• Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    TEMPORARY ROOF ‘TOOK OFF’ IN HIGH WINDS

    Contractor fined after flying roof lands on roadway

    Pyeroy Ltd has been prosecuted after the roof on a temporary extension at Lynemouth Power Station was “blown off” in high winds exposing workers and others at risk on 23 December 2013.The roof was a 25m span x 6m in length which weighed 2 tonnes. It rested on 8m high scaffolding supports.

    The ‘flying roof’ struck the roof of an adjacent biomass shed before landing 50m beyond the other end of the shed on a roadway used by delivery wagons and occasional pedestrians. The incident occurred just before Christmas and the normally busy road was deserted.

    Bedlington Magistrates heard (28 January) heard that the roof structure was part of a temporary extension to a permanent shed at the power station, designed to increase capacity and provide weather protection during deliveries by tipper wagons.

    Pyeroy Ltd was asked to install a temporary extension which was designed by the company. It was constructed in June and July 2012 by Pyeroy’s own workforce with the help of a specialist roofing contractor. However, poor communication resulted in an incomplete design plan being used.

    HSE established that although the structure was routinely inspected during the build and once it was brought into use from October 2012, it was inherently unsafe.

    On 22 December the weather was worse than normal with the “winds picking up” and some of the sheeting on the structure needed to be re-tied. The temporary roof was blown off its end supports early the following morning.

    HSE inspectors found that those involved in construction of the extension lacked the necessary knowledge and experience to do the work. The company also failed to properly communicate with the build team and to check the construction was carried out as it should be.

    No assurances about ‘robustness’ of roof

    Pyeroy Limited, of Kirkstone House, St Omers Road, Western Riverside Route, Gateshead, was fined £10,000 and ordered to pay £1.045.50 in costs after pleading guilty to breaching Section 3(1) of the Health and Safety at Work etc Act 1974.

    After the case, HSE inspector Andrew Woodhall said:

    “Thankfully no one was injured as a result of this incident, but it should not and need not have happened.

    It was easily preventable had Pyeroy Ltd ensured the work was carried out to the correct standards; that its team had the necessary skills and experience to carry out the work; and had it checked on the work during construction of the extension.

    Regardless of the wind speeds, no-one knew whether the structure would be properly built or had been properly built, so they could give no assurances about the robustness of the roof. As a result of these failings, workers and others visiting the power station were needlessly put at risk.”

    Latest Construction Health and Safety News

    DEATH EXPOSED MINIMAL MEWP MAINTENANCE

    Court told about “almost complete” lack of MEWP maintenance

    Read the rest of this article »

    Posted on 21st June 2018

    CONTRACTOR FAILED TO IDENTIFY ASBESTOS PRESENCE

    ACMs disturbed during works and firm failed to take suitable actions

    Read the rest of this article »

    Posted on 21st June 2018

    FALL THROUGH ROOF ON LOCAL COUNCIL BUILDING

    Fragile rooflight fractured when workman ‘misplaced footing’

    Read the rest of this article »

    Posted on 21st June 2018

    YOUNG WORKER POSED SPECIAL RISK TO CONTROL

    Conviction highlights duty to young persons and the vulnerable

    Read the rest of this article »

    Posted on 21st June 2018

    TOWER DEFECTS AND UNSAFE SYSTEM CAUSED DEATH

    Maintenance supervisor fell to his death through roof opening

    Read the rest of this article »

    Posted on 21st June 2018

    UK MAJOR FINED £1/2m OVER HAVS RISK FAILURES

    Danger caused by poor management of vibrating hand tool risk

    Read the rest of this article »

    Posted on 21st June 2018

    HSE ENFORCEMENT WEEKLY UPDATE 20th JUNE 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 20th June 2018

    DIRECTOR FAILED COMPLY WITH HSE PROHIBITION

    Precautions not taken to prevent excavation collapse and falling

    Read the rest of this article »

    Posted on 11th June 2018

    SCAFFOLD NOT TO INDUSTRY STANDARD OR DESIGN

    Specialist and contractor in court over unsafe work at height

    Read the rest of this article »

    Posted on 7th June 2018

    ROAD WORKER RUN OVER BY ROAD ROLLER

    Reversing alarm not working and warning light not fitted

    Read the rest of this article »

    Posted on 5th June 2018

    CLIENT AND SURVEYOR FINED OVER ASBESTOS SURVEY

    Refurbishment and demolition asbestos survey proved inadequate

    Read the rest of this article »

    Posted on 5th June 2018

    FATALITY: ROAD WORKER DRAGGED ALONG ROAD

    Night shift worker loses life when struck by road sweeping vehicle

    Read the rest of this article »

    Posted on 3rd June 2018

    CDM PRINCIPAL DESIGNERS AVOID HSE ENFORCEMENT

    Regulator enforcement database reveals few notices involve CDM PDs

    Read the rest of this article »

    Posted on 3rd June 2018

    PROPERTY MANAGERS FINED WITH CONTRACTOR

    Defendants failed to check for asbestos during soffit replacement works

    Read the rest of this article »

    Posted on 29th May 2018

    EXCAVATION CAUSED RETAINING WALL COLLAPSE

    Precautions not taken to secure stability of free-standing wall

    Read the rest of this article »

    Posted on 29th May 2018

    OVERHEAD CABLE STRIKE FIRM FINED £500,000+

    Inadequate system caused risk of harm despite lack of worker injury

    Read the rest of this article »

    Posted on 29th May 2018

    CDM 2015 PRINCIPAL DESIGNER FINED OVER FIRE RISK

    PD and PC failed to comply with CDM 2015 responsibilities

    Read the rest of this article »

    Posted on 23rd May 2018

    SENTENCING GUIDELINES UNDER THE MICROSCOPE

    Lawyer argues guidelines undermine reduction in ‘regulatory burden’

    Read the rest of this article »

    Posted on 23rd May 2018

    PANEL STRUCK WORKMAN DURING LIFTING OPERATION

    Third party contractor falls victim of poor lift planning

    Read the rest of this article »

    Posted on 21st May 2018

    DIRECTOR LED HAZARDOUS WORK AT HEIGHT

    Three occasions when work lacked suitable and sufficient precautions

    Read the rest of this article »

    Posted on 21st May 2018

    RISK ASSESSED BUT CONTROLS FOUND WANTING

    Joiner fell through unprotected opening on roof of new building

    Read the rest of this article »

    Posted on 21st May 2018

    RIBA CRITICAL OF HACKITT REVIEW FINAL REPORT

    High rise residential review dismissed as “major missed opportunity”

    Read the rest of this article »

    Posted on 21st May 2018

    CONSTRUCTION SECTOR DEATHS: THE ‘BIG THREE’

    HSE in-year fatalities for 2017/18 may indicate upward trend

    Read the rest of this article »

    Posted on 16th May 2018

    SCAFFOLDING SITE ACCIDENTS AT RECORD LOW

    NASC Annual Report reveals all time low in 2017 incidents

    Read the rest of this article »

    Posted on 14th May 2018

    DUMPER TRUCK HAND-BRAKE NOT MAINTAINED

    Workman injured when pinned against stack of concrete blocks

    Read the rest of this article »

    Posted on 14th May 2018
    Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data