    WINDOW REPLACEMENT DISTURBED SCHOOL ASBESTOS

    Presence of asbestos kept from company workers

    Frames Conservatories Direct Ltd (FCDL) has been prosecuted after workers were exposed to asbestos containing material during work to replace window units at a school in Bury St Edmunds.

    FCDL informed Westley Middle school that asbestos panels would be removed by registered contractors and disposed of in the correct manner over the school summer holidays in 2012.

    However, Bury St Edmunds Magistrates heard that the company was not licensed to work with asbestos. Furthermore, employees undertaking the work were not told they would be handling asbestos, nor did they use any control measures to prevent the spread of fibres.

    HSE investigated after being alerted both by FCDL employees and the school’s headteacher.

    The court heard that concerns were raised when other contractors noticed suspect material in a floor void and consulted a licensed asbestos contractor who then visited the school.

    The contractor saw window panels being removed and notified FCDL employees that they were handling materials likely to contain asbestos. Work was immediately stopped and the area sealed off.

    A licensed contractor undertook an extensive programme of cleaning under strictly controlled conditions in all affected areas of the school. Once completed, air tests were carried out and the areas certified safe for re-occupation.

    The school spent some £111,495 on environmental cleaning and replacement of teaching aids and other items that had to be destroyed because of contamination.

    Exposed to levels many times in excess of limit

    Frames Conservatories Direct Ltd, of Barton Retail Park, Barton Road, Bury St Edmunds, was fined a total of £24,000 and ordered to pay £10,571 in costs after pleading guilty to breaching regulations 8(1) and 11(1) of the Control of Asbestos Regulations 2012.

    Speaking after the hearing, HSE Inspector Elizabeth Fowle said:

    “This incident has been extremely stressful for those affected and has also been disruptive and costly for the school. All of this could have been avoided if the company had simply asked, ‘Should we be doing this work with asbestos?’

    Frames Conservatories Direct Ltd knew the window panels they planned to remove contained asbestos but wrongly decided they would work with the material. They did not tell their employees about the presence of asbestos or specify any safety measures.

    As a result, they exposed workers to asbestos levels many times in excess of the Control Limit. The long term health risks associated with inhalation of asbestos fibres include lung cancer and mesothelioma.

    It was extremely fortunate that this work took place during the school holiday which meant that there were no pupils on site and few school staff.”

    Latest Construction Health and Safety News

    HSE ENFORCEMENT WEEKLY UPDATE 13th JUNE 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 13th June 2018

    DIRECTOR FAILED COMPLY WITH HSE PROHIBITION

    Precautions not taken to prevent excavation collapse and falling

    Read the rest of this article »

    Posted on 11th June 2018

    SCAFFOLD NOT TO INDUSTRY STANDARD OR DESIGN

    Specialist and contractor in court over unsafe work at height

    Read the rest of this article »

    Posted on 7th June 2018

    ROAD WORKER RUN OVER BY ROAD ROLLER

    Reversing alarm not working and warning light not fitted

    Read the rest of this article »

    Posted on 5th June 2018

    CLIENT AND SURVEYOR FINED OVER ASBESTOS SURVEY

    Refurbishment and demolition asbestos survey proved inadequate

    Read the rest of this article »

    Posted on 5th June 2018

    FATALITY: ROAD WORKER DRAGGED ALONG ROAD

    Night shift worker loses life when struck by road sweeping vehicle

    Read the rest of this article »

    Posted on 3rd June 2018

    CDM PRINCIPAL DESIGNERS AVOID HSE ENFORCEMENT

    Regulator enforcement database reveals few notices involve CDM PDs

    Read the rest of this article »

    Posted on 3rd June 2018

    PROPERTY MANAGERS FINED WITH CONTRACTOR

    Defendants failed to check for asbestos during soffit replacement works

    Read the rest of this article »

    Posted on 29th May 2018

    EXCAVATION CAUSED RETAINING WALL COLLAPSE

    Precautions not taken to secure stability of free-standing wall

    Read the rest of this article »

    Posted on 29th May 2018

    OVERHEAD CABLE STRIKE FIRM FINED £500,000+

    Inadequate system caused risk of harm despite lack of worker injury

    Read the rest of this article »

    Posted on 29th May 2018

    CDM 2015 PRINCIPAL DESIGNER FINED OVER FIRE RISK

    PD and PC failed to comply with CDM 2015 responsibilities

    Read the rest of this article »

    Posted on 23rd May 2018

    SENTENCING GUIDELINES UNDER THE MICROSCOPE

    Lawyer argues guidelines undermine reduction in ‘regulatory burden’

    Read the rest of this article »

    Posted on 23rd May 2018

    PANEL STRUCK WORKMAN DURING LIFTING OPERATION

    Third party contractor falls victim of poor lift planning

    Read the rest of this article »

    Posted on 21st May 2018

    DIRECTOR LED HAZARDOUS WORK AT HEIGHT

    Three occasions when work lacked suitable and sufficient precautions

    Read the rest of this article »

    Posted on 21st May 2018

    RISK ASSESSED BUT CONTROLS FOUND WANTING

    Joiner fell through unprotected opening on roof of new building

    Read the rest of this article »

    Posted on 21st May 2018

    RIBA CRITICAL OF HACKITT REVIEW FINAL REPORT

    High rise residential review dismissed as “major missed opportunity”

    Read the rest of this article »

    Posted on 21st May 2018

    CONSTRUCTION SECTOR DEATHS: THE ‘BIG THREE’

    HSE in-year fatalities for 2017/18 may indicate upward trend

    Read the rest of this article »

    Posted on 16th May 2018

    SCAFFOLDING SITE ACCIDENTS AT RECORD LOW

    NASC Annual Report reveals all time low in 2017 incidents

    Read the rest of this article »

    Posted on 14th May 2018

    DUMPER TRUCK HAND-BRAKE NOT MAINTAINED

    Workman injured when pinned against stack of concrete blocks

    Read the rest of this article »

    Posted on 14th May 2018

    SPARE POWER INTERLOCK KEY CAUSED DEATH

    Dangerous machinery safety precautions defeated for maintenance tasks

    Read the rest of this article »

    Posted on 10th May 2018

    COLLAPSED CAR PARK WAS UNDER REPAIR

    Rusted steel supports triggered collapse of fascia and floor

    Read the rest of this article »

    Posted on 8th May 2018

    DUMPER OVERTURN CAUSED FATAL INJURIES

    Precautions during spoil heap creation were inadequate

    Read the rest of this article »

    Posted on 8th May 2018

    HARDWOOD DUST CONTROL NOT MAINTAINED

    Manufacturer failed to examine and test local extraction system

    Read the rest of this article »

    Posted on 8th May 2018

    SCAFFOLD CONTRACTOR OVERLOOKED MAJOR HAZARD

    Well-known risk unidentified during scaffold erection project

    Read the rest of this article »

    Posted on 8th May 2018

    THREE FIRMS FINED £1/2M FOR FRAGILE RISK FAILURES

    Fall through rooflight hazard poorly planned and managed

    Read the rest of this article »

    Posted on 2nd May 2018
    Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data