Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    CDM 2015 PUTS DESIGNERS AT HEART OF PROJECT SAFETY

    HSE original CDM Coordination intentions may now come to fruition 

    The Health and Safety Executive (HSE) is proposing that current CDM 2007 Coordinator duties will become the responsibility of architect practices or other designers appointed to the statutory role of ‘Principal Designer’. The proposed change reflects original HSE intentions when the CDM Regulations were first placed on the stature book in 1994.

    At that time the HSE Construction Sector hoped the regulations would not give rise to a new ‘discipline’ and that the Planning Supervisor/CDM Coordinator function would be undertaken by existing project team members e.g. architects and other designers.

    The HSE hopes did not come to fruition and the function primarily became the preserve of dedicated Planning Supervisors and CDM Coordinators. However, if the current HSE proposals become law the design community will be placed at the heart of project safety.

    The changes will become effective from April 2015 presenting both risks and opportunities for all architects and other designers.

    Key changes affecting architects and others

    The CDM Regulations 2015 are planned to require (inter alia) that:

    • Appointed Principal Designer – a PD must be appointed on ALL construction projects (both ‘business’ AND ‘domestic’) where there is more than one contractor. 
    • Deemed Principle Designers – where a domestic client does not appoint a PD the first designer appointed during the pre-construction phase will be ‘deemed’ to be appointed. 

    The project architect is most likely to be the ‘Appointed’ or ‘Deemed’ PD.

    HSE estimated that 1 million additional small projects will require the appointment of a PD each year. See our concise Summary of what is proposed.

    Principal designer responsibilities

    The PD is required to plan, manage, monitor and coordinate the project pre-construction phase to ensure:

    • the project is carried out without risks to health or safety;
    • pre-construction information preparation and provision;
    • identification, elimination, or control of foreseeable risks;
    • cooperation of all persons working on the project;
    • compliance of all designers with their duties;
    • preparation and revision of a health safety file; and
    • liaison with principal contractor e.g. information for construction phase plan

    The draft Regulations are based on a the PD duty to “plan, manage, monitor and coordinate the pre-construction phase” of a project. This wide-ranging  responsibility appears to include both ‘design’ and other ‘preparatory’ work embracing a ‘management’ role beyond the current CDMC function.

    Architects and other designers taking on the PD role will need to review their preparedness for the new duties.

     

    Latest Construction Health and Safety News

    FESTIVE GREETINGS TO ALL OUR READERS

    Read the rest of this article »

    Posted on 18th December 2018

    POSITIVE STORY ON FRAGILE SURFACE HAZARDS

    Major roofing contractor testifies to working from below roof

    Read the rest of this article »

    Posted on 18th December 2018

    LEISURE CENTRE USER FELL ILL AFTER SHOWER USE

    Legionella risk assessment and control measures found wanting

    Read the rest of this article »

    Posted on 18th December 2018

    STONE CUTTING MACHINE GUARDS FAILED HSE TEST

    Precautions taken following HSE enforcement fell into disuse

    Read the rest of this article »

    Posted on 18th December 2018

    ROOFWORK CREATED CARBON MONOXIDE RISK

    Falling rubble damaged and blocked home chimney flue

    Read the rest of this article »

    Posted on 18th December 2018

    HSE ENFORCEMENT WEEKLY UPDATE 12th DEC 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 12th December 2018

    HSE SAFETY ALERT: TOWER CRANE BRAKES

    Collapse of tower crane jib in high winds prompts HSE warning

    Read the rest of this article »

    Posted on 11th December 2018

    VISITING ENGINEER CRUSHED BY SCAFFOLD TUBES

    Principal contractor “signed off” contractor storage arrangements

    Read the rest of this article »

    Posted on 11th December 2018

    CONCRETE EJECTED BY PUMPING UNIT CLAIMED LIFE

    Company and director failed to train and supervise pumping operations

    Read the rest of this article »

    Posted on 5th December 2018

    REFRESHED GUIDANCE ON FITNESS TO OPERATE PLANT

    Construction plant medical fitness Good Practice Guide

    Read the rest of this article »

    Posted on 4th December 2018

    MAJOR CONTRACTOR & LUL USED UNSAFE SYSTEM

    Work method to eliminate moving vehicle hazard not adopted

    Read the rest of this article »

    Posted on 4th December 2018

    OVERTURNING LORRY CAUSED DEATH OF DRIVER

    Groundworks project stockpiling arrangements not properly managed

    Read the rest of this article »

    Posted on 3rd December 2018

    FORTH BRIDGE LIFTING OPERATION NOT PLANNED

    Major project PC failed to plan, supervise and carry out lift safely

    Read the rest of this article »

    Posted on 3rd December 2018

    DEVELOPER FAILED ON ASBESTOS ASSESSMENT

    HSE inspection revealed refurb works without asbestos survey

    Read the rest of this article »

    Posted on 28th November 2018

    POST DRIVER HAMMER CRUSHED HAND OF WORKMAN

    Unsafe system of work for vehicle crash barrier installation

    Read the rest of this article »

    Posted on 28th November 2018

    WORKER FELL FROM LOFT THROUGH CEILING

    Major house builder lacked understanding of loft fragile surfaces risk

    Read the rest of this article »

    Posted on 28th November 2018

    NEW SITE DUMPER SAFETY GUIDANCE ISSUED

    Construction plant sector concerns prompts CPA consults on draft

    Read the rest of this article »

    Posted on 28th November 2018

    CCTV INSTALLER FELL THROUGH FRAGILE ROOFLIGHT

    Contractor failed to properly plan and control the risks

    Read the rest of this article »

    Posted on 28th November 2018

    VISITOR DIED FALLING INTO CONCEALED BASEMENT

    Contractor failed to protect basement void on domestic project

    Read the rest of this article »

    Posted on 28th November 2018

    RACKING FALL REVEALED UNSAFE SYSTEM OF WORK

    European firm fined £300,000 after UK sub-contractor employee fell

    Read the rest of this article »

    Posted on 18th November 2018

    FAILURE TO ACT ON VIBRATION AND SILICA HAZARDS

    Worker health put at risk during stripping of furnace lining

    Read the rest of this article »

    Posted on 18th November 2018

    MAJOR FM FIRM FAILED TO MAINTAIN BACK-UP POWER

    Power loss at laboratory site created potential risk from biological agents

    Read the rest of this article »

    Posted on 18th November 2018

    IGNORING HSE PROHIBITIONS COST FIRM £250,000

    CDM 2015 and work at height requirements repeatedly breached

    Read the rest of this article »

    Posted on 16th November 2018

    ROOF COLLAPSED UNDER EXCESS LOADING

    Director and company fined over roof design failures

    Read the rest of this article »

    Posted on 11th November 2018

    FORK LIFT OVERTURNED IN SCAFFOLDING YARD

    Untrained operator suffered life changing crush injuries

    Read the rest of this article »

    Posted on 10th November 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic