• Total Access Higher Safety
    Turner Access Chipmunk Data

    CDM REGULATIONS 2015: NEW RIBA PLAN OF WORK

    Project team must be properly assembled at new Stage1

    IMPORTANT UPDATE (01.02.2015) – From 1st April 2015 the CDM-C role is abolished and the client must appoint a Principal Designer as “early as possible” in the design process. Click here for more information,

    The new RIBA Plan of Work 2013 was launched in May 2013 reflecting “the very best principles in contemporary building practice”.

    RIBA state that the original Plan of Work was conceived at a time when the regulatory framework for building design and construction, industry structures and procurement arrangements were simpler and more defined.

    The new plan responds to the UK Government Construction Strategy which called on RIBA to take a leading role in shaping a set of unified work stages suitable for use by all the members of the project team.

    RIBA President Angela Brady said:

    ‘This has been a meticulously detailed project which has delivered a brilliant solution to a once in a generation opportunity to update the industry’s process model and address key changes in areas such as procurement, town planning, sustainability, BIM and construction delivery. I encourage all architects to support the new plan which gives clarity to our role and clarity for our clients.’

    The new RIBA Plan of Work 2013 replaces the former A-L stages in the RIBA Outline Plan of Work 2007 with eight new numbered stages and eight task bars that replace the description of key tasks. Three of these task bars (procurement, programme and planning) can be customised via a new online tool.

    CDM Coordinator required at the outset 

    The CDM Regulations 2007 require construction project clients to appoint a Coordinator on notifiable projects. See above for IMPORTANT UPDATE CDM-Cordinator replaced by CDM Principle Designer

    Current HSE advice on the timing of Coordinator (now the PD) appointments states that “the principal designer should be appointed as early as possible in the design process, if practicable at the concept stage.”

    The new RIBA Plan of Work 2013 states that “assembling the project team” is required by new Stage 1 – Preparation and Brief .

    In addition the “health and safety strategy” should be developed during Stage 2 – Concept Design.

    Latest Construction Health and Safety News

    FATALITY: HOMES PROJECT IN SCOTLAND

    Circumstances of construction worker death remain unclear

    Read the rest of this article »

    Posted on 24th April 2017

    HSE OPEN FEE FOR INTERVENTION CONSULTATION

    hselogo1Regulator proposal for revised FFI disputes process

    Read the rest of this article »

    Posted on 24th April 2017

    LIFTING OPERATION WITH EXCAVATOR CAUSED DEATH

    Groundworker fatally injured when struck by concrete drainage cover

    Read the rest of this article »

    Posted on 24th April 2017

    WATER FIRM FINED £1.8M AFTER WORKER DROWNED

    Workman fell through opening into sand filtration tank

    Read the rest of this article »

    Posted on 24th April 2017

    PC AND CONTRACTOR PAY PRICE FOR UNSAFE WORKING

    Dangerous working practices continued during ‘snowy’ weather

    Read the rest of this article »

    Posted on 24th April 2017

    HSE ENFORCEMENT WEEKLY UPDATE 19th APRIL 2017

    hselogo1Prosecutions and enforcement notices weekly update and analysis

    Read the rest of this article »

    Posted on 20th April 2017

    TOUGHER COURT PENALTIES UNDER NEW GUIDELINES

    Analysis of health and safety prosecutions reveals rise on most metrics

    Read the rest of this article »

    Posted on 18th April 2017

    HSE ENFORCEMENT WEEKLY UPDATE 12th APRIL 2017

    hselogo1Prosecutions and enforcement notices weekly update and analysis

    Read the rest of this article »

    Posted on 18th April 2017

    STOP. MAKE A CHANGE DAY – 18th APRIL 2017

    Infrastructure sector holds first ever ‘National Stand-Down Day’

    Read the rest of this article »

    Posted on 18th April 2017

    ELECTRICIAN FAILED TO PROTECT HIS TRAINEE

    Community service sentence after apprentice fell through ceiling

    Read the rest of this article »

    Posted on 18th April 2017

    CLIENT FINED OVER ABSENT ASBESTOS SURVEY

    Refurbishment project commenced before survey undertaken

    Read the rest of this article »

    Posted on 18th April 2017

    GROUNDWORKER LEFT PARALYSED BY FALLING PIPE

    Gas infrastructure business failed to maintain safe system of work

    Read the rest of this article »

    Posted on 18th April 2017

    MAJOR CONTRACTOR FAILED ON POWER LINE RISK

    Workman suffers severe burns after post touches 11kV overhead cable

    Read the rest of this article »

    Posted on 6th April 2017

    HSE ENFORCEMENT WEEKLY UPDATE 6th APRIL 2017

    hselogo1Prosecutions and enforcement notices weekly update and analysis

    Read the rest of this article »

    Posted on 6th April 2017

    LADDER UNSUITABLE FOR IVY CLEARING TASK

    Electricity supplier fined £900,000 after linesman ladder fall

    Read the rest of this article »

    Posted on 3rd April 2017

    ABSENCE OF ASBESTOS SURVEY PUT FIRMS IN COURT

    Contractor and removal firm jointly responsible for failings

    Read the rest of this article »

    Posted on 3rd April 2017

    WORKING WELL TOGTHER DESIGNER CDM EVENT

    Designer Awareness Day – Preventing Occupational Disease through Design

    Read the rest of this article »

    Posted on 3rd April 2017

    INDUSTRY BODIES STRUCTURE MEWP SAFETY ALERTS

    Strategic Forum Plant Safety Group publishes Safety Alert Protocol

    Read the rest of this article »

    Posted on 3rd April 2017

    ASPHALT MIXER CLAIMS FINGERS OF WORKMAN

    Guarding on mixing machine below the safety standard required

    Read the rest of this article »

    Posted on 3rd April 2017

    FATALITY: SECOND WINDFARM DEATH IN TWO WEEKS

    Workman fell on operational windfarm under maintenance

    Read the rest of this article »

    Posted on 3rd April 2017

    HSE ENFORCEMENT WEEKLY UPDATE 29th MAR 2017

    hselogo1Prosecutions and enforcement notices weekly update and analysis

    Read the rest of this article »

    Posted on 29th March 2017

    UTILITY COMPANY CONVICTED AFTER FALL

    Workman died when fall protection lanyard accidentally severed

    Read the rest of this article »

    Posted on 28th March 2017

    INTENDED SYSTEM UNSAFE … AND NOT FOLLOWED

    Principal contractor and partner failed to protect from roof fall hazard

    Read the rest of this article »

    Posted on 28th March 2017

    DRAMATIC RESCUE FROM HEIGHT CAUGHT ON VIDEO

    Painter in US saved by fall arrest and rescued after platform failure

    Read the rest of this article »

    Posted on 28th March 2017

    MAJOR CONTRACTOR MANAGEMENT FOUND LACKING

    Fatal dumper truck incident caused by inadequate ‘oversight’

    Read the rest of this article »

    Posted on 27th March 2017
    Turner Access Chipmunk Data
    Total Access Higher Safety