• Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    RESEARCH REVEALS LIMITS TO ASBESTOS ENCLOSURES

    Enclosure ventilation when removing ceiling tiles dependent upon void volume

    When removing high-risk asbestos-containing materials the work should be carried out inside a specially constructed ventilated enclosure to prevent the spread of asbestos outside the work area.

    HSE commissioned research to investigate the factors that affect the containment potential of temporary ventilated enclosures. This work entitled RR988 – Ventilation of enclosures for removal of asbestos containing materials considered:

    • the way that air moves within ventilated enclosures;
    • how the construction of enclosures and airlocks affects air movement and containment;
    • how the positioning of extraction points and air inlets affect air movement and containment;
    • relationship between air flow and negative pressure, and containment; and
    • factors which affect the ability of enclosures to contain asbestos, such as unplanned openings.

    In addition, the effect of removing ceiling tiles and the size of ceiling void relative to the enclosure was investigated.

    Celing voids may need to be considered contaminated

    The effect of removing ceiling tiles was found to be dependent upon the volume of the void above the false ceiling compared to the enclosure. The researchers concluded that:

    “When the volume of the void was much larger than the enclosure, for instance a small enclosure in a large room where the void is unsealed, removing a ceiling tile caused ΔP and the airlock door deflection to fall to zero.

    Tracer gas and smoke tests showed that once the tile was removed air was able to enter the void and therefore potentially spread contamination to surrounding areas.

    When the volume of the void was less than the enclosure, removal of a ceiling tile caused a reduction of ΔP but the airlock door deflection was unchanged. Tracer gas and smoke tests showed that once the pressure between the two spaces had equalised air could move freely between the two. This means that in this situation the whole void would potentially be contaminated and would require cleaning after completion of the work.

    These results were interesting and should be considered, especially in cases where the void is small compared to the enclosure. The results have shown that once the tile is removed the void becomes part of the enclosure and contaminated air can move freely between the spaces. This means that upon completion of the work the whole void should be considered to be contaminated and be cleaned. ((ΔP) is pressure difference between the interior of the enclosure and the surrounding space)” 

     

    Latest Construction Health and Safety News

    HSE TO OVERSEE NEW BUILDING SAFETY REGIME

    Government to deliver biggest change in building safety for a generation

    Read the rest of this article »

    Posted on 21st January 2020

    CONTRACTS MANAGER HANDED TWO YEAR PRISON TERM

    Safety fall arrest netting would have saved life of deceased workman

    Read the rest of this article »

    Posted on 15th January 2020

    WORKER FATALLY INJURED BY CONCRETE BEAM

    Lifting operation not properly planned, managed and supervised

    Read the rest of this article »

    Posted on 15th January 2020

    TREE FELLING OPERATIONS LACKED DEFINED COMMS

    Workman struck by falling tree inside “normal” exclusion zone

    Read the rest of this article »

    Posted on 14th January 2020

    CONTRACTOR ARRESTED OVER WELFARE FAILINGS

    Recalcitrant sole trader failed to attend court hearing

    Read the rest of this article »

    Posted on 14th January 2020

    MAJOR DEMOLITION CONTRACTOR FINED £500,000

    Collapse of concrete slab caused death of worker and excavator fall

    Read the rest of this article »

    Posted on 14th January 2020

    FALL FROM LADDER WHILST CARRYING BUCKET

    Contractor failed to provide basic safe lifting aids

    Read the rest of this article »

    Posted on 14th January 2020

    FAILURE TO COMPLY WITH HSE NOTICE PROVES COSTLY

    Director given suspended jail term and company fined £60,000

    Read the rest of this article »

    Posted on 14th January 2020

    DEVELOPER FAILED TO PLAN AND CHECK COMPETENCE

    Fall caused by ad-hoc working methods and lack of monitoring

    Read the rest of this article »

    Posted on 14th January 2020

    CYLINDER LEAK TEST CAUSED FATAL INJURIES

    Corrosion inhibitor triggered failure and shrapnel ejection

    Read the rest of this article »

    Posted on 14th January 2020

    FESTIVE GREETINGS TO ALL OUR READERS

    Read the rest of this article »

    Posted on 20th December 2019

    JAIL TERM FOLLOWS ROUTINE HSE SPOT CHECK

    Director of a roofing firm handed a suspended prison sentence

    Read the rest of this article »

    Posted on 19th December 2019

    TEENAGER FELL 3M DURING BLOCK AND BEAM WORK

    Workers uninstructed and left to devise own safe system of work

    Read the rest of this article »

    Posted on 19th December 2019

    PARCEL CARRIER FINED HEAVILY OVER FLT INCIDENT

    Reversing fork lift lacked segregation from pedestrians

    Read the rest of this article »

    Posted on 18th December 2019

    CONTRACTOR FINED OVER FLOOR OPENING FALL

    Thorough risk assessment and edge protection were both inadequate

    Read the rest of this article »

    Posted on 18th December 2019

    THREE WORKERS “CARRIED ALONG” IN SEWER INCIDENT

    Mentally affected and one man treated for long-term traumatic stress

    Read the rest of this article »

    Posted on 11th December 2019

    SOLAR FIRM AND DIRECTOR SENTENCED OVER DEATH

    Brother of business owner died in fall during panel installation

    Read the rest of this article »

    Posted on 10th December 2019

    DIRECTOR AND COMPANY FINED FOR ASBESTOS RISK

    HSE refurbishment campaign inspection revealed asbestos offences

    Read the rest of this article »

    Posted on 10th December 2019

    BULK BAG COLLAPSE CAUSED BY UNSAFE STACKING

    Bulk bag collapsed onto workman when struck by fork lift

    Read the rest of this article »

    Posted on 9th December 2019

    INTERLOCKED GUARD NOT WORKING TO ISOLATE POWER

    Two workmen seriously injured when plant started unexpectedly

    Read the rest of this article »

    Posted on 9th December 2019

    STREET FURNITURE RISK TO PUBLIC FINED £1.4M

    Council prosecuted following injury to child playing on hinged bollard

    Read the rest of this article »

    Posted on 9th December 2019

    WORKMEN SUFFER SERIOUS BURNS FROM CABLE STRIKE

    Assessment and system of work failed to appreciate electrical risk

    Read the rest of this article »

    Posted on 29th November 2019

    LADDERS WERE INAPPROPRIATE FOR WORK ON ROOF

    Workman paralysed after falling whilst installing roof ladder

    Read the rest of this article »

    Posted on 28th November 2019

    FIRM FAILED TO MANAGE EXHAUST VENTILATION

    HSE enforcement notices on wood dust and welding fume ignored

    Read the rest of this article »

    Posted on 27th November 2019

    RECALCITRANT DIRECTOR BARRED FROM OFFICE

    Dangerous telehandler used despite earlier fatality and enforcement

    Read the rest of this article »

    Posted on 25th November 2019
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data