• Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    CDM REGULATIONS 2015: NEW RIBA PLAN OF WORK

    Project team must be properly assembled at new Stage1

    The construction project client must appoint a CDM 2015 Principal Designer as “early as possible” in the design process.

    The RIBA Plan of Work 2013 was launched in May 2013 and is said to reflect “the very best principles in contemporary building practice”.

    RIBA state that the original Plan of Work was conceived at a time when the regulatory framework for building design and construction, industry structures and procurement arrangements were simpler and more defined.

    The new plan responds to the UK Government Construction Strategy which called on RIBA to take a leading role in shaping a set of unified work stages suitable for use by all the members of the project team.

    RIBA President Angela Brady said:

    ‘This has been a meticulously detailed project which has delivered a brilliant solution to a once in a generation opportunity to update the industry’s process model and address key changes in areas such as procurement, town planning, sustainability, BIM and construction delivery. I encourage all architects to support the new plan which gives clarity to our role and clarity for our clients.’

    The new RIBA Plan of Work 2013 replaces the former A-L stages in the RIBA Outline Plan of Work 2007 with eight new numbered stages and eight task bars that replace the description of key tasks. Three of these task bars (procurement, programme and planning) can be customised via a new online tool.

    CDM Principal Designer required at the outset 

    The CDM Regulations 2105 require that construction project clients must appoint a Principal Designer on  projects involving more than one contractor.

    Current HSE advice on the timing of Principal Designer appointments states that “the principal designer should be appointed as early as possible in the design process, if practicable at the concept stage.”

    The new RIBA Plan of Work 2013 states that “assembling the project team” is required by new Stage 1 – Preparation and Brief .

    In addition the “health and safety strategy” should be developed during Stage 2 – Concept Design.

     

    Latest Construction Health and Safety News

    CONTRACTS MANAGER HANDED TWO YEAR PRISON TERM

    Safety fall arrest netting would have saved life of deceased workman

    Read the rest of this article »

    Posted on 15th January 2020

    WORKER FATALLY INJURED BY CONCRETE BEAM

    Lifting operation not properly planned, managed and supervised

    Read the rest of this article »

    Posted on 15th January 2020

    TREE FELLING OPERATIONS LACKED DEFINED COMMS

    Workman struck by falling tree inside “normal” exclusion zone

    Read the rest of this article »

    Posted on 14th January 2020

    CONTRACTOR ARRESTED OVER WELFARE FAILINGS

    Recalcitrant sole trader failed to attend court hearing

    Read the rest of this article »

    Posted on 14th January 2020

    MAJOR DEMOLITION CONTRACTOR FINED £500,000

    Collapse of concrete slab caused death of worker and excavator fall

    Read the rest of this article »

    Posted on 14th January 2020

    FALL FROM LADDER WHILST CARRYING BUCKET

    Contractor failed to provide basic safe lifting aids

    Read the rest of this article »

    Posted on 14th January 2020

    FAILURE TO COMPLY WITH HSE NOTICE PROVES COSTLY

    Director given suspended jail term and company fined £60,000

    Read the rest of this article »

    Posted on 14th January 2020

    DEVELOPER FAILED TO PLAN AND CHECK COMPETENCE

    Fall caused by ad-hoc working methods and lack of monitoring

    Read the rest of this article »

    Posted on 14th January 2020

    CYLINDER LEAK TEST CAUSED FATAL INJURIES

    Corrosion inhibitor triggered failure and shrapnel ejection

    Read the rest of this article »

    Posted on 14th January 2020

    FESTIVE GREETINGS TO ALL OUR READERS

    Read the rest of this article »

    Posted on 20th December 2019

    JAIL TERM FOLLOWS ROUTINE HSE SPOT CHECK

    Director of a roofing firm handed a suspended prison sentence

    Read the rest of this article »

    Posted on 19th December 2019

    TEENAGER FELL 3M DURING BLOCK AND BEAM WORK

    Workers uninstructed and left to devise own safe system of work

    Read the rest of this article »

    Posted on 19th December 2019

    PARCEL CARRIER FINED HEAVILY OVER FLT INCIDENT

    Reversing fork lift lacked segregation from pedestrians

    Read the rest of this article »

    Posted on 18th December 2019

    CONTRACTOR FINED OVER FLOOR OPENING FALL

    Thorough risk assessment and edge protection were both inadequate

    Read the rest of this article »

    Posted on 18th December 2019

    THREE WORKERS “CARRIED ALONG” IN SEWER INCIDENT

    Mentally affected and one man treated for long-term traumatic stress

    Read the rest of this article »

    Posted on 11th December 2019

    SOLAR FIRM AND DIRECTOR SENTENCED OVER DEATH

    Brother of business owner died in fall during panel installation

    Read the rest of this article »

    Posted on 10th December 2019

    DIRECTOR AND COMPANY FINED FOR ASBESTOS RISK

    HSE refurbishment campaign inspection revealed asbestos offences

    Read the rest of this article »

    Posted on 10th December 2019

    BULK BAG COLLAPSE CAUSED BY UNSAFE STACKING

    Bulk bag collapsed onto workman when struck by fork lift

    Read the rest of this article »

    Posted on 9th December 2019

    INTERLOCKED GUARD NOT WORKING TO ISOLATE POWER

    Two workmen seriously injured when plant started unexpectedly

    Read the rest of this article »

    Posted on 9th December 2019

    STREET FURNITURE RISK TO PUBLIC FINED £1.4M

    Council prosecuted following injury to child playing on hinged bollard

    Read the rest of this article »

    Posted on 9th December 2019

    WORKMEN SUFFER SERIOUS BURNS FROM CABLE STRIKE

    Assessment and system of work failed to appreciate electrical risk

    Read the rest of this article »

    Posted on 29th November 2019

    LADDERS WERE INAPPROPRIATE FOR WORK ON ROOF

    Workman paralysed after falling whilst installing roof ladder

    Read the rest of this article »

    Posted on 28th November 2019

    FIRM FAILED TO MANAGE EXHAUST VENTILATION

    HSE enforcement notices on wood dust and welding fume ignored

    Read the rest of this article »

    Posted on 27th November 2019

    RECALCITRANT DIRECTOR BARRED FROM OFFICE

    Dangerous telehandler used despite earlier fatality and enforcement

    Read the rest of this article »

    Posted on 25th November 2019

    DIRECTOR HID UNSAFE WORKING PRACTICES FROM HSE

    Workers exposed to sprayed paints containing asthma causing isocyantes

    Read the rest of this article »

    Posted on 25th November 2019
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data