Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    CDM REGULATIONS 2015: NEW RIBA PLAN OF WORK

    Project team must be properly assembled at new Stage1

    The construction project client must appoint a CDM 2015 Principal Designer as “early as possible” in the design process.

    The RIBA Plan of Work 2013 was launched in May 2013 and is said to reflect “the very best principles in contemporary building practice”.

    RIBA state that the original Plan of Work was conceived at a time when the regulatory framework for building design and construction, industry structures and procurement arrangements were simpler and more defined.

    The new plan responds to the UK Government Construction Strategy which called on RIBA to take a leading role in shaping a set of unified work stages suitable for use by all the members of the project team.

    RIBA President Angela Brady said:

    ‘This has been a meticulously detailed project which has delivered a brilliant solution to a once in a generation opportunity to update the industry’s process model and address key changes in areas such as procurement, town planning, sustainability, BIM and construction delivery. I encourage all architects to support the new plan which gives clarity to our role and clarity for our clients.’

    The new RIBA Plan of Work 2013 replaces the former A-L stages in the RIBA Outline Plan of Work 2007 with eight new numbered stages and eight task bars that replace the description of key tasks. Three of these task bars (procurement, programme and planning) can be customised via a new online tool.

    CDM Principal Designer required at the outset 

    The CDM Regulations 2105 require that construction project clients must aappoint a Principal Designer on  projects involving more than one contractor.

    Current HSE advice on the timing of Principal Designer appointments states that “the principal designer should be appointed as early as possible in the design process, if practicable at the concept stage.”

    The new RIBA Plan of Work 2013 states that “assembling the project team” is required by new Stage 1 – Preparation and Brief .

    In addition the “health and safety strategy” should be developed during Stage 2 – Concept Design.

     

    Latest Construction Health and Safety News

    HSE ENFORCEMENT WEEKLY UPDATE 12th DEC 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 12th December 2018

    HSE SAFETY ALERT: TOWER CRANE BRAKES

    Collapse of tower crane jib in high winds prompts HSE warning

    Read the rest of this article »

    Posted on 11th December 2018

    VISITING ENGINEER CRUSHED BY SCAFFOLD TUBES

    Principal contractor “signed off” contractor storage arrangements

    Read the rest of this article »

    Posted on 11th December 2018

    CONCRETE EJECTED BY PUMPING UNIT CLAIMED LIFE

    Company and director failed to train and supervise pumping operations

    Read the rest of this article »

    Posted on 5th December 2018

    REFRESHED GUIDANCE ON FITNESS TO OPERATE PLANT

    Construction plant medical fitness Good Practice Guide

    Read the rest of this article »

    Posted on 4th December 2018

    MAJOR CONTRACTOR & LUL USED UNSAFE SYSTEM

    Work method to eliminate moving vehicle hazard not adopted

    Read the rest of this article »

    Posted on 4th December 2018

    OVERTURNING LORRY CAUSED DEATH OF DRIVER

    Groundworks project stockpiling arrangements not properly managed

    Read the rest of this article »

    Posted on 3rd December 2018

    FORTH BRIDGE LIFTING OPERATION NOT PLANNED

    Major project PC failed to plan, supervise and carry out lift safely

    Read the rest of this article »

    Posted on 3rd December 2018

    DEVELOPER FAILED ON ASBESTOS ASSESSMENT

    HSE inspection revealed refurb works without asbestos survey

    Read the rest of this article »

    Posted on 28th November 2018

    POST DRIVER HAMMER CRUSHED HAND OF WORKMAN

    Unsafe system of work for vehicle crash barrier installation

    Read the rest of this article »

    Posted on 28th November 2018

    WORKER FELL FROM LOFT THROUGH CEILING

    Major house builder lacked understanding of loft fragile surfaces risk

    Read the rest of this article »

    Posted on 28th November 2018

    NEW SITE DUMPER SAFETY GUIDANCE ISSUED

    Construction plant sector concerns prompts CPA consults on draft

    Read the rest of this article »

    Posted on 28th November 2018

    CCTV INSTALLER FELL THROUGH FRAGILE ROOFLIGHT

    Contractor failed to properly plan and control the risks

    Read the rest of this article »

    Posted on 28th November 2018

    VISITOR DIED FALLING INTO CONCEALED BASEMENT

    Contractor failed to protect basement void on domestic project

    Read the rest of this article »

    Posted on 28th November 2018

    RACKING FALL REVEALED UNSAFE SYSTEM OF WORK

    European firm fined £300,000 after UK sub-contractor employee fell

    Read the rest of this article »

    Posted on 18th November 2018

    FAILURE TO ACT ON VIBRATION AND SILICA HAZARDS

    Worker health put at risk during stripping of furnace lining

    Read the rest of this article »

    Posted on 18th November 2018

    MAJOR FM FIRM FAILED TO MAINTAIN BACK-UP POWER

    Power loss at laboratory site created potential risk from biological agents

    Read the rest of this article »

    Posted on 18th November 2018

    IGNORING HSE PROHIBITIONS COST FIRM £250,000

    CDM 2015 and work at height requirements repeatedly breached

    Read the rest of this article »

    Posted on 16th November 2018

    ROOF COLLAPSED UNDER EXCESS LOADING

    Director and company fined over roof design failures

    Read the rest of this article »

    Posted on 11th November 2018

    FORK LIFT OVERTURNED IN SCAFFOLDING YARD

    Untrained operator suffered life changing crush injuries

    Read the rest of this article »

    Posted on 10th November 2018

    STRUCTURAL SAFETY ALERT: EFFECTS OF SCALE

    SCOSS issues alert after concerns disclosed over ‘large structures’

    Read the rest of this article »

    Posted on 7th November 2018

    ASBESTOS EXPOSED BY UNTRAINED WORKERS

    Contractor failed to act properly despite HSE intervention

    Read the rest of this article »

    Posted on 7th November 2018

    GAS MAIN STRIKE REPAIR CAUSED SEVERE BURNS

    Contractor excavator damage to gas pipe ends in £1.2m fine

    Read the rest of this article »

    Posted on 7th November 2018

    REBAR FELL FROM FLT IN UNSAFE LIFTING OPERATION

    Multiple fractures caused by inappropriate use of fork lift

    Read the rest of this article »

    Posted on 7th November 2018

    POORLY PLANNED LIFT DISMANTLE INJURED WORKMAN

    Counterweight or suspension rope struck worker in lift shaft

    Read the rest of this article »

    Posted on 1st November 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic