Turner Access Higher Safety Total Access
Total Access Ethentic Chipmunk Data
Chipmunk Data Turner Access Ethentic

DESIGNER FINED OVER MISSING CDM INFORMATION

HSE conclude rare prosecution of designer under CDM Regulations

Cundall Johnston and Partners LLP and Brims Construction Ltd have been prosecuted under the CDM Regulations 2007 after a 2 tonne brick archway collapsed injuring two workers. The incident occurred on a major refurbishment project at a former toffee factory in Newcastle, on 15 February 2011.

The two men were “shoring up” the arch after it become unstable due to the removal of masonry on one of the support pillars. One fractured a foot and the other injured his back in the incident

Newcastle Magistrates’ Court heard that brick pillars adjoining the archway had been weakened after ‘pockets’ were created in the masonry to hold steel beams, which were being installed as part of a major refurbishment of the former confectionary building.

The court was told the removal of the masonry caused the arch to become unstable, as the pillar had acted as a buttress. The condition of the arch was brought to the attention of Brims’ site foreman who instructed the two joiners to shore it up. A plan of work was devised but it was not reviewed by Brims to check that it was a safe method of working.

HSE inspectors found that Cundall Johnston and Partners LLP had not provided information in its designs to ensure those carrying out the work would have known removing the masonry would cause the archway to become unstable. Brims Construction Ltd failed to plan and manage the work to deal with the unstable archway safely.

Drawings must include ‘sufficient information’ on potential danger

Cundall Johnston and Partners LLP, of Newcastle pleaded guilty to a breach of Regulation 11(6)(c) and the company was fined £1,000 with costs of £7,000. Regulation 11(6)(c) requires that a designer take all reasonable steps to provide with designs sufficient information about aspects of the design of the structure or its construction or maintenance as will adequately assist contractors to comply with their duties.

Brims Construction Ltd, of Sunderland, was fined £1,000 and ordered to pay £5,000 in costs after pleading guilty to breaching Regulation 22(1)(a) of the Construction Design and Management Regulations 2007. Regulation 22(1)(a) requires that the project principal contractor must plan, manage and monitor the construction phase in a way which ensures it is carried out without risks to health or safety.

Speaking after the case HSE Inspector Keith Partington said:

“Fortunately the injuries suffered by the workers were not serious. However, if could have been a lot worse as around two tonnes of brickwork fell down when the arch collapsed. This incident could have easily been avoided.

Firstly, if the designers had ensured sufficient information was available in the drawings it would have alerted those carrying out the work to the potential dangers to start with.

Brims should also have properly planned and managed the work.”

Comment

PP Construction Safety provides bespoke training for those with designer duties under CDM 2007

Latest Construction Health and Safety News

PRISON TERM FOR SOLE TRADER CONTRACTOR

Small contractor pays the price for failing to manage work at height hazards

Read the rest of this article »

Posted on 19th October 2017

WORKMAN FELL THROUGH ROOF OPENING

Waterproof membrane concealed conservatory roof hazard

Read the rest of this article »

Posted on 19th October 2017

HSE ENFORCEMENT WEEKLY UPDATE 18th OCT 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 19th October 2017

DEATH AND POORLY MANAGED RISK FINED £3.8 MILLION

Unstable precast concrete panels toppled MEWP and crushed operator

Read the rest of this article »

Posted on 18th October 2017

DOING SAFETY DIFFERENTLY – THE MOVIE…

Reducing compliance bureaucracy and putting trusting in people

Read the rest of this article »

Posted on 13th October 2017

WORKMAN FELL FROM EDGE OF UNGUARDED OPENING

Firm fined £95,000 over failure to assess and protect workers at height

Read the rest of this article »

Posted on 13th October 2017

FITTERS FINGERS SEVERED BY UNGUARDED TABLE SAW

Compensation order for injured workman takes precedence over fine

Read the rest of this article »

Posted on 13th October 2017

HSE ENFORCEMENT WEEKLY UPDATE 11th OCT 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 11th October 2017

ROOF WORKER FRACTURED BACK IN FRAGILE FALL

Fragile wood wool slabs failed to support weight of workman

Read the rest of this article »

Posted on 11th October 2017

PRODUCTS: ELIMINATING HEALTH RISKS BY DESIGN

Innovative product eliminates key hazards for CDM 2015 designers

Read the rest of this article »

Posted on 11th October 2017

DRIVER DIED WHEN CRUSHED BETWEEN VEHICLES

Firm failed to follow industry guidance on coupling and uncoupling

Read the rest of this article »

Posted on 10th October 2017

WORKER LOSES HANDS AND FEET IN POWER LINE STRIKE

Director handed prison term over unsafe scaffolding operation

Read the rest of this article »

Posted on 6th October 2017

INDUSTRY FORUM CONSIDERS DUMPER HAZARDS

CPA and CECA plan new guidance on Forward Tipping Dumpers

Read the rest of this article »

Posted on 6th October 2017

HSE ENFORCEMENT WEEKLY UPDATE 4th OCT 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 5th October 2017

INCIDENT: UNDERGROUND CABLE STRIKE

Three treated for burns after power cable struck in London

Read the rest of this article »

Posted on 5th October 2017

COUNCIL FAILED TO IMPLEMENT STATED HAVS POLICY

Fined £150k over failure to control and monitor hand-arm vibration hazard

Read the rest of this article »

Posted on 5th October 2017

PROJECT MANAGER FINED OVER FAILURE TO MANAGE

Principal Contractor prosecuted alongside responsible manager

Read the rest of this article »

Posted on 3rd October 2017

HSE CONSTRUCTION BLITZ GOES LIVE ON HEALTH RISKS

hselogo1Second phase of campaign looks for compliance on dust management

Read the rest of this article »

Posted on 2nd October 2017

UPDATE OF ALL HSE ASBESTOS ESSENTIALS GUIDANCE

HSE publish fresh guidance for Non-Licensed work with asbestos

Read the rest of this article »

Posted on 27th September 2017

HSE FINALISES PRIORITIES ON HEALTH AND CDM

Clients and designers need to act on lung disease and other health risks

Read the rest of this article »

Posted on 27th September 2017

HSE ENFORCEMENT WEEKLY UPDATE 27th SEPT 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 27th September 2017

SCAFFOLD INSPECTORS ISSUED FALSIFIED CERTIFICATES

Prosecution for two after workman fell from illegitimately signed off scaffold

Read the rest of this article »

Posted on 25th September 2017

REVERSING EXCAVATOR CRUSHED WORKMAN

Lack of management system to segregate pedestrians and vehicles

Read the rest of this article »

Posted on 21st September 2017

CLIENT FINED £2.5 MILLION AFTER CONTRACTOR DEATH

Fatal fall through roof leaves client responsible for massive fine

Read the rest of this article »

Posted on 21st September 2017

HSE ENFORCEMENT WEEKLY UPDATE 20th SEPT 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 20th September 2017
Turner Access Chipmunk Data
Total Access Ethentic
Higher Safety Turner Access