    HOARDING COLLAPSE TRAPPED TWENTY SHOPPERS

    Fit-out firm failed to erect fit for purpose site fencing

    Oracle Interiors Ltd has been fined after shoppers were crushed when a site hoarding collapsed in the heart of Oxford Street London less than 24 hours after the structure was erected in March 2012.

    Four people were injured, three seriously, in the incident including 25 year-old Charlotte Hammond who sustained an open fracture of her right ankle that required extensive surgery.

    The over 3m high hoarding weighed almost 1 tonne and was erected the day before the incident to fence off refurbishment works being undertaken in a clothing store.

    Westminster Magistrates heard (3 Dec) the hoarding was held in place by a single timber brace. It was inherently weak and was not designed or installed to sufficiently withstand gusts of wind or knocks from passing shoppers. Both factors should have been included in the assessment, design and construction.

    It was estimated that 20 people were trapped by the hoarding when it collapsed although most managed to escape unharmed as emergency crews and fellow passers-by rushed to help.

    Injuries sustained by the other victims included broken bones in the back and crushed nerves in an arm.

    Innocent shoppers traumatised

    Oracle Interiors Ltd, of Salisbury, was fined £10,000 and ordered to pay £13,069 in costs after pleading guilty to a single breach of the Construction (Design and Management) Regulations 2007.

    After the hearing, HSE Inspector Wendy Garnett commented:

    “The law clearly states that all temporary structures, including hoardings, are properly designed, and so installed to withstand any foreseeable loads imposed on it.

    That clearly wasn’t the case on this occasion and innocent shoppers were subjected to a frightening and, for some, hugely traumatic ordeal that had a long-term impact.

    Charlotte and others could easily have been killed by the hoarding and they were completely unaware that it posed a risk – not only to them, but to the tens of thousands of people who walked along Oxford Street that busy afternoon.

    Oracle Interiors Ltd could and should have done more to prevent the collapse.”

    Latest Construction Health and Safety News

    HSE CONSTRUCTION DUST CONTROL ‘BLITZ’ STARTS

    Regulator inspections will check health taken as seriously as safety

    Read the rest of this article »

    Posted on 20th September 2018

    FLOOR CONSTRUCTION SYSTEM OF WORK UNSAFE

    Welder fell 3m from mezzanine area through purlin openings

    Read the rest of this article »

    Posted on 20th September 2018

    WORKER SUFFERS FATAL BURNS IN OXYGEN RICH AREA

    Sparks from angle grinder ignited clothing of workman in confined space

    Read the rest of this article »

    Posted on 19th September 2018

    RIBA PUBLISH DRAFT POST GRENFELL FIRE SAFETY PLAN

    Architects institute consults on ‘golden thread of fire safety information’

    Read the rest of this article »

    Posted on 19th September 2018

    MAJOR UK CONTRACTORS HIT BY MAJOR FINES

    Firms ordered to pay over £3m after foot trapped in rotating ‘screw’

    Read the rest of this article »

    Posted on 19th September 2018

    HSE ENFORCEMENT WEEKLY UPDATE 19th SEPT 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 19th September 2018

    DRIVER DIED TRAPPED BETWEEN TRAILER AND VEHICLE

    Firm fined £1.5 million over failure to assess coupling operations

    Read the rest of this article »

    Posted on 14th September 2018

    ACTUAL SYSTEM OF WORK WAS OPPOSITE OF RAMS

    Workman fell 4m through fragile asbestos roof sheet

    Read the rest of this article »

    Posted on 13th September 2018

    CDM PRINCIPAL DESIGNER FUNCTION MISUNDERSTOOD?

    Consultants claim CDM 2015 design risk management has ‘gone backwards’

    Read the rest of this article »

    Posted on 8th September 2018

    RISK ASSESSED PRECAUTIONS NOT IMPLEMENTED

    Action not paperwork essential to prevent fall during lifting operation

    Read the rest of this article »

    Posted on 7th September 2018

    CROSSRAIL PUBLISH BEST PRACTICE H&S GUIDES

    Sharing major project best practice can leave a lasting legacy

    Read the rest of this article »

    Posted on 5th September 2018

    SCHOOL STAFF LACKED ASBESTOS AWARENESS TRAINING

    Council fined £200k over asbestos flue and gasket rope failures

    Read the rest of this article »

    Posted on 5th September 2018

    INCIDENT: MEWP OVERTURN IN CITY CENTRE

    Images show aftermath of mobile elevating platform collapse

    Read the rest of this article »

    Posted on 5th September 2018

    SAFETY ALERT: DEFECTIVE SCAFFOLD COUPLER

    National Access and Scaffolding Confederation issues warning

    Read the rest of this article »

    Posted on 31st August 2018

    DEMOLISHING INTERNAL WALL REVEALED ASBESTOS

    Firm lacked survey and asbestos management plan for premises

    Read the rest of this article »

    Posted on 31st August 2018

    NEW HEALTH AND SAFETY TEST FOR ARCHITECTS

    RIBA raise the bar for members on design risk management and ‘life safety’

    Read the rest of this article »

    Posted on 31st August 2018

    POWER BUSINESSES FAILED ON LIFTING OPERATION

    Panel fell on workman during turbine maintenance project

    Read the rest of this article »

    Posted on 31st August 2018

    MAJOR INFRASTRUCTURE FIRM COMMITS TO ZERO HARM

    Behaviours to deliver zero lost time injury incident rate by 2021

    Read the rest of this article »

    Posted on 31st August 2018

    MANAGING TOWER CRANE FALLING OBJECT RISK

    CPA issues new technical information note

    Read the rest of this article »

    Posted on 31st August 2018

    POST EXPLOSION ASBESTOS WORK WAS UNSAFE

    Asbestos cement panels removed and cut with power tools

    Read the rest of this article »

    Posted on 31st August 2018

    FALL THROUGH UNFLOORED FACTORY ROOF SPACE

    Non-routine tasks require assessment and clear risk controls

    Read the rest of this article »

    Posted on 31st August 2018

    SEVENTH LONDON CYCLIST DEATH DURING 2018

    Building products vehicle involved in death of Queens doctor

    Read the rest of this article »

    Posted on 17th August 2018

    MAJOR CONTRACTOR FAILED TO SUPERVISE LIFT

    Errors whilst lifting pre-cast concrete blocks fined £600,000

    Read the rest of this article »

    Posted on 14th August 2018

    FIRM FINED £400,000 OVER VIBRATING TOOLS RISK

    Hand-held orbital sanders, rivet guns, grinders and drills caused harm

    Read the rest of this article »

    Posted on 14th August 2018

    OVERHEAD POWER AND EARTHING OF SCAFFOLDS

    NASC combines updates advice on scaffold electrical risks

    Read the rest of this article »

    Posted on 9th August 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic