Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    RESEARCH REVEALS LIMITS TO ASBESTOS ENCLOSURES

    Enclosure ventilation when removing ceiling tiles dependent upon void volume

    When removing high-risk asbestos-containing materials the work should be carried out inside a specially constructed ventilated enclosure to prevent the spread of asbestos outside the work area.

    HSE commissioned research to investigate the factors that affect the containment potential of temporary ventilated enclosures. This work entitled RR988 – Ventilation of enclosures for removal of asbestos containing materials considered:

    • the way that air moves within ventilated enclosures;
    • how the construction of enclosures and airlocks affects air movement and containment;
    • how the positioning of extraction points and air inlets affect air movement and containment;
    • relationship between air flow and negative pressure, and containment; and
    • factors which affect the ability of enclosures to contain asbestos, such as unplanned openings.

    In addition, the effect of removing ceiling tiles and the size of ceiling void relative to the enclosure was investigated.

    Celing voids may need to be considered contaminated

    The effect of removing ceiling tiles was found to be dependent upon the volume of the void above the false ceiling compared to the enclosure. The researchers concluded that:

    “When the volume of the void was much larger than the enclosure, for instance a small enclosure in a large room where the void is unsealed, removing a ceiling tile caused ΔP and the airlock door deflection to fall to zero.

    Tracer gas and smoke tests showed that once the tile was removed air was able to enter the void and therefore potentially spread contamination to surrounding areas.

    When the volume of the void was less than the enclosure, removal of a ceiling tile caused a reduction of ΔP but the airlock door deflection was unchanged. Tracer gas and smoke tests showed that once the pressure between the two spaces had equalised air could move freely between the two. This means that in this situation the whole void would potentially be contaminated and would require cleaning after completion of the work.

    These results were interesting and should be considered, especially in cases where the void is small compared to the enclosure. The results have shown that once the tile is removed the void becomes part of the enclosure and contaminated air can move freely between the spaces. This means that upon completion of the work the whole void should be considered to be contaminated and be cleaned. ((ΔP) is pressure difference between the interior of the enclosure and the surrounding space)” 

     

    Latest Construction Health and Safety News

    HSE ENFORCEMENT WEEKLY UPDATE 12th DEC 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 12th December 2018

    HSE SAFETY ALERT: TOWER CRANE BRAKES

    Collapse of tower crane jib in high winds prompts HSE warning

    Read the rest of this article »

    Posted on 11th December 2018

    VISITING ENGINEER CRUSHED BY SCAFFOLD TUBES

    Principal contractor “signed off” contractor storage arrangements

    Read the rest of this article »

    Posted on 11th December 2018

    CONCRETE EJECTED BY PUMPING UNIT CLAIMED LIFE

    Company and director failed to train and supervise pumping operations

    Read the rest of this article »

    Posted on 5th December 2018

    REFRESHED GUIDANCE ON FITNESS TO OPERATE PLANT

    Construction plant medical fitness Good Practice Guide

    Read the rest of this article »

    Posted on 4th December 2018

    MAJOR CONTRACTOR & LUL USED UNSAFE SYSTEM

    Work method to eliminate moving vehicle hazard not adopted

    Read the rest of this article »

    Posted on 4th December 2018

    OVERTURNING LORRY CAUSED DEATH OF DRIVER

    Groundworks project stockpiling arrangements not properly managed

    Read the rest of this article »

    Posted on 3rd December 2018

    FORTH BRIDGE LIFTING OPERATION NOT PLANNED

    Major project PC failed to plan, supervise and carry out lift safely

    Read the rest of this article »

    Posted on 3rd December 2018

    DEVELOPER FAILED ON ASBESTOS ASSESSMENT

    HSE inspection revealed refurb works without asbestos survey

    Read the rest of this article »

    Posted on 28th November 2018

    POST DRIVER HAMMER CRUSHED HAND OF WORKMAN

    Unsafe system of work for vehicle crash barrier installation

    Read the rest of this article »

    Posted on 28th November 2018

    WORKER FELL FROM LOFT THROUGH CEILING

    Major house builder lacked understanding of loft fragile surfaces risk

    Read the rest of this article »

    Posted on 28th November 2018

    NEW SITE DUMPER SAFETY GUIDANCE ISSUED

    Construction plant sector concerns prompts CPA consults on draft

    Read the rest of this article »

    Posted on 28th November 2018

    CCTV INSTALLER FELL THROUGH FRAGILE ROOFLIGHT

    Contractor failed to properly plan and control the risks

    Read the rest of this article »

    Posted on 28th November 2018

    VISITOR DIED FALLING INTO CONCEALED BASEMENT

    Contractor failed to protect basement void on domestic project

    Read the rest of this article »

    Posted on 28th November 2018

    RACKING FALL REVEALED UNSAFE SYSTEM OF WORK

    European firm fined £300,000 after UK sub-contractor employee fell

    Read the rest of this article »

    Posted on 18th November 2018

    FAILURE TO ACT ON VIBRATION AND SILICA HAZARDS

    Worker health put at risk during stripping of furnace lining

    Read the rest of this article »

    Posted on 18th November 2018

    MAJOR FM FIRM FAILED TO MAINTAIN BACK-UP POWER

    Power loss at laboratory site created potential risk from biological agents

    Read the rest of this article »

    Posted on 18th November 2018

    IGNORING HSE PROHIBITIONS COST FIRM £250,000

    CDM 2015 and work at height requirements repeatedly breached

    Read the rest of this article »

    Posted on 16th November 2018

    ROOF COLLAPSED UNDER EXCESS LOADING

    Director and company fined over roof design failures

    Read the rest of this article »

    Posted on 11th November 2018

    FORK LIFT OVERTURNED IN SCAFFOLDING YARD

    Untrained operator suffered life changing crush injuries

    Read the rest of this article »

    Posted on 10th November 2018

    STRUCTURAL SAFETY ALERT: EFFECTS OF SCALE

    SCOSS issues alert after concerns disclosed over ‘large structures’

    Read the rest of this article »

    Posted on 7th November 2018

    ASBESTOS EXPOSED BY UNTRAINED WORKERS

    Contractor failed to act properly despite HSE intervention

    Read the rest of this article »

    Posted on 7th November 2018

    GAS MAIN STRIKE REPAIR CAUSED SEVERE BURNS

    Contractor excavator damage to gas pipe ends in £1.2m fine

    Read the rest of this article »

    Posted on 7th November 2018

    REBAR FELL FROM FLT IN UNSAFE LIFTING OPERATION

    Multiple fractures caused by inappropriate use of fork lift

    Read the rest of this article »

    Posted on 7th November 2018

    POORLY PLANNED LIFT DISMANTLE INJURED WORKMAN

    Counterweight or suspension rope struck worker in lift shaft

    Read the rest of this article »

    Posted on 1st November 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic