Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    BUILDERS AND ARCHITECTS LOOK SET FOR NEW DUTIES

    Domestic client CDM 2015 responsibilities will be ‘deemed’ to others

    HSE is proposing new responsibilities for managing construction projects be placed on “domestic clients” i.e. those who procure extensions etc for their own homes. These domestic clients were excluded under CDM 2007.

    UPDATE JAN 2015: HSE publish CDM 2015 Regulations and Guides

    However, the direct impact on domestic clients is intended to be eased by ‘deeming’ that either an appointed building contractor or designer e.g. project architect, will be responsible for the domestic client project management and coordination responsibilities.

    Single contractor projects

    Where there is no more than one contractor working on a domestic project at any time the contractor (rather than the domestic client) will be required to take the following actions:

    • Arrangements – for managing the project so it is carried safely and with acceptable welfare;
    • Review – maintain and review those arrangements throughout the project;
    • Information – provide Pre-Construction Information to designers and others;;
    • H&S Plan – draw up a Construction Phase Plan;
    • Inform – notify larger projects to HSE.

    These responsibilities are in addition to specific contractor duties included in the proposals.

    View our initial Summary of New Responsibilities proposed

    More than one contractor projects

    Where there is more than one contractor (or it is reasonably foreseeable that more than one contractor will be) working on a project at any time the domestic client must appoint in writing a ‘Principal Designer’ (PD) and a ‘Principal Contractor’ (PC).

    If the domestic client fails to make these appointments the proposed regulations will deem the first designer appointed during the pre-construction phase to be the PD and the first contractor appointed during the construction phase to the PC with responsibilities as defined.

    Under CDM 2007 full application of the regulations (involving an CDM-C and PC) applied only to business projects. The current proposals require that the new PD and PC appointments are made on ALL domestic projects where there is more than one contractor.

    It is unlikely that domestic clients will make the required appointments and these new duties will therefore most likely fall to the project architect (PD) and main contractor (PC).

    Support for architects appointed or ‘deemed’ as PD.

    All domestic projects will be affected

    HSE estimate 1 million additional projects will require the project PD role.

    In addition, there will be many more single contractor projects requiring the contractor to take the actions summarised above including pre-construction information and a preparation of a construction phase plan.

    These will be new requirements for many small contractors.

    Latest Construction Health and Safety News

    CONSTRUCTION SITE DEATHS SET TO FALL?

    HSE in-year fatality records for 2018/19 suggest significant reduction

    Read the rest of this article »

    Posted on 22nd March 2019

    HSE ENFORCEMENT DATABASE UPDATE 20th MAR 2019

    hselogo1Latest online register of prosecutions and enforcement notices

    Read the rest of this article »

    Posted on 20th March 2019

    BRICKLAYER FATALLY INJURED BY FALLING WALL

    Masonry collapsed during concrete back filling operation

    Read the rest of this article »

    Posted on 18th March 2019

    BASIC LADDER SAFETY FAILURES FINED £150,000

    Repair and maintenance firm had no excuse for errors causing injury

    Read the rest of this article »

    Posted on 18th March 2019

    HSE ISSUES REMINDER ON SAFE SCAFFOLD DESIGN

    Recent incidents and high winds prompt warning from regulator

    Read the rest of this article »

    Posted on 12th March 2019

    LORRY DRIVER DIED IN OVERHEAD POWER STRIKE

    Major company failed to communicate precautions to grab arm operator

    Read the rest of this article »

    Posted on 12th March 2019

    ASSESSMENT SHOWED RISK – PRECAUTIONS NOT TAKEN

    Workman seriously injured when falling into open unguarded stairwell

    Read the rest of this article »

    Posted on 1st March 2019

    MAJOR FIRM FAILED TO IMPLEMENT SAFE SYSTEM

    Procedures for safe plant refuelling failed to prevent death of workman

    Read the rest of this article »

    Posted on 26th February 2019

    CLIENT PROSECUTED OVER CONTRACTOR FATAL FALL

    Company breached duty to protect contractors as well as employees

    Read the rest of this article »

    Posted on 26th February 2019

    FOURTEEN YEAR FAILURE TO MANAGE ASBESTOS

    Firm failed to implement asbestos management plan following survey

    Read the rest of this article »

    Posted on 25th February 2019

    CHILD INJURED BY WALL COLLAPSE INCIDENT

    Council failed to carry out “intelligence led” condition inspections

    Read the rest of this article »

    Posted on 18th February 2019

    BOTTLE JACK SUPPORT FAILED TO PREVENT DEATH

    Director sentenced alongside company over death of engineer

    Read the rest of this article »

    Posted on 18th February 2019

    TEMPORARY WORKS FAILURES CAUSED FATAL FALL

    Platform not designed and system for installation and inspection inadequate

    Read the rest of this article »

    Posted on 18th February 2019

    SOLVENT IGNITED DURING FLOOR CLEANING WORKS

    Flammable solvent fire fought with water spreading fire further

    Read the rest of this article »

    Posted on 13th February 2019

    INEVITABLE COLLAPSE OF SCAFFOLD ON TO SCHOOL

    Scaffold not designed or installed to withstand foreseeable loads

    Read the rest of this article »

    Posted on 13th February 2019

    OIL DRUM EXPLODED DURING HOT CUTTING WORK

    Firm fined £400k after drum lid ejected causing loss of leg

    Read the rest of this article »

    Posted on 12th February 2019

    ROOFLIGHT FALL ON NUCLEAR POWER SITE

    Energy generating company and maintenance contractor fined

    Read the rest of this article »

    Posted on 12th February 2019

    DIRECTOR PROSECUTED AFTER 6METRE ROOF FALL

    Untrained worker fell through rooflight in fragile asbestos roof

    Read the rest of this article »

    Posted on 12th February 2019

    HSE ALERT: MILD STEEL WELDING CANCER RISK

    HSE announces enforcement action change based on new cancer evidence

    Read the rest of this article »

    Posted on 11th February 2019

    LORRY MOUNTED LIFTING OPERATION PROVED FATAL

    Steel staircase toppled from vehicle after sling snagged

    Read the rest of this article »

    Posted on 7th February 2019

    DIRECTOR AND BUSINESS IN COURT OVER DEATH

    Scaffold not priced for on domestic roof-line refurbishment work

    Read the rest of this article »

    Posted on 6th February 2019

    FRAGILE ROOFLIGHT HAZARD PROTECTION MISSING

    Two businesses prosecuted after a worker fell through a fragile rooflight

    Read the rest of this article »

    Posted on 5th February 2019

    STRUCTURAL SAFETY BODY LATEST NEWSLETTER

    CROSS publishes reports and expert comment on a range of issues

    Read the rest of this article »

    Posted on 4th February 2019

    FINGERS CRUSHED BY METAL FOLDING MACHINE

    Steel cladding firm fined £600k over failure guard access to danger

    Read the rest of this article »

    Posted on 4th February 2019

    ASBESTOS ILLEGALLY REMOVED AFTER SURVEY

    Surveyor pricing asbestos work found contractor jumped the gun

    Read the rest of this article »

    Posted on 4th February 2019
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    One Response to “BUILDERS AND ARCHITECTS LOOK SET FOR NEW DUTIES”

    1. CDM REGULATIONS 2014 PROPOSALS EXPLAINED | PP Construction Safety News Desk Says:

      […] Support for architects […]