access to HSE prosecutions and notices register mysteriously unavailable

    Read the rest of this article »

    Posted on 15th January 2019

    POOR LIFT MAINTENANCE CLAIMED LIFE OF CHILD

    Affordable housing business and contractor fined over £1.5m

    Read the rest of this article »

    Posted on 15th January 2019

    NEW CPA CRANE SAFETY GUIDANCE ISSUED

    Guide covers use of mobile lifting appliances beside railways

    Read the rest of this article »

    Posted on 14th January 2019

    RIBA CONDEMNS RISKIER PROCUREMENT OUTCOMES

    Holistic focus on safety is required and not just cost cutting

    Read the rest of this article »

    Posted on 8th January 2019

    DIRECTOR JAILED OVER PAINT STRIPPER ILLEGAL SALE

    Banned and restricted chemicals sold contrary to legal requirements

    Read the rest of this article »

    Posted on 5th January 2019

    CLIENT FAILED TO PROCURE ASBESTOS SURVEY

    Demolition work released large quantities of asbestos fibres

    Read the rest of this article »

    Posted on 2nd January 2019

    LIVE WORKING IGNITED CLOTHES OF ELECTRICIAN

    Spanner came into contact with live terminal causing life-changing burns

    Read the rest of this article »

    Posted on 31st December 2018

    WORKMEN FELL FROM ‘BIN’ ATTACHED TO EXCAVATOR

    Premature removal of scissor lift prompted unsafe system of work

    Read the rest of this article »

    Posted on 31st December 2018

    MANY SITES FAIL HSE HEALTH RISK CONTROL TEST

    HSE Construction site ‘blitz’ finds breaches at 43% of site visits

    Read the rest of this article »

    Posted on 31st December 2018

    MAKESHIFT FALL ARREST SYSTEM CAUGHT ON CAMERA

    Contactors fined for using harness not attached to suitable anchor

    Read the rest of this article »

    Posted on 31st December 2018

    HYDRAULIC RAM SEVERED HAND OF WORKMAN

    Major contractor failed to follow own policies and procedures

    Read the rest of this article »

    Posted on 31st December 2018

    ALL WORK AREAS NOT INCLUDED IN ASBESTOS SURVEY

    Company fined after asbestos containing materials were released

    Read the rest of this article »

    Posted on 31st December 2018

    FESTIVE GREETINGS TO ALL OUR READERS

    Read the rest of this article »

    Posted on 18th December 2018

    POSITIVE STORY ON FRAGILE SURFACE HAZARDS

    Major roofing contractor testifies to working from below roof

    Read the rest of this article »

    Posted on 18th December 2018

    LEISURE CENTRE USER FELL ILL AFTER SHOWER USE

    Legionella risk assessment and control measures found wanting

    Read the rest of this article »

    Posted on 18th December 2018

    STONE CUTTING MACHINE GUARDS FAILED HSE TEST

    Precautions taken following HSE enforcement fell into disuse

    Read the rest of this article »

    Posted on 18th December 2018

    ROOFWORK CREATED CARBON MONOXIDE RISK

    Falling rubble damaged and blocked home chimney flue

    Read the rest of this article »

    Posted on 18th December 2018

    HSE SAFETY ALERT: TOWER CRANE BRAKES

    Collapse of tower crane jib in high winds prompts HSE warning

    Read the rest of this article »

    Posted on 11th December 2018

    VISITING ENGINEER CRUSHED BY SCAFFOLD TUBES

    Principal contractor “signed off” contractor storage arrangements

    Read the rest of this article »

    Posted on 11th December 2018

    CONCRETE EJECTED BY PUMPING UNIT CLAIMED LIFE

    Company and director failed to train and supervise pumping operations

    Read the rest of this article »

    Posted on 5th December 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic