• Total Access Higher Safety
    Turner Access Chipmunk Data

    TEMPORARY ROOF ‘TOOK OFF’ IN HIGH WINDS

    Contractor fined after flying roof lands on roadway

    Pyeroy Ltd has been prosecuted after the roof on a temporary extension at Lynemouth Power Station was “blown off” in high winds exposing workers and others at risk on 23 December 2013.The roof was a 25m span x 6m in length which weighed 2 tonnes. It rested on 8m high scaffolding supports.

    The ‘flying roof’ struck the roof of an adjacent biomass shed before landing 50m beyond the other end of the shed on a roadway used by delivery wagons and occasional pedestrians. The incident occurred just before Christmas and the normally busy road was deserted.

    Bedlington Magistrates heard (28 January) heard that the roof structure was part of a temporary extension to a permanent shed at the power station, designed to increase capacity and provide weather protection during deliveries by tipper wagons.

    Pyeroy Ltd was asked to install a temporary extension which was designed by the company. It was constructed in June and July 2012 by Pyeroy’s own workforce with the help of a specialist roofing contractor. However, poor communication resulted in an incomplete design plan being used.

    HSE established that although the structure was routinely inspected during the build and once it was brought into use from October 2012, it was inherently unsafe.

    On 22 December the weather was worse than normal with the “winds picking up” and some of the sheeting on the structure needed to be re-tied. The temporary roof was blown off its end supports early the following morning.

    HSE inspectors found that those involved in construction of the extension lacked the necessary knowledge and experience to do the work. The company also failed to properly communicate with the build team and to check the construction was carried out as it should be.

    No assurances about ‘robustness’ of roof

    Pyeroy Limited, of Kirkstone House, St Omers Road, Western Riverside Route, Gateshead, was fined £10,000 and ordered to pay £1.045.50 in costs after pleading guilty to breaching Section 3(1) of the Health and Safety at Work etc Act 1974.

    After the case, HSE inspector Andrew Woodhall said:

    “Thankfully no one was injured as a result of this incident, but it should not and need not have happened.

    It was easily preventable had Pyeroy Ltd ensured the work was carried out to the correct standards; that its team had the necessary skills and experience to carry out the work; and had it checked on the work during construction of the extension.

    Regardless of the wind speeds, no-one knew whether the structure would be properly built or had been properly built, so they could give no assurances about the robustness of the roof. As a result of these failings, workers and others visiting the power station were needlessly put at risk.”

    Latest Construction Health and Safety News

    FATALITY: HOMES PROJECT IN SCOTLAND

    Circumstances of construction worker death remain unclear

    Read the rest of this article »

    Posted on 24th April 2017

    HSE OPEN FEE FOR INTERVENTION CONSULTATION

    hselogo1Regulator proposal for revised FFI disputes process

    Read the rest of this article »

    Posted on 24th April 2017

    LIFTING OPERATION WITH EXCAVATOR CAUSED DEATH

    Groundworker fatally injured when struck by concrete drainage cover

    Read the rest of this article »

    Posted on 24th April 2017

    WATER FIRM FINED £1.8M AFTER WORKER DROWNED

    Workman fell through opening into sand filtration tank

    Read the rest of this article »

    Posted on 24th April 2017

    PC AND CONTRACTOR PAY PRICE FOR UNSAFE WORKING

    Dangerous working practices continued during ‘snowy’ weather

    Read the rest of this article »

    Posted on 24th April 2017

    HSE ENFORCEMENT WEEKLY UPDATE 19th APRIL 2017

    hselogo1Prosecutions and enforcement notices weekly update and analysis

    Read the rest of this article »

    Posted on 20th April 2017

    TOUGHER COURT PENALTIES UNDER NEW GUIDELINES

    Analysis of health and safety prosecutions reveals rise on most metrics

    Read the rest of this article »

    Posted on 18th April 2017

    HSE ENFORCEMENT WEEKLY UPDATE 12th APRIL 2017

    hselogo1Prosecutions and enforcement notices weekly update and analysis

    Read the rest of this article »

    Posted on 18th April 2017

    STOP. MAKE A CHANGE DAY – 18th APRIL 2017

    Infrastructure sector holds first ever ‘National Stand-Down Day’

    Read the rest of this article »

    Posted on 18th April 2017

    ELECTRICIAN FAILED TO PROTECT HIS TRAINEE

    Community service sentence after apprentice fell through ceiling

    Read the rest of this article »

    Posted on 18th April 2017

    CLIENT FINED OVER ABSENT ASBESTOS SURVEY

    Refurbishment project commenced before survey undertaken

    Read the rest of this article »

    Posted on 18th April 2017

    GROUNDWORKER LEFT PARALYSED BY FALLING PIPE

    Gas infrastructure business failed to maintain safe system of work

    Read the rest of this article »

    Posted on 18th April 2017

    MAJOR CONTRACTOR FAILED ON POWER LINE RISK

    Workman suffers severe burns after post touches 11kV overhead cable

    Read the rest of this article »

    Posted on 6th April 2017

    HSE ENFORCEMENT WEEKLY UPDATE 6th APRIL 2017

    hselogo1Prosecutions and enforcement notices weekly update and analysis

    Read the rest of this article »

    Posted on 6th April 2017

    LADDER UNSUITABLE FOR IVY CLEARING TASK

    Electricity supplier fined £900,000 after linesman ladder fall

    Read the rest of this article »

    Posted on 3rd April 2017

    ABSENCE OF ASBESTOS SURVEY PUT FIRMS IN COURT

    Contractor and removal firm jointly responsible for failings

    Read the rest of this article »

    Posted on 3rd April 2017

    WORKING WELL TOGTHER DESIGNER CDM EVENT

    Designer Awareness Day – Preventing Occupational Disease through Design

    Read the rest of this article »

    Posted on 3rd April 2017

    INDUSTRY BODIES STRUCTURE MEWP SAFETY ALERTS

    Strategic Forum Plant Safety Group publishes Safety Alert Protocol

    Read the rest of this article »

    Posted on 3rd April 2017

    ASPHALT MIXER CLAIMS FINGERS OF WORKMAN

    Guarding on mixing machine below the safety standard required

    Read the rest of this article »

    Posted on 3rd April 2017

    FATALITY: SECOND WINDFARM DEATH IN TWO WEEKS

    Workman fell on operational windfarm under maintenance

    Read the rest of this article »

    Posted on 3rd April 2017

    HSE ENFORCEMENT WEEKLY UPDATE 29th MAR 2017

    hselogo1Prosecutions and enforcement notices weekly update and analysis

    Read the rest of this article »

    Posted on 29th March 2017

    UTILITY COMPANY CONVICTED AFTER FALL

    Workman died when fall protection lanyard accidentally severed

    Read the rest of this article »

    Posted on 28th March 2017

    INTENDED SYSTEM UNSAFE … AND NOT FOLLOWED

    Principal contractor and partner failed to protect from roof fall hazard

    Read the rest of this article »

    Posted on 28th March 2017

    DRAMATIC RESCUE FROM HEIGHT CAUGHT ON VIDEO

    Painter in US saved by fall arrest and rescued after platform failure

    Read the rest of this article »

    Posted on 28th March 2017

    MAJOR CONTRACTOR MANAGEMENT FOUND LACKING

    Fatal dumper truck incident caused by inadequate ‘oversight’

    Read the rest of this article »

    Posted on 27th March 2017
    Turner Access Chipmunk Data
    Total Access Higher Safety