• Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    CDM 2015 DESIGNERS ALERTED TO TRIBUNAL RESULT

    Revised regulations may pose dilemma for CDM ‘Principal Designers’

    Solicitor Ann Metherall of Burges Salmon has highlighted potential issues for designers under the long-awaited CDM 201x. See below.

    The Consultation Document is expected to propose scrapping the CDM Coordinator role and placing project preparation stage coordination with the new position of ‘Principal Designer’ (PD). The HSE consultation is now expected to start in April 2014.

    Ann Metherall suggests that design practices anticipating assuming the PD role should review their health and safety skills and training in advance of changes to the CDM Regulations.

    Industry guidance will explain Principle Designer duties

    A CDM Industry Guidance Steering Group is working on “a suite of industry guidance” aimed at smaller businesses which includes guidance on the role of the proposed Principal Designer under the new regulations.

    HSE state that the Group “faces a number of challenges” including time constraints adding that:

    “when public consultation on new Regulations commences, further iterations of the guidance will be needed to ensure it is consistent with the rest of the planned suite of guidance and the proposed CDM ‘L’ series publication.”

    The Steering Group programme of work anticipates the new CDM Regulations coming into force in April 2015 and is planning for the release of all Guidance by 31 October 2014

    Designers may be unwilling or unable to fulfil Coordinator role

    “The recent case of MWH UK Ltd v Wise [2014] EWHC 427 (Admin) has highlighted some issues that may result from directing the pre–construction co-ordination role away from CDM Co-ordinators to a Principal Designer.

    In MWH, the court reiterated that one of the CDM Co-ordinator’s duties is to check any pre-construction information and to advise the client regarding any gaps in that information. In this case, MWH UK Limited had failed to properly advise the client regarding the risk of the presence of asbestos and the absence of an asbestos survey.

    The court also held that the CDM Co-ordinator was the key safety advisor at the pre-construction stage of the project and was expected to be able to identify the nature and level of detail of the hazards to be addressed.

    The judge emphasised that the CDM Co-ordinator was not expected to have the expertise to make a detailed assessment of the hazards, but was expected to have sufficient expertise to understand whether they had been addressed, which was a matter of fact and degree in each case.

    This case will undoubtedly raise concerns amongst design professionals who, under the current proposals, will be required to fill the role of Principal Designer.

    Although the set of duties which will make up the role of Principal Designer are yet to be explicitly defined, it is clear from MWH that there are obligations currently performed by a CDM Co-ordinator that many designers would be unwilling or perhaps unable to fulfil.

    Design professionals might consider using the continued delay in introducing new CDM regulations to review their health and safety skills and training to identify the duties they are willing and competent to take on when the changes to CDM arrive.

    Latest Construction Health and Safety News

    HSE TO OVERSEE NEW BUILDING SAFETY REGIME

    Government to deliver biggest change in building safety for a generation

    Read the rest of this article »

    Posted on 21st January 2020

    CONTRACTS MANAGER HANDED TWO YEAR PRISON TERM

    Safety fall arrest netting would have saved life of deceased workman

    Read the rest of this article »

    Posted on 15th January 2020

    WORKER FATALLY INJURED BY CONCRETE BEAM

    Lifting operation not properly planned, managed and supervised

    Read the rest of this article »

    Posted on 15th January 2020

    TREE FELLING OPERATIONS LACKED DEFINED COMMS

    Workman struck by falling tree inside “normal” exclusion zone

    Read the rest of this article »

    Posted on 14th January 2020

    CONTRACTOR ARRESTED OVER WELFARE FAILINGS

    Recalcitrant sole trader failed to attend court hearing

    Read the rest of this article »

    Posted on 14th January 2020

    MAJOR DEMOLITION CONTRACTOR FINED £500,000

    Collapse of concrete slab caused death of worker and excavator fall

    Read the rest of this article »

    Posted on 14th January 2020

    FALL FROM LADDER WHILST CARRYING BUCKET

    Contractor failed to provide basic safe lifting aids

    Read the rest of this article »

    Posted on 14th January 2020

    FAILURE TO COMPLY WITH HSE NOTICE PROVES COSTLY

    Director given suspended jail term and company fined £60,000

    Read the rest of this article »

    Posted on 14th January 2020

    DEVELOPER FAILED TO PLAN AND CHECK COMPETENCE

    Fall caused by ad-hoc working methods and lack of monitoring

    Read the rest of this article »

    Posted on 14th January 2020

    CYLINDER LEAK TEST CAUSED FATAL INJURIES

    Corrosion inhibitor triggered failure and shrapnel ejection

    Read the rest of this article »

    Posted on 14th January 2020

    FESTIVE GREETINGS TO ALL OUR READERS

    Read the rest of this article »

    Posted on 20th December 2019

    JAIL TERM FOLLOWS ROUTINE HSE SPOT CHECK

    Director of a roofing firm handed a suspended prison sentence

    Read the rest of this article »

    Posted on 19th December 2019

    TEENAGER FELL 3M DURING BLOCK AND BEAM WORK

    Workers uninstructed and left to devise own safe system of work

    Read the rest of this article »

    Posted on 19th December 2019

    PARCEL CARRIER FINED HEAVILY OVER FLT INCIDENT

    Reversing fork lift lacked segregation from pedestrians

    Read the rest of this article »

    Posted on 18th December 2019

    CONTRACTOR FINED OVER FLOOR OPENING FALL

    Thorough risk assessment and edge protection were both inadequate

    Read the rest of this article »

    Posted on 18th December 2019

    THREE WORKERS “CARRIED ALONG” IN SEWER INCIDENT

    Mentally affected and one man treated for long-term traumatic stress

    Read the rest of this article »

    Posted on 11th December 2019

    SOLAR FIRM AND DIRECTOR SENTENCED OVER DEATH

    Brother of business owner died in fall during panel installation

    Read the rest of this article »

    Posted on 10th December 2019

    DIRECTOR AND COMPANY FINED FOR ASBESTOS RISK

    HSE refurbishment campaign inspection revealed asbestos offences

    Read the rest of this article »

    Posted on 10th December 2019

    BULK BAG COLLAPSE CAUSED BY UNSAFE STACKING

    Bulk bag collapsed onto workman when struck by fork lift

    Read the rest of this article »

    Posted on 9th December 2019

    INTERLOCKED GUARD NOT WORKING TO ISOLATE POWER

    Two workmen seriously injured when plant started unexpectedly

    Read the rest of this article »

    Posted on 9th December 2019

    STREET FURNITURE RISK TO PUBLIC FINED £1.4M

    Council prosecuted following injury to child playing on hinged bollard

    Read the rest of this article »

    Posted on 9th December 2019

    WORKMEN SUFFER SERIOUS BURNS FROM CABLE STRIKE

    Assessment and system of work failed to appreciate electrical risk

    Read the rest of this article »

    Posted on 29th November 2019

    LADDERS WERE INAPPROPRIATE FOR WORK ON ROOF

    Workman paralysed after falling whilst installing roof ladder

    Read the rest of this article »

    Posted on 28th November 2019

    FIRM FAILED TO MANAGE EXHAUST VENTILATION

    HSE enforcement notices on wood dust and welding fume ignored

    Read the rest of this article »

    Posted on 27th November 2019

    RECALCITRANT DIRECTOR BARRED FROM OFFICE

    Dangerous telehandler used despite earlier fatality and enforcement

    Read the rest of this article »

    Posted on 25th November 2019
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data