• Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    CDM 2015 DESIGNERS ALERTED TO TRIBUNAL RESULT

    Revised regulations may pose dilemma for CDM ‘Principal Designers’

    Solicitor Ann Metherall of Burges Salmon has highlighted potential issues for designers under the long-awaited CDM 201x. See below.

    The Consultation Document is expected to propose scrapping the CDM Coordinator role and placing project preparation stage coordination with the new position of ‘Principal Designer’ (PD). The HSE consultation is now expected to start in April 2014.

    Ann Metherall suggests that design practices anticipating assuming the PD role should review their health and safety skills and training in advance of changes to the CDM Regulations.

    Industry guidance will explain Principle Designer duties

    A CDM Industry Guidance Steering Group is working on “a suite of industry guidance” aimed at smaller businesses which includes guidance on the role of the proposed Principal Designer under the new regulations.

    HSE state that the Group “faces a number of challenges” including time constraints adding that:

    “when public consultation on new Regulations commences, further iterations of the guidance will be needed to ensure it is consistent with the rest of the planned suite of guidance and the proposed CDM ‘L’ series publication.”

    The Steering Group programme of work anticipates the new CDM Regulations coming into force in April 2015 and is planning for the release of all Guidance by 31 October 2014

    Designers may be unwilling or unable to fulfil Coordinator role

    “The recent case of MWH UK Ltd v Wise [2014] EWHC 427 (Admin) has highlighted some issues that may result from directing the pre–construction co-ordination role away from CDM Co-ordinators to a Principal Designer.

    In MWH, the court reiterated that one of the CDM Co-ordinator’s duties is to check any pre-construction information and to advise the client regarding any gaps in that information. In this case, MWH UK Limited had failed to properly advise the client regarding the risk of the presence of asbestos and the absence of an asbestos survey.

    The court also held that the CDM Co-ordinator was the key safety advisor at the pre-construction stage of the project and was expected to be able to identify the nature and level of detail of the hazards to be addressed.

    The judge emphasised that the CDM Co-ordinator was not expected to have the expertise to make a detailed assessment of the hazards, but was expected to have sufficient expertise to understand whether they had been addressed, which was a matter of fact and degree in each case.

    This case will undoubtedly raise concerns amongst design professionals who, under the current proposals, will be required to fill the role of Principal Designer.

    Although the set of duties which will make up the role of Principal Designer are yet to be explicitly defined, it is clear from MWH that there are obligations currently performed by a CDM Co-ordinator that many designers would be unwilling or perhaps unable to fulfil.

    Design professionals might consider using the continued delay in introducing new CDM regulations to review their health and safety skills and training to identify the duties they are willing and competent to take on when the changes to CDM arrive.

    Latest Construction Health and Safety News

    HSE ENFORCEMENT WEEKLY UPDATE 16th MAY 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 16th May 2018

    CONSTRUCTION SECTOR DEATHS: THE ‘BIG THREE’

    HSE in-year fatalities for 2017/18 may indicate upward trend

    Read the rest of this article »

    Posted on 16th May 2018

    SCAFFOLDING SITE ACCIDENTS AT RECORD LOW

    NASC Annual Report reveals all time low in 2017 incidents

    Read the rest of this article »

    Posted on 14th May 2018

    DUMPER TRUCK HAND-BRAKE NOT MAINTAINED

    Workman injured when pinned against stack of concrete blocks

    Read the rest of this article »

    Posted on 14th May 2018

    SPARE POWER INTERLOCK KEY CAUSED DEATH

    Dangerous machinery safety precautions defeated for maintenance tasks

    Read the rest of this article »

    Posted on 10th May 2018

    HSE ENFORCEMENT WEEKLY UPDATE 9th MAY 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 9th May 2018

    COLLAPSED CAR PARK WAS UNDER REPAIR

    Rusted steel supports triggered collapse of fascia and floor

    Read the rest of this article »

    Posted on 8th May 2018

    DUMPER OVERTURN CAUSED FATAL INJURIES

    Precautions during spoil heap creation were inadequate

    Read the rest of this article »

    Posted on 8th May 2018

    HARDWOOD DUST CONTROL NOT MAINTAINED

    Manufacturer failed to examine and test local extraction system

    Read the rest of this article »

    Posted on 8th May 2018

    SCAFFOLD CONTRACTOR OVERLOOKED MAJOR HAZARD

    Well-known risk unidentified during scaffold erection project

    Read the rest of this article »

    Posted on 8th May 2018

    THREE FIRMS FINED £1/2M FOR FRAGILE RISK FAILURES

    Fall through rooflight hazard poorly planned and managed

    Read the rest of this article »

    Posted on 2nd May 2018

    CONTRACTORS IGNORED ASBESTOS RISK

    Asbestos pipe lagging worked on without licence and proper precautions

    Read the rest of this article »

    Posted on 2nd May 2018

    HSE ENFORCEMENT UPDATE 2nd MAY 2018

    hselogo1Prosecutions and enforcement notices update and analysis

    Read the rest of this article »

    Posted on 2nd May 2018

    SOFT LANDING BAGS TRIGGERED A FALL!

    Fall arrest bag thrown from scaffold took workman with bag

    Read the rest of this article »

    Posted on 1st May 2018

    FAILURE TO NOTIFY HSE PREVENTED INVESTIGATION

    Regulator prosecutes over RIDDOR non-compliance

    Read the rest of this article »

    Posted on 1st May 2018

    CLIENT AND CONTRACTOR TOGETHER IN COURT

    Fragile roof fall exposes client failure to manage project

    Read the rest of this article »

    Posted on 1st May 2018

    UNTRAINED DUMPER DRIVER SURVIVES OVERTURN

    Inadequate barriers plus lack of operator and manager training

    Read the rest of this article »

    Posted on 1st May 2018

    PROJECT CLIENT PROSECUTED UNDER CDM 2015

    Building demolished without suitable precautions to prevent danger

    Read the rest of this article »

    Posted on 1st May 2018

    LORRY RUNAWAY CLAIMED LIFE OF DRIVER

    Workman died after being drawn under trailer

    Read the rest of this article »

    Posted on 25th April 2018

    PETROL VAPOUR DANGER LEFT UNCONTROLLED

    Workman suffered severe burns during refuelling equipment

    Read the rest of this article »

    Posted on 25th April 2018

    HSE ENFORCEMENT UPDATE 25th APRIL 2018

    hselogo1Prosecutions and enforcement notices update and analysis

    Read the rest of this article »

    Posted on 25th April 2018

    ROPE ACCESS WORKER FELL THROUGH FRAGILE ROOF

    Prison sentence imposed on owner of rope access firm

    Read the rest of this article »

    Posted on 24th April 2018

    FIRMS FINED £2M OVER FALLING PIPE FATALITY

    Incorrect stacking of pipes triggered fall and crushing of workman

    Read the rest of this article »

    Posted on 20th April 2018

    DOMESTIC PROJECT PC HANDED JAIL TERM

    Workman fell from unprotected roof edge on dormer extension

    Read the rest of this article »

    Posted on 20th April 2018

    MAJOR CONTRACTOR ERRED ON FRAGILE ROOF RISK

    Firms fine £965,000 after painter fell through waiting room roof

    Read the rest of this article »

    Posted on 19th April 2018
    Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data