Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    WINDOW REPLACEMENT DISTURBED SCHOOL ASBESTOS

    Presence of asbestos kept from company workers

    Frames Conservatories Direct Ltd (FCDL) has been prosecuted after workers were exposed to asbestos containing material during work to replace window units at a school in Bury St Edmunds.

    FCDL informed Westley Middle school that asbestos panels would be removed by registered contractors and disposed of in the correct manner over the school summer holidays in 2012.

    However, Bury St Edmunds Magistrates heard that the company was not licensed to work with asbestos. Furthermore, employees undertaking the work were not told they would be handling asbestos, nor did they use any control measures to prevent the spread of fibres.

    HSE investigated after being alerted both by FCDL employees and the school’s headteacher.

    The court heard that concerns were raised when other contractors noticed suspect material in a floor void and consulted a licensed asbestos contractor who then visited the school.

    The contractor saw window panels being removed and notified FCDL employees that they were handling materials likely to contain asbestos. Work was immediately stopped and the area sealed off.

    A licensed contractor undertook an extensive programme of cleaning under strictly controlled conditions in all affected areas of the school. Once completed, air tests were carried out and the areas certified safe for re-occupation.

    The school spent some £111,495 on environmental cleaning and replacement of teaching aids and other items that had to be destroyed because of contamination.

    Exposed to levels many times in excess of limit

    Frames Conservatories Direct Ltd, of Barton Retail Park, Barton Road, Bury St Edmunds, was fined a total of £24,000 and ordered to pay £10,571 in costs after pleading guilty to breaching regulations 8(1) and 11(1) of the Control of Asbestos Regulations 2012.

    Speaking after the hearing, HSE Inspector Elizabeth Fowle said:

    “This incident has been extremely stressful for those affected and has also been disruptive and costly for the school. All of this could have been avoided if the company had simply asked, ‘Should we be doing this work with asbestos?’

    Frames Conservatories Direct Ltd knew the window panels they planned to remove contained asbestos but wrongly decided they would work with the material. They did not tell their employees about the presence of asbestos or specify any safety measures.

    As a result, they exposed workers to asbestos levels many times in excess of the Control Limit. The long term health risks associated with inhalation of asbestos fibres include lung cancer and mesothelioma.

    It was extremely fortunate that this work took place during the school holiday which meant that there were no pupils on site and few school staff.”

    Latest Construction Health and Safety News

    CONCRETE EJECTED BY PUMPING UNIT CLAIMED LIFE

    Company and director failed to train and supervise pumping operations

    Read the rest of this article »

    Posted on 5th December 2018

    HSE ENFORCEMENT WEEKLY UPDATE 5th DEC 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 5th December 2018

    REFRESHED GUIDANCE ON FITNESS TO OPERATE PLANT

    Construction plant medical fitness Good Practice Guide

    Read the rest of this article »

    Posted on 4th December 2018

    MAJOR CONTRACTOR & LUL USED UNSAFE SYSTEM

    Work method to eliminate moving vehicle hazard not adopted

    Read the rest of this article »

    Posted on 4th December 2018

    OVERTURNING LORRY CAUSED DEATH OF DRIVER

    Groundworks project stockpiling arrangements not properly managed

    Read the rest of this article »

    Posted on 3rd December 2018

    FORTH BRIDGE LIFTING OPERATION NOT PLANNED

    Major project PC failed to plan, supervise and carry out lift safely

    Read the rest of this article »

    Posted on 3rd December 2018

    DEVELOPER FAILED ON ASBESTOS ASSESSMENT

    HSE inspection revealed refurb works without asbestos survey

    Read the rest of this article »

    Posted on 28th November 2018

    POST DRIVER HAMMER CRUSHED HAND OF WORKMAN

    Unsafe system of work for vehicle crash barrier installation

    Read the rest of this article »

    Posted on 28th November 2018

    WORKER FELL FROM LOFT THROUGH CEILING

    Major house builder lacked understanding of loft fragile surfaces risk

    Read the rest of this article »

    Posted on 28th November 2018

    NEW SITE DUMPER SAFETY GUIDANCE ISSUED

    Construction plant sector concerns prompts CPA consults on draft

    Read the rest of this article »

    Posted on 28th November 2018

    CCTV INSTALLER FELL THROUGH FRAGILE ROOFLIGHT

    Contractor failed to properly plan and control the risks

    Read the rest of this article »

    Posted on 28th November 2018

    VISITOR DIED FALLING INTO CONCEALED BASEMENT

    Contractor failed to protect basement void on domestic project

    Read the rest of this article »

    Posted on 28th November 2018

    RACKING FALL REVEALED UNSAFE SYSTEM OF WORK

    European firm fined £300,000 after UK sub-contractor employee fell

    Read the rest of this article »

    Posted on 18th November 2018

    FAILURE TO ACT ON VIBRATION AND SILICA HAZARDS

    Worker health put at risk during stripping of furnace lining

    Read the rest of this article »

    Posted on 18th November 2018

    MAJOR FM FIRM FAILED TO MAINTAIN BACK-UP POWER

    Power loss at laboratory site created potential risk from biological agents

    Read the rest of this article »

    Posted on 18th November 2018

    IGNORING HSE PROHIBITIONS COST FIRM £250,000

    CDM 2015 and work at height requirements repeatedly breached

    Read the rest of this article »

    Posted on 16th November 2018

    ROOF COLLAPSED UNDER EXCESS LOADING

    Director and company fined over roof design failures

    Read the rest of this article »

    Posted on 11th November 2018

    FORK LIFT OVERTURNED IN SCAFFOLDING YARD

    Untrained operator suffered life changing crush injuries

    Read the rest of this article »

    Posted on 10th November 2018

    STRUCTURAL SAFETY ALERT: EFFECTS OF SCALE

    SCOSS issues alert after concerns disclosed over ‘large structures’

    Read the rest of this article »

    Posted on 7th November 2018

    ASBESTOS EXPOSED BY UNTRAINED WORKERS

    Contractor failed to act properly despite HSE intervention

    Read the rest of this article »

    Posted on 7th November 2018

    GAS MAIN STRIKE REPAIR CAUSED SEVERE BURNS

    Contractor excavator damage to gas pipe ends in £1.2m fine

    Read the rest of this article »

    Posted on 7th November 2018

    REBAR FELL FROM FLT IN UNSAFE LIFTING OPERATION

    Multiple fractures caused by inappropriate use of fork lift

    Read the rest of this article »

    Posted on 7th November 2018

    POORLY PLANNED LIFT DISMANTLE INJURED WORKMAN

    Counterweight or suspension rope struck worker in lift shaft

    Read the rest of this article »

    Posted on 1st November 2018

    CONSTRUCTION INJURY AND ILL-HEALTH 2017/18

    hselogo1Fatal injury rate in long term decline whilst ill-health trend flat lining

    Read the rest of this article »

    Posted on 1st November 2018

    DUMPER DRIVEN INTO OPEN UNGUARDED EXCAVATION

    Contractor fined over absence of suitable excavation / dumper precautions

    Read the rest of this article »

    Posted on 1st November 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic