• Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    DESIGNER FINED OVER MISSING CDM INFORMATION

    HSE conclude rare prosecution of designer under CDM Regulations

    Cundall Johnston and Partners LLP and Brims Construction Ltd have been prosecuted under the CDM Regulations 2007 after a 2 tonne brick archway collapsed injuring two workers. The incident occurred on a major refurbishment project at a former toffee factory in Newcastle, on 15 February 2011.

    The two men were “shoring up” the arch after it become unstable due to the removal of masonry on one of the support pillars. One fractured a foot and the other injured his back in the incident

    Newcastle Magistrates’ Court heard that brick pillars adjoining the archway had been weakened after ‘pockets’ were created in the masonry to hold steel beams, which were being installed as part of a major refurbishment of the former confectionary building.

    The court was told the removal of the masonry caused the arch to become unstable, as the pillar had acted as a buttress. The condition of the arch was brought to the attention of Brims’ site foreman who instructed the two joiners to shore it up. A plan of work was devised but it was not reviewed by Brims to check that it was a safe method of working.

    HSE inspectors found that Cundall Johnston and Partners LLP had not provided information in its designs to ensure those carrying out the work would have known removing the masonry would cause the archway to become unstable. Brims Construction Ltd failed to plan and manage the work to deal with the unstable archway safely.

    Drawings must include ‘sufficient information’ on potential danger

    Cundall Johnston and Partners LLP, of Newcastle pleaded guilty to a breach of Regulation 11(6)(c) and the company was fined £1,000 with costs of £7,000. Regulation 11(6)(c) requires that a designer take all reasonable steps to provide with designs sufficient information about aspects of the design of the structure or its construction or maintenance as will adequately assist contractors to comply with their duties.

    Brims Construction Ltd, of Sunderland, was fined £1,000 and ordered to pay £5,000 in costs after pleading guilty to breaching Regulation 22(1)(a) of the Construction Design and Management Regulations 2007. Regulation 22(1)(a) requires that the project principal contractor must plan, manage and monitor the construction phase in a way which ensures it is carried out without risks to health or safety.

    Speaking after the case HSE Inspector Keith Partington said:

    “Fortunately the injuries suffered by the workers were not serious. However, if could have been a lot worse as around two tonnes of brickwork fell down when the arch collapsed. This incident could have easily been avoided.

    Firstly, if the designers had ensured sufficient information was available in the drawings it would have alerted those carrying out the work to the potential dangers to start with.

    Brims should also have properly planned and managed the work.”

    Comment

    PP Construction Safety provides bespoke training for those with designer duties under CDM 2007

    Latest Construction Health and Safety News

    HSE ENFORCEMENT WEEKLY UPDATE 13th JUNE 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 13th June 2018

    DIRECTOR FAILED COMPLY WITH HSE PROHIBITION

    Precautions not taken to prevent excavation collapse and falling

    Read the rest of this article »

    Posted on 11th June 2018

    SCAFFOLD NOT TO INDUSTRY STANDARD OR DESIGN

    Specialist and contractor in court over unsafe work at height

    Read the rest of this article »

    Posted on 7th June 2018

    ROAD WORKER RUN OVER BY ROAD ROLLER

    Reversing alarm not working and warning light not fitted

    Read the rest of this article »

    Posted on 5th June 2018

    CLIENT AND SURVEYOR FINED OVER ASBESTOS SURVEY

    Refurbishment and demolition asbestos survey proved inadequate

    Read the rest of this article »

    Posted on 5th June 2018

    FATALITY: ROAD WORKER DRAGGED ALONG ROAD

    Night shift worker loses life when struck by road sweeping vehicle

    Read the rest of this article »

    Posted on 3rd June 2018

    CDM PRINCIPAL DESIGNERS AVOID HSE ENFORCEMENT

    Regulator enforcement database reveals few notices involve CDM PDs

    Read the rest of this article »

    Posted on 3rd June 2018

    PROPERTY MANAGERS FINED WITH CONTRACTOR

    Defendants failed to check for asbestos during soffit replacement works

    Read the rest of this article »

    Posted on 29th May 2018

    EXCAVATION CAUSED RETAINING WALL COLLAPSE

    Precautions not taken to secure stability of free-standing wall

    Read the rest of this article »

    Posted on 29th May 2018

    OVERHEAD CABLE STRIKE FIRM FINED £500,000+

    Inadequate system caused risk of harm despite lack of worker injury

    Read the rest of this article »

    Posted on 29th May 2018

    CDM 2015 PRINCIPAL DESIGNER FINED OVER FIRE RISK

    PD and PC failed to comply with CDM 2015 responsibilities

    Read the rest of this article »

    Posted on 23rd May 2018

    SENTENCING GUIDELINES UNDER THE MICROSCOPE

    Lawyer argues guidelines undermine reduction in ‘regulatory burden’

    Read the rest of this article »

    Posted on 23rd May 2018

    PANEL STRUCK WORKMAN DURING LIFTING OPERATION

    Third party contractor falls victim of poor lift planning

    Read the rest of this article »

    Posted on 21st May 2018

    DIRECTOR LED HAZARDOUS WORK AT HEIGHT

    Three occasions when work lacked suitable and sufficient precautions

    Read the rest of this article »

    Posted on 21st May 2018

    RISK ASSESSED BUT CONTROLS FOUND WANTING

    Joiner fell through unprotected opening on roof of new building

    Read the rest of this article »

    Posted on 21st May 2018

    RIBA CRITICAL OF HACKITT REVIEW FINAL REPORT

    High rise residential review dismissed as “major missed opportunity”

    Read the rest of this article »

    Posted on 21st May 2018

    CONSTRUCTION SECTOR DEATHS: THE ‘BIG THREE’

    HSE in-year fatalities for 2017/18 may indicate upward trend

    Read the rest of this article »

    Posted on 16th May 2018

    SCAFFOLDING SITE ACCIDENTS AT RECORD LOW

    NASC Annual Report reveals all time low in 2017 incidents

    Read the rest of this article »

    Posted on 14th May 2018

    DUMPER TRUCK HAND-BRAKE NOT MAINTAINED

    Workman injured when pinned against stack of concrete blocks

    Read the rest of this article »

    Posted on 14th May 2018

    SPARE POWER INTERLOCK KEY CAUSED DEATH

    Dangerous machinery safety precautions defeated for maintenance tasks

    Read the rest of this article »

    Posted on 10th May 2018

    COLLAPSED CAR PARK WAS UNDER REPAIR

    Rusted steel supports triggered collapse of fascia and floor

    Read the rest of this article »

    Posted on 8th May 2018

    DUMPER OVERTURN CAUSED FATAL INJURIES

    Precautions during spoil heap creation were inadequate

    Read the rest of this article »

    Posted on 8th May 2018

    HARDWOOD DUST CONTROL NOT MAINTAINED

    Manufacturer failed to examine and test local extraction system

    Read the rest of this article »

    Posted on 8th May 2018

    SCAFFOLD CONTRACTOR OVERLOOKED MAJOR HAZARD

    Well-known risk unidentified during scaffold erection project

    Read the rest of this article »

    Posted on 8th May 2018

    THREE FIRMS FINED £1/2M FOR FRAGILE RISK FAILURES

    Fall through rooflight hazard poorly planned and managed

    Read the rest of this article »

    Posted on 2nd May 2018
    Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data