Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    PC FOCUSED ON ‘PAPER’ RATHER THAN ‘PRECAUTIONS’

    Temporary platform in shaft collapsed causing 10m fall on major project

    St George South London Ltd (SGSL) has today (9th Jan) been sentenced after a construction worker was seriously injured when a temporary work platform “disintegrated” during a failed lifting operation on a major London project. SGSL was the project principal contractor.

    Noel Doyle, aged 32, suffered a shattered right elbow, broken vertebrae, pelvis and ribs, and damage to internal organs when he fell some 10m at St George Wharf in Vauxhall on 10 February 2009. He required extensive treatment and physiotherapy, has limited movement in his right arm and is no longer able to work in construction.

    Southwark Crown Court heard that Mr Doyle was helping two colleagues, including a foreman, to raise a temporary work platform inside a concrete stairwell shaft within a building under construction. The platform was lifted from one floor to another by a crane using four lifting chains before being locked in place in the shaft to enable the next level to be constructed.

    The platform was raised to a new level when the crane operator was inadvertently instructed by the foreman to move away whilst one of the lifting chains was still attached to the platform which then disintegrated. Two workmen managed to jump to safety but Mr Doyle was unable to do so. He fell into the shaft and parts of the platform and equipment came “raining down” on him.

    HSE investigators found that SGSL failed to properly plan and manage the construction work so as to avoid risks to safety. The company failed to ensure that contractors developed and implemented safe systems of work, particularly in relation to the management and use of temporary works.

    PC inspections superficial and did not identify significant systemic failures

    St George South London Ltd, of St George House, The Boulevard, Imperial Wharf, Fulham, was fined £50,000 and ordered to pay £27,386 in costs after pleading guilty to a breach of the Construction (Design and Management) Regulations 2007. The company subcontracted for the construction of the reinforced concrete frame of the building was also prosecuted over the incident.

    After sentencing HSE Inspector Loraine Charles said:

    “It is vitally important that principal contractors appreciate that managing and monitoring subcontractors involves more than merely requiring them to provide risk assessments and method statements, and then carrying out basic hazard spotting inspections.

    They need to make sure that there is a proper assessment of the content of the documentation provided to ensure that they make sense and properly address the risks associated with the work being undertaken.

    In this case, St George South London concerned themselves more with the existence than the content of the subcontractor safety documents, and although they themselves carried out regular site safety inspections, all of these were superficial and failed to identify significant systemic failures.” 

     

     

     

    Latest Construction Health and Safety News

    FESTIVE GREETINGS TO ALL OUR READERS

    Read the rest of this article »

    Posted on 18th December 2018

    POSITIVE STORY ON FRAGILE SURFACE HAZARDS

    Major roofing contractor testifies to working from below roof

    Read the rest of this article »

    Posted on 18th December 2018

    LEISURE CENTRE USER FELL ILL AFTER SHOWER USE

    Legionella risk assessment and control measures found wanting

    Read the rest of this article »

    Posted on 18th December 2018

    STONE CUTTING MACHINE GUARDS FAILED HSE TEST

    Precautions taken following HSE enforcement fell into disuse

    Read the rest of this article »

    Posted on 18th December 2018

    ROOFWORK CREATED CARBON MONOXIDE RISK

    Falling rubble damaged and blocked home chimney flue

    Read the rest of this article »

    Posted on 18th December 2018

    HSE ENFORCEMENT WEEKLY UPDATE 19th DEC 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 18th December 2018

    HSE SAFETY ALERT: TOWER CRANE BRAKES

    Collapse of tower crane jib in high winds prompts HSE warning

    Read the rest of this article »

    Posted on 11th December 2018

    VISITING ENGINEER CRUSHED BY SCAFFOLD TUBES

    Principal contractor “signed off” contractor storage arrangements

    Read the rest of this article »

    Posted on 11th December 2018

    CONCRETE EJECTED BY PUMPING UNIT CLAIMED LIFE

    Company and director failed to train and supervise pumping operations

    Read the rest of this article »

    Posted on 5th December 2018

    REFRESHED GUIDANCE ON FITNESS TO OPERATE PLANT

    Construction plant medical fitness Good Practice Guide

    Read the rest of this article »

    Posted on 4th December 2018

    MAJOR CONTRACTOR & LUL USED UNSAFE SYSTEM

    Work method to eliminate moving vehicle hazard not adopted

    Read the rest of this article »

    Posted on 4th December 2018

    OVERTURNING LORRY CAUSED DEATH OF DRIVER

    Groundworks project stockpiling arrangements not properly managed

    Read the rest of this article »

    Posted on 3rd December 2018

    FORTH BRIDGE LIFTING OPERATION NOT PLANNED

    Major project PC failed to plan, supervise and carry out lift safely

    Read the rest of this article »

    Posted on 3rd December 2018

    DEVELOPER FAILED ON ASBESTOS ASSESSMENT

    HSE inspection revealed refurb works without asbestos survey

    Read the rest of this article »

    Posted on 28th November 2018

    POST DRIVER HAMMER CRUSHED HAND OF WORKMAN

    Unsafe system of work for vehicle crash barrier installation

    Read the rest of this article »

    Posted on 28th November 2018

    WORKER FELL FROM LOFT THROUGH CEILING

    Major house builder lacked understanding of loft fragile surfaces risk

    Read the rest of this article »

    Posted on 28th November 2018

    NEW SITE DUMPER SAFETY GUIDANCE ISSUED

    Construction plant sector concerns prompts CPA consults on draft

    Read the rest of this article »

    Posted on 28th November 2018

    CCTV INSTALLER FELL THROUGH FRAGILE ROOFLIGHT

    Contractor failed to properly plan and control the risks

    Read the rest of this article »

    Posted on 28th November 2018

    VISITOR DIED FALLING INTO CONCEALED BASEMENT

    Contractor failed to protect basement void on domestic project

    Read the rest of this article »

    Posted on 28th November 2018

    RACKING FALL REVEALED UNSAFE SYSTEM OF WORK

    European firm fined £300,000 after UK sub-contractor employee fell

    Read the rest of this article »

    Posted on 18th November 2018

    FAILURE TO ACT ON VIBRATION AND SILICA HAZARDS

    Worker health put at risk during stripping of furnace lining

    Read the rest of this article »

    Posted on 18th November 2018

    MAJOR FM FIRM FAILED TO MAINTAIN BACK-UP POWER

    Power loss at laboratory site created potential risk from biological agents

    Read the rest of this article »

    Posted on 18th November 2018

    IGNORING HSE PROHIBITIONS COST FIRM £250,000

    CDM 2015 and work at height requirements repeatedly breached

    Read the rest of this article »

    Posted on 16th November 2018

    ROOF COLLAPSED UNDER EXCESS LOADING

    Director and company fined over roof design failures

    Read the rest of this article »

    Posted on 11th November 2018

    FORK LIFT OVERTURNED IN SCAFFOLDING YARD

    Untrained operator suffered life changing crush injuries

    Read the rest of this article »

    Posted on 10th November 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic