Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    DESIGNERS FACE HSE INVOICES OVER NON-COMPLIANCE

    HSE call for design decisions justified by “risk rather than cost”

    An Open Letter from the HSE to the ‘structural timber industry’ has been published (29/10).

    The letter is intended for “all parties involved in the design, specification, procurement and construction of timber frame structures” explaining HSE expectations in relation to the management of fire risks prior to and during the construction of timber frame structures.

    The Structural Timber Association (STA), which represents the industry’s manufacturers and suppliers, has cooperated with HSE in producing the letter.

    HSE approach to off-site fire risks

    Fire precautions during the construction of timber frame structures fall within HSE remit. See the HSE published guidance on  Fire Safety in Construction.

    The regulator points out that duty holders have responsibility to ensure the safety and health of workers and those who might be affected by their work activities, including those arising from fire risks. Serious incidents have arisen where fires involving timber frame structures under construction have affected neighbouring buildings and HSE has therefore worked with the STA to produce the guidance.

    In summary HSE state:

    “All those making design and procurement decisions that significantly affect fire risk should consider and reduce the risk and consequences of fire during the construction phase through DESIGN. Failure so to do may constitute a material breach for which HSE will apply its Fee for Intervention scheme to those duty holders who have contributed to the breach.”

    Justify decisions in terms of risk rather than cost

    HSE state that CDM 2007 Regulation 11 requires risks to be considered and eliminated/reduced so far as is reasonably practicable through the design process adding:

    “The primary legal responsibility for assessing off-site fire risk rests with those making design and procurement decisions before work starts on site. Designers and manufacturers of timber frame structures duties under CDM Regulation 11 cannot be passed on to the Principal Contractor.

    The STA publication Design guide to separating distances during construction is intended to be used at the design and procurement stages of a project. HSE commends the STA for the substantial work carried out and make it freely available to all rather than being restricted to STA members.

    Following the guidance is “not compulsory” and if an alternative approach to the guidance is used, a competent person with fire engineering qualifications and experience will need to determine the risks and to identify appropriate controls. HSE go on to state:

    “The persons involved should justify their decisions and recommendations in terms of risk, rather than cost.”

    Design process to be followed

    The letter states that for a proposed structure, the STA guidance enables minimum separation distances to be determined. Where space does not provide the separation distances required for a Category A structure, it provides guidance on selecting alternative timber frame structures to provide an adequate level of fire protection to neighbours during the construction phase.

    If a Category B or C structure or alternative fire engineered solution is needed, then it should be specified when the timber frame is being procured. Everyone in the supply chain has a responsibility to work towards this end. In practical terms HSE expects:

    • An assessment of the particular site and its constraints when the method of construction is being considered;
    • For timber-framed structures, assessment can be undertaken using STA’s ‘Design guide to separating distances during construction’;
    • The assessment should identify that where there is insufficient separation distance to allow a Category A structure, the appropriate level of Category B or C to match the site constraints (unless an alternative fire engineered solution is developed by a competent person) should be recommended;
    • The appropriate category frame should be specified to the manufacturers;
    • Timber frame manufacturers, including non-STA members have a significant role to play in ensuring appropriate specification and procurement of frames. Manufacturers should be advising their customers of the guidance and requirements. Use of the STA audit checklist may assist manufacturers in compiling records to demonstrate the steps they have taken to discharge their obligations under CDM Regulation 11 and record who has made specific decisions;
    • Any specific information and instructions that must be followed to guarantee the specified category or approved solution to be achieved on site must be passed to the Principal Contractor;
    • The Principal Contractor must adhere to the conditions required to achieve the specified category of structure; and
    • The Principal Contractor must devise and apply appropriate fire precautions during the build, including control of hot works, provision of fire warning and extinguishing systems, provision of means of escape etc.

    Finally the letter states:

    “HSE inspectors expect duty holders to comply with CDM Regulation 11 using this guidance to assist. Where a duty holder chooses not to follow the STA guidance but to implement a fire-engineered solution, standards of the equivalence to the guidance should be adopted.

    Duty holders should expect that in the latter circumstances, if lower standards are adopted then HSE may consider there to have been a material breach of health and safety law attracting charges under our Fee for Intervention Scheme”

    Latest Construction Health and Safety News

    CHILD INJURED BY WALL COLLAPSE INCIDENT

    Council failed to carry out “intelligence led” condition inspections

    Read the rest of this article »

    Posted on 18th February 2019

    BOTTLE JACK SUPPORT FAILED TO PREVENT DEATH

    Director sentenced alongside company over death of engineer

    Read the rest of this article »

    Posted on 18th February 2019

    TEMPORARY WORKS FAILURES CAUSED FATAL FALL

    Platform not designed and system for installation and inspection inadequate

    Read the rest of this article »

    Posted on 18th February 2019

    SOLVENT IGNITED DURING FLOOR CLEANING WORKS

    Flammable solvent fire fought with water spreading fire further

    Read the rest of this article »

    Posted on 13th February 2019

    INEVITABLE COLLAPSE OF SCAFFOLD ON TO SCHOOL

    Scaffold not designed or installed to withstand foreseeable loads

    Read the rest of this article »

    Posted on 13th February 2019

    HSE ENFORCEMENT WEEKLY UPDATE 13th FEB 2019

    hselogo1Latest online register of prosecutions and enforcement notices

    Read the rest of this article »

    Posted on 13th February 2019

    OIL DRUM EXPLODED DURING HOT CUTTING WORK

    Firm fined £400k after drum lid ejected causing loss of leg

    Read the rest of this article »

    Posted on 12th February 2019

    ROOFLIGHT FALL ON NUCLEAR POWER SITE

    Energy generating company and maintenance contractor fined

    Read the rest of this article »

    Posted on 12th February 2019

    DIRECTOR PROSECUTED AFTER 6METRE ROOF FALL

    Untrained worker fell through rooflight in fragile asbestos roof

    Read the rest of this article »

    Posted on 12th February 2019

    HSE ALERT: MILD STEEL WELDING CANCER RISK

    HSE announces enforcement action change based on new cancer evidence

    Read the rest of this article »

    Posted on 11th February 2019

    LORRY MOUNTED LIFTING OPERATION PROVED FATAL

    Steel staircase toppled from vehicle after sling snagged

    Read the rest of this article »

    Posted on 7th February 2019

    DIRECTOR AND BUSINESS IN COURT OVER DEATH

    Scaffold not priced for on domestic roof-line refurbishment work

    Read the rest of this article »

    Posted on 6th February 2019

    FRAGILE ROOFLIGHT HAZARD PROTECTION MISSING

    Two businesses prosecuted after a worker fell through a fragile rooflight

    Read the rest of this article »

    Posted on 5th February 2019

    STRUCTURAL SAFETY BODY LATEST NEWSLETTER

    CROSS publishes reports and expert comment on a range of issues

    Read the rest of this article »

    Posted on 4th February 2019

    FINGERS CRUSHED BY METAL FOLDING MACHINE

    Steel cladding firm fined £600k over failure guard access to danger

    Read the rest of this article »

    Posted on 4th February 2019

    ASBESTOS ILLEGALLY REMOVED AFTER SURVEY

    Surveyor pricing asbestos work found contractor jumped the gun

    Read the rest of this article »

    Posted on 4th February 2019

    SITE DUMPER PRECAUTIONS FAILED TO PREVENT DEATH

    Contractor fined £600k for poor management of vehicle/people interface

    Read the rest of this article »

    Posted on 4th February 2019

    BUILDER EXPOSED RESIDENTS TO POISONING HAZARD

    Prison term for builder who put three at risk from carbon monoxide

    Read the rest of this article »

    Posted on 4th February 2019

    POOR SEPARATION OF VEHICLES AND PEDESTRIANS

    Logistics company fined £150,000 after driver suffers serious injuries

    Read the rest of this article »

    Posted on 4th February 2019

    £1MILLION FINE OVER VEHICLE RISK MANAGEMENT

    Death of workman exposed uncontrolled vehicle manoeuvring

    Read the rest of this article »

    Posted on 25th January 2019

    ACCREDITATION IS ONLY ONE WAY TO CONFIDENCE

    HSE publishes guidance on demonstrating CDM 2015 competence

    Read the rest of this article »

    Posted on 24th January 2019

    PRECAUTIONS ON PAPER LACKING IN PRACTICE

    Fatal fall through opening in concrete slab during work with breaker

    Read the rest of this article »

    Posted on 24th January 2019

    HSE TARGETS HEALTH ON LONDON PROJECTS

    Regulator starts inspection ‘blitz’ on construction sites

    Read the rest of this article »

    Posted on 23rd January 2019

    WORKMAN FELL FROM UNSECURED LADDER

    Industrial cladding company failed to assess and control WAH

    Read the rest of this article »

    Posted on 18th January 2019

    SCAFFOLDER FELL THROUGH FRAGILE ROOFLIGHT

    Fall through roof leaves workman with life-changing injuries

    Read the rest of this article »

    Posted on 18th January 2019
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic