Turner Access Higher Safety Total Access
Total Access Ethentic Chipmunk Data
Chipmunk Data Turner Access Ethentic

CDM 2015 DESIGNERS ALERTED TO TRIBUNAL RESULT

Revised regulations may pose dilemma for CDM ‘Principal Designers’

Solicitor Ann Metherall of Burges Salmon has highlighted potential issues for designers under the long-awaited CDM 201x. See below.

The Consultation Document is expected to propose scrapping the CDM Coordinator role and placing project preparation stage coordination with the new position of ‘Principal Designer’ (PD). The HSE consultation is now expected to start in April 2014.

Ann Metherall suggests that design practices anticipating assuming the PD role should review their health and safety skills and training in advance of changes to the CDM Regulations.

Industry guidance will explain Principle Designer duties

A CDM Industry Guidance Steering Group is working on “a suite of industry guidance” aimed at smaller businesses which includes guidance on the role of the proposed Principal Designer under the new regulations.

HSE state that the Group “faces a number of challenges” including time constraints adding that:

“when public consultation on new Regulations commences, further iterations of the guidance will be needed to ensure it is consistent with the rest of the planned suite of guidance and the proposed CDM ‘L’ series publication.”

The Steering Group programme of work anticipates the new CDM Regulations coming into force in April 2015 and is planning for the release of all Guidance by 31 October 2014

Designers may be unwilling or unable to fulfil Coordinator role

“The recent case of MWH UK Ltd v Wise [2014] EWHC 427 (Admin) has highlighted some issues that may result from directing the pre–construction co-ordination role away from CDM Co-ordinators to a Principal Designer.

In MWH, the court reiterated that one of the CDM Co-ordinator’s duties is to check any pre-construction information and to advise the client regarding any gaps in that information. In this case, MWH UK Limited had failed to properly advise the client regarding the risk of the presence of asbestos and the absence of an asbestos survey.

The court also held that the CDM Co-ordinator was the key safety advisor at the pre-construction stage of the project and was expected to be able to identify the nature and level of detail of the hazards to be addressed.

The judge emphasised that the CDM Co-ordinator was not expected to have the expertise to make a detailed assessment of the hazards, but was expected to have sufficient expertise to understand whether they had been addressed, which was a matter of fact and degree in each case.

This case will undoubtedly raise concerns amongst design professionals who, under the current proposals, will be required to fill the role of Principal Designer.

Although the set of duties which will make up the role of Principal Designer are yet to be explicitly defined, it is clear from MWH that there are obligations currently performed by a CDM Co-ordinator that many designers would be unwilling or perhaps unable to fulfil.

Design professionals might consider using the continued delay in introducing new CDM regulations to review their health and safety skills and training to identify the duties they are willing and competent to take on when the changes to CDM arrive.

Latest Construction Health and Safety News

MAJOR CONTRACTORS LAUNCH H&S ALERT SYSTEM

Build UK members share information for effective prevention of harm

Read the rest of this article »

Posted on 19th July 2017

HSE ENFORCEMENT WEEKLY UPDATE 19th JULY 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 19th July 2017

STRUCTURAL SAFETY BODY LATEST NEWSLETTER

SCOSS publishes reports and expert comment on a range of issues

Read the rest of this article »

Posted on 18th July 2017

SAFE SYSTEM DEVISED BUT NOT IMPLEMENTED

Workman injured by goods falling from double-decked trailer

Read the rest of this article »

Posted on 18th July 2017

PREVENTION PLANNING REQUIRED FOR FRAGILE RISK

Fall arrest safety netting not used to mitigate fall consequences

Read the rest of this article »

Posted on 17th July 2017

MANAGEMENT OF FORMWORK NOT UP TO THE MARK

Erector fell 3m after access scaffold board failed under load

Read the rest of this article »

Posted on 17th July 2017

VIBRATION UNCONTROLLED & WORKERS UNINFORMED

Engineering firm fined £120,000 over hand-arm vibration risk

Read the rest of this article »

Posted on 14th July 2017

HSE ENFORCEMENT WEEKLY UPDATE 12th JULY 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 12th July 2017

SCAFFOLDER WAS UNTRAINED AND UNSUPERVISED

Contractor and director failed to train injured workman to CISRC scheme

Read the rest of this article »

Posted on 10th July 2017

WORKPLACE MANSLAUGHTER OUTCOMES SET TO RISE

Guidelines target gross negligence with serious disregard and cost-cutting

Read the rest of this article »

Posted on 7th July 2017

WORKMAN BURNT CLEANING WITH FLAMMABLE LIQUIDS

Flammable substance and unprotected electrical equipment trigger flash fire

Read the rest of this article »

Posted on 7th July 2017

PUWER FAILINGS AND INJURY END IN £1,900,000 FINE

Massive fine after workman suffers friction burns caused by conveyor

Read the rest of this article »

Posted on 7th July 2017

HSE ENFORCEMENT WEEKLY UPDATE 5th JULY 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 7th July 2017

HSE REPORTS CONSTRUCTION DEATHS AT RECORD LOW

hselogo1Fatalities decline whilst asbestos related mesothelioma deaths rise

Read the rest of this article »

Posted on 5th July 2017

CURSORY AND NEGLIGENT ASSESSMENT BY DIRECTOR

Building firm owner jailed after workman died in trench collapse

Read the rest of this article »

Posted on 3rd July 2017

UPDATE – DIRECTOR AND EXCAVATOR OPERATOR JAILED

Excavation collapse dangers ignored by director and digger operator

Read the rest of this article »

Posted on 3rd July 2017

HSE SAFETY ALERT: TRACK TENSIONING INCIDENT

hselogo1Workman died from hydraulic injection injury whilst tensioning track

Read the rest of this article »

Posted on 30th June 2017

OXYGEN PIPE EXPLOSION CAUSED SEVERE BURNS

Components used containing materials unsuitable for use with oxygen

Read the rest of this article »

Posted on 30th June 2017

HSE ENFORCEMENT WEEKLY UPDATE 28th JUNE 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 28th June 2017

ROOF FALL CAUSES LIFE CHANGING INJURIES

Inadequate planning and absence of necessary equipment caused fall

Read the rest of this article »

Posted on 25th June 2017

LIFT PLANNING AND CONTROL FOUND WANTING

Female building worker struck by scaffold fittings tipped from stillage

Read the rest of this article »

Posted on 25th June 2017

FATALITY: CRANE COLLAPSE ON HOMES PROJECT

Two workmen die in crane collapse in Crewe

Read the rest of this article »

Posted on 23rd June 2017

BUILD UK EXPLAINS PROJECT H&S TRAINING STANDARD

UK contractors clarify skill cards needed on CDM 2015 projects

Read the rest of this article »

Posted on 21st June 2017

HSE ENFORCEMENT WEEKLY UPDATE 21 JUNE 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 21st June 2017

CIVILS FIRMS PAYS PRICE OVER PUBLIC DANGER

Fencing wire struck member of public relaxing in own garden

Read the rest of this article »

Posted on 20th June 2017
Turner Access Chipmunk Data
Total Access Ethentic
Higher Safety Turner Access