Turner Access Higher Safety Total Access
Total Access Ethentic Chipmunk Data
Chipmunk Data Turner Access Ethentic

DESIGNER FINED OVER MISSING CDM INFORMATION

HSE conclude rare prosecution of designer under CDM Regulations

Cundall Johnston and Partners LLP and Brims Construction Ltd have been prosecuted under the CDM Regulations 2007 after a 2 tonne brick archway collapsed injuring two workers. The incident occurred on a major refurbishment project at a former toffee factory in Newcastle, on 15 February 2011.

The two men were “shoring up” the arch after it become unstable due to the removal of masonry on one of the support pillars. One fractured a foot and the other injured his back in the incident

Newcastle Magistrates’ Court heard that brick pillars adjoining the archway had been weakened after ‘pockets’ were created in the masonry to hold steel beams, which were being installed as part of a major refurbishment of the former confectionary building.

The court was told the removal of the masonry caused the arch to become unstable, as the pillar had acted as a buttress. The condition of the arch was brought to the attention of Brims’ site foreman who instructed the two joiners to shore it up. A plan of work was devised but it was not reviewed by Brims to check that it was a safe method of working.

HSE inspectors found that Cundall Johnston and Partners LLP had not provided information in its designs to ensure those carrying out the work would have known removing the masonry would cause the archway to become unstable. Brims Construction Ltd failed to plan and manage the work to deal with the unstable archway safely.

Drawings must include ‘sufficient information’ on potential danger

Cundall Johnston and Partners LLP, of Newcastle pleaded guilty to a breach of Regulation 11(6)(c) and the company was fined £1,000 with costs of £7,000. Regulation 11(6)(c) requires that a designer take all reasonable steps to provide with designs sufficient information about aspects of the design of the structure or its construction or maintenance as will adequately assist contractors to comply with their duties.

Brims Construction Ltd, of Sunderland, was fined £1,000 and ordered to pay £5,000 in costs after pleading guilty to breaching Regulation 22(1)(a) of the Construction Design and Management Regulations 2007. Regulation 22(1)(a) requires that the project principal contractor must plan, manage and monitor the construction phase in a way which ensures it is carried out without risks to health or safety.

Speaking after the case HSE Inspector Keith Partington said:

“Fortunately the injuries suffered by the workers were not serious. However, if could have been a lot worse as around two tonnes of brickwork fell down when the arch collapsed. This incident could have easily been avoided.

Firstly, if the designers had ensured sufficient information was available in the drawings it would have alerted those carrying out the work to the potential dangers to start with.

Brims should also have properly planned and managed the work.”

Comment

PP Construction Safety provides bespoke training for those with designer duties under CDM 2007

Latest Construction Health and Safety News

NEW ISO 45001 MANAGEMENT STANDARD IMMINENT

Standard capable of replacing OHSAS 18001 with relative ease

Read the rest of this article »

Posted on 20th February 2018

APPEAL COURT RULES ON LEGAL PRIVILEGE CASE

Decision may prompt further caution during internal investigations

Read the rest of this article »

Posted on 20th February 2018

TIPPER TRUCK STRUCK PEDESTRIAN ON SITE ROAD

Contractor fined £500,000 over poor traffic management arrangements

Read the rest of this article »

Posted on 16th February 2018

FALLING SCAFFOLD CLIP STRUCK PASSER-BY

Firm failed to follow risk assessment and method statement

Read the rest of this article »

Posted on 16th February 2018

HSE ENFORCEMENT WEEKLY UPDATE 14th FEB 2018

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 16th February 2018

HOMES FIRM FINED £1/2M OVER DUMPER DEATH

Developer and contractor failed to manage people and plant interface

Read the rest of this article »

Posted on 14th February 2018

SUPREME COURT RULES ON HSE ENFORCEMENT NOTICES

Post service evidence can be used to support HSE notice appeals

Read the rest of this article »

Posted on 9th February 2018

SAFE INSTALLATION OF PRE-CAST FLOORING

Code of Practice for health and safety updated by industry federation

Read the rest of this article »

Posted on 8th February 2018

HSE ENFORCEMENT WEEKLY UPDATE 8th FEB 2018

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 8th February 2018

MANUAL HANDLING MUST INVOLVE ‘REAL RISK’

Court provides clarity on manual handling risk assessment rules

Read the rest of this article »

Posted on 7th February 2018

SKIP LORRY DRIVER FATALLY INJURED BY LOADER

Hire company fined after lorry driver crushed between two vehicles

Read the rest of this article »

Posted on 5th February 2018

PUBLIC RISK COSTS CONTRACTOR DEARLY

Principal Contractor failed to assess and supervise work

Read the rest of this article »

Posted on 5th February 2018

TUBES FELL WHILST LIFTING OVER PERSONS BELOW

Lifting operations were not carried out in safe manner

Read the rest of this article »

Posted on 2nd February 2018

‘DAREDEVIL’ SCAFFOLDER LANDS IN DOCK

Former HSE Inspector snaps dangerous working practices at 60 feet

Read the rest of this article »

Posted on 2nd February 2018

HSE ENFORCEMENT WEEKLY UPDATE 1st FEB 2018

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 1st February 2018

DIDCOT FATAL COLLAPSE: INVESTIGATION UPDATE

Police and HSE still seeking to understand why boiler house collapsed

Read the rest of this article »

Posted on 1st February 2018

SCAFFOLDER TRAINING REACHES NEW HEIGHTS

CISRS training card renewal by CPD embraced by scaffolders

Read the rest of this article »

Posted on 30th January 2018

HSE SUMMARY OF CONSTRUCTION SECTOR HARM

Infographic provides insight into industry priority hazards

Read the rest of this article »

Posted on 29th January 2018

FIRM FAILED TO IMPLEMENT AGREED CONTROLS

Risk assessment carried out but precautions not taken

Read the rest of this article »

Posted on 29th January 2018

HSE MUSCULOSKELETAL DISORDERS SUMMIT 2018

hselogo1Regulator focuses on MSDs in construction and others sectors

Read the rest of this article »

Posted on 28th January 2018

LOAD FELL FROM MAGNET AND STRUCK WORKMAN

Firm failed to properly assess and revise crane safe working load

Read the rest of this article »

Posted on 25th January 2018

RAISING THE BAR ON LIFTING OPERATIONS SKILLS

New ‘Lifting Technician Trailblazer Apprenticeship’ ready for delivery

Read the rest of this article »

Posted on 24th January 2018

HSE ENFORCEMENT WEEKLY UPDATE 24th JAN 2018

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 24th January 2018

SCAFFOLDING FIRM FINED OVER UNSAFE LOADING

Bin of scaffold fittings lifted by crane struck scaffolder

Read the rest of this article »

Posted on 24th January 2018

FATAL FALL FROM EDGE OF INDUSTRIAL ROOF

Suitable protection missing during installation of roof sheets

Read the rest of this article »

Posted on 23rd January 2018
Turner Access Chipmunk Data
Total Access Ethentic
Higher Safety Turner Access