Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    TEMPORARY ROOF ‘TOOK OFF’ IN HIGH WINDS

    Contractor fined after flying roof lands on roadway

    Pyeroy Ltd has been prosecuted after the roof on a temporary extension at Lynemouth Power Station was “blown off” in high winds exposing workers and others at risk on 23 December 2013.The roof was a 25m span x 6m in length which weighed 2 tonnes. It rested on 8m high scaffolding supports.

    The ‘flying roof’ struck the roof of an adjacent biomass shed before landing 50m beyond the other end of the shed on a roadway used by delivery wagons and occasional pedestrians. The incident occurred just before Christmas and the normally busy road was deserted.

    Bedlington Magistrates heard (28 January) heard that the roof structure was part of a temporary extension to a permanent shed at the power station, designed to increase capacity and provide weather protection during deliveries by tipper wagons.

    Pyeroy Ltd was asked to install a temporary extension which was designed by the company. It was constructed in June and July 2012 by Pyeroy’s own workforce with the help of a specialist roofing contractor. However, poor communication resulted in an incomplete design plan being used.

    HSE established that although the structure was routinely inspected during the build and once it was brought into use from October 2012, it was inherently unsafe.

    On 22 December the weather was worse than normal with the “winds picking up” and some of the sheeting on the structure needed to be re-tied. The temporary roof was blown off its end supports early the following morning.

    HSE inspectors found that those involved in construction of the extension lacked the necessary knowledge and experience to do the work. The company also failed to properly communicate with the build team and to check the construction was carried out as it should be.

    No assurances about ‘robustness’ of roof

    Pyeroy Limited, of Kirkstone House, St Omers Road, Western Riverside Route, Gateshead, was fined £10,000 and ordered to pay £1.045.50 in costs after pleading guilty to breaching Section 3(1) of the Health and Safety at Work etc Act 1974.

    After the case, HSE inspector Andrew Woodhall said:

    “Thankfully no one was injured as a result of this incident, but it should not and need not have happened.

    It was easily preventable had Pyeroy Ltd ensured the work was carried out to the correct standards; that its team had the necessary skills and experience to carry out the work; and had it checked on the work during construction of the extension.

    Regardless of the wind speeds, no-one knew whether the structure would be properly built or had been properly built, so they could give no assurances about the robustness of the roof. As a result of these failings, workers and others visiting the power station were needlessly put at risk.”

    Latest Construction Health and Safety News

    SEVENTH LONDON CYCLIST DEATH DURING 2018

    Building products vehicle involved in death of Queens doctor

    Read the rest of this article »

    Posted on 17th August 2018

    HSE ENFORCEMENT WEEKLY UPDATE 15th AUGUST 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 15th August 2018

    MAJOR CONTRACTOR FAILED TO SUPERVISE LIFT

    Errors whilst lifting pre-cast concrete blocks fined £600,000

    Read the rest of this article »

    Posted on 14th August 2018

    FIRM FINED £400,000 OVER VIBRATING TOOLS RISK

    Hand-held orbital sanders, rivet guns, grinders and drills caused harm

    Read the rest of this article »

    Posted on 14th August 2018

    OVERHEAD POWER AND EARTHING OF SCAFFOLDS

    NASC combines updates advice on scaffold electrical risks

    Read the rest of this article »

    Posted on 9th August 2018

    REVERSING VEHICLE CLAIMED LIFE OF ‘BANKSMAN’

    Workman trapped whilst assisting colleague in reversing lorry

    Read the rest of this article »

    Posted on 7th August 2018

    TWO WORKMEN DIED IN SPRAY BOOTH EXPLOSION

    Flammable vapour ignited by ignition sources present at the scene

    Read the rest of this article »

    Posted on 6th August 2018

    SOLAR SPECIALIST FAILED TO PLAN FOR SAFETY

    Fragile roof failed under weight of solar installation worker

    Read the rest of this article »

    Posted on 6th August 2018

    DIRECTOR AND COMPANY FINED FOR SAFETY BREACHES

    Basic work at height risks and welfare requirements ignored

    Read the rest of this article »

    Posted on 6th August 2018

    REFURB PROJECT REQUIRED ASBESTOS ASSESSMENT

    Property management firm fined over lack of asbestos survey

    Read the rest of this article »

    Posted on 6th August 2018

    CLIENT FAILED MANAGEMENT ARRANGEMENTS TEST

    Homes developer prosecuted for breaching CDM 2015 client duties

    Read the rest of this article »

    Posted on 6th August 2018

    JAIL TERM FOR DEVELOPER AFTER BUILDING COLLAPSE

    Inexperienced workers demolished structure without Principal Contractor

    Read the rest of this article »

    Posted on 6th August 2018

    CDM 2015 DUTYHOLDERS IGNORED HSE ADVICE

    Contractor, client and director convicted after dangerous site conditions

    Read the rest of this article »

    Posted on 6th August 2018

    MASSIVE FINE OVER USE OF UNSAFE GAS FITTINGS

    College gas installation contractor exposed after multiple gas leaks

    Read the rest of this article »

    Posted on 17th July 2018

    TEMP WORKS DESIGNED BY MANAGER AND UNCHECKED

    Collapse of platform highlighted failure in temporary works management

    Read the rest of this article »

    Posted on 17th July 2018

    RAISING SAFETY STANDARDS FOR CRANE LIFTING OPS

    Major crane seminar seeks to raise standards and share best practice

    Read the rest of this article »

    Posted on 17th July 2018

    WORKMAN SURVIVES 6m FALL THROUGH ROOFLIGHT

    Unsecured boards provided to cover nearby fragile materials

    Read the rest of this article »

    Posted on 17th July 2018

    MAJOR FACILITIES FIRM FAILED ON FLAT ROOF SAFETY

    Site specific planning lacking and safety standards not monitored

    Read the rest of this article »

    Posted on 17th July 2018

    HSE ALERT: UNAUTHORISED ACCESS TO SCAFFOLDS

    hselogo1Regulator sets out new guidance to protect children and the public

    Read the rest of this article »

    Posted on 17th July 2018

    ASSUMING OTHERS WILL ACT IS NO DEFENCE

    Incomplete edge protection caused 8m fall from roof

    Read the rest of this article »

    Posted on 17th July 2018

    LEADING ROOFING SPECIALIST FOUND WANTING

    Risk to employees and the public after failure to meet required standard

    Read the rest of this article »

    Posted on 17th July 2018

    SCAFFOLDER DEVELOPMENT EMBRACED BY INDUSTRY

    CPD training attracts over 2500 scaffolders during first year of operation

    Read the rest of this article »

    Posted on 11th July 2018

    SECURITY PANELS FELL DESPITE EARLY WARNING

    Firm fined £1/4 million after worker crushed by falling fencing

    Read the rest of this article »

    Posted on 10th July 2018

    VEHICLE STRIKE TRIGGERED FALL OF ROOF TRUSSES

    Manufacturer failed to identify a suitable safe system of work

    Read the rest of this article »

    Posted on 10th July 2018

    INCIDENT: CHILD STRUCK BY FALLING OBJECT

    Wood falling from scaffold triggers arrest of two on construction site

    Read the rest of this article »

    Posted on 10th July 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic