Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    TEMPORARY WORKS: HSE FREQUENTLY ASKED QUESTIONS

    HSE provide answers to basic temporary works issues 

    “Temporary works” are “engineered solutions” used to support or protect an existing structure or the permanent works during construction, or to support an item of plant or equipment, or the vertical sides or side-slopes of an excavation, or to provide access. The construction of most types of permanent works will require the use of some form of temporary works.

    Temporary works is defined in BS5975: 2008 “Code of practice for temporary works procedures and the permissible stress design of falsework” as “(those) parts of the works that allow or enable construction of, protect, support or provide access to, the permanent works and which might or might not remain in place at the completion of the works”.

    Examples of temporary works include, but are not limited to:

    • Earthworks – trenches, excavations, temporary slopes and stockpiles. Structures – formwork, falsework, propping, façade retention, needling, shoring, edge protection, scaffolding, temporary bridges, site hoarding and signage, site fencing, cofferdams.
    • Equipment/plant foundations – tower crane bases, supports, anchors and ties for construction hoists and mast climbing work platforms (MCWPs), groundworks to provide suitable locations for plant erection, e.g. mobile cranes and piling rigs.

    HSE has now issued answers to a range of Frequently Asked Questions regarding “temporary works” which are repeated below.

    More detailed information on Management of Temporary Works is also available. 

    **************************

     

    TEMPORARY WORKS – HSE FREQUENTLY ASKED QUESTIONS

     

    What are permanent works?

    Permanent works are the parts of a construction project that will be used and remain in position for a long time – e.g. 60 years. This includes buildings and structures such as bridges, roads, retaining walls, etc. The construction of most types of permanent works will require the use of some form of temporary works.

    What are temporary works?

    Temporary works (TW) are the parts of a construction project that are needed to enable the permanent works to be built. Usually the TW are removed after use – e.g. access scaffolds, props, shoring, excavation support, falsework and formwork, etc. Sometimes the TW is incorporated into the permanent works – e.g. haul road foundations and crane or piling platforms may be used for hardstanding or road foundations.

    Are temporary works different to permanent works?

    It is very important that the same degree of care and attention is given to the design and construction of temporary works (TW) as to the design and construction of the permanent works. As TW may be in place for only a short while there is a tendency to assume they are less important. This is incorrect. Lack of care with design, selection, assembly, etc leaves TW liable to fail or collapse. This places people at risk of injury and can cause the project to be delayed.

    Can I organise the temporary works myself?

    The person organising the temporary works needs to be aware of the problems that can occur at each stage of the process and how to prevent these. They need to coordinate design, selection of equipment, appointment of contractors, supervision of work, checking completion, authorisation to load and removal. Unless this is done in a thorough and systematic way problems are likely to occur. If you take this on yourself you must ensure each part of the process is correctly carried out.

    Do I have to appoint a ‘temporary works coordinator’ (TWC)?

    British Standard 5975 sets out one way of managing temporary works (TW) that has been found to work well on medium and large projects and uses the job title Temporary Works Coordinator (TWC). There is no legal requirement to use this job title or the BS recommended process, but you should remember that BS5975 provides an industry consensus view on what is considered to be good practice. The legal requirement is that the party in control must ensure that work is allocated and carried out in a manner that does not create unacceptable risk of harm to workers or members of the public. On projects with relatively simple TW needs, you may choose not to appoint a TWC. However, you must still make sure that TW are properly managed to ensure safety.

    Do I need to provide calculations for every temporary works situation?

    Where the situation is small scale and straightforward there may be a “standard solution” provided for the temporary works (TW). These include, for example, use of a tower or system scaffold for access; design of a basic access scaffold to a standard configuration using existing data from tables; selection of a trench box to support a 2m excavation in firm, dry ground. In each of these cases the person organising the TW will need to assess the ground to be sure it is suitable for the equipment involved, and check that any assumptions made in the calculations for the standard solution are valid for this particular situation and the conditions on site. On a simple job the supplier’s data will allow an experienced person to consider the necessary issues without further calculation.

    Propping using standard equipment such as screw props (‘Acrows’) needs careful consideration. To select the type, size, number and decide spacing, information is needed about the loads that will act on the props. This will include the wall above and the additional load from any other floor or roof beams etc that enter the wall above or close to the opening. Even with proprietary equipment, the support system must be worked out by a person who knows the correct methods of assessing the loads and designing the support arrangement. Failure of TW is often found to result from the loadings being underestimated; and in particular where loadings from the sides are not considered.

    Can all structural engineers design temporary works?

    No. Temporary works (TW) can be very sensitive to how they are used and are easily affected by other work taking place nearby. For these reasons the TW designer needs TW training and experience.

    If I get a structural engineer to design the temporary works will they be the project TWC?

    No. Coordinating the temporary works (TW) is not automatically the responsibility of the engineer carrying out the design work. Coordination is a much wider role that includes planning where and when TW will be needed and ensuring that they are correctly installed, used, checked and maintained. Some design engineers may be happy to be additionally contracted to act as project Temporary Works Coordinator.

    Latest Construction Health and Safety News

    HSE ENFORCEMENT WEEKLY UPDATE 21st JAN 2019

    hselogo1HSE online register of prosecutions and enforcement notices

    Read the rest of this article »

    Posted on 22nd January 2019

    WORKMAN FELL FROM UNSECURED LADDER

    Industrial cladding company failed to assess and control WAH

    Read the rest of this article »

    Posted on 18th January 2019

    SCAFFOLDER FELL THROUGH FRAGILE ROOFLIGHT

    Fall through roof leaves workman with life-changing injuries

    Read the rest of this article »

    Posted on 18th January 2019

    ARM DRAGGED INTO CONVEYOR BELT DANGER

    Workman seriously injured on first day at work in quarry

    Read the rest of this article »

    Posted on 16th January 2019

    ROOF TRUSSES TOPPLED TRAPPING WORKMAN

    Principal contractor failed to plan, manage and monitor project

    Read the rest of this article »

    Posted on 16th January 2019

    SCAFFOLDING AWARENESS TRAINING FOR ALL

    CISRS set to target painters, bricklayers, electricians and plumbers

    Read the rest of this article »

    Posted on 16th January 2019

    POOR LIFT MAINTENANCE CLAIMED LIFE OF CHILD

    Affordable housing business and contractor fined over £1.5m

    Read the rest of this article »

    Posted on 15th January 2019

    NEW CPA CRANE SAFETY GUIDANCE ISSUED

    Guide covers use of mobile lifting appliances beside railways

    Read the rest of this article »

    Posted on 14th January 2019

    RIBA CONDEMNS RISKIER PROCUREMENT OUTCOMES

    Holistic focus on safety is required and not just cost cutting

    Read the rest of this article »

    Posted on 8th January 2019

    DIRECTOR JAILED OVER PAINT STRIPPER ILLEGAL SALE

    Banned and restricted chemicals sold contrary to legal requirements

    Read the rest of this article »

    Posted on 5th January 2019

    CLIENT FAILED TO PROCURE ASBESTOS SURVEY

    Demolition work released large quantities of asbestos fibres

    Read the rest of this article »

    Posted on 2nd January 2019

    LIVE WORKING IGNITED CLOTHES OF ELECTRICIAN

    Spanner came into contact with live terminal causing life-changing burns

    Read the rest of this article »

    Posted on 31st December 2018

    WORKMEN FELL FROM ‘BIN’ ATTACHED TO EXCAVATOR

    Premature removal of scissor lift prompted unsafe system of work

    Read the rest of this article »

    Posted on 31st December 2018

    MANY SITES FAIL HSE HEALTH RISK CONTROL TEST

    HSE Construction site ‘blitz’ finds breaches at 43% of site visits

    Read the rest of this article »

    Posted on 31st December 2018

    MAKESHIFT FALL ARREST SYSTEM CAUGHT ON CAMERA

    Contactors fined for using harness not attached to suitable anchor

    Read the rest of this article »

    Posted on 31st December 2018

    HYDRAULIC RAM SEVERED HAND OF WORKMAN

    Major contractor failed to follow own policies and procedures

    Read the rest of this article »

    Posted on 31st December 2018

    ALL WORK AREAS NOT INCLUDED IN ASBESTOS SURVEY

    Company fined after asbestos containing materials were released

    Read the rest of this article »

    Posted on 31st December 2018

    FESTIVE GREETINGS TO ALL OUR READERS

    Read the rest of this article »

    Posted on 18th December 2018

    POSITIVE STORY ON FRAGILE SURFACE HAZARDS

    Major roofing contractor testifies to working from below roof

    Read the rest of this article »

    Posted on 18th December 2018

    LEISURE CENTRE USER FELL ILL AFTER SHOWER USE

    Legionella risk assessment and control measures found wanting

    Read the rest of this article »

    Posted on 18th December 2018

    STONE CUTTING MACHINE GUARDS FAILED HSE TEST

    Precautions taken following HSE enforcement fell into disuse

    Read the rest of this article »

    Posted on 18th December 2018

    ROOFWORK CREATED CARBON MONOXIDE RISK

    Falling rubble damaged and blocked home chimney flue

    Read the rest of this article »

    Posted on 18th December 2018

    HSE SAFETY ALERT: TOWER CRANE BRAKES

    Collapse of tower crane jib in high winds prompts HSE warning

    Read the rest of this article »

    Posted on 11th December 2018

    VISITING ENGINEER CRUSHED BY SCAFFOLD TUBES

    Principal contractor “signed off” contractor storage arrangements

    Read the rest of this article »

    Posted on 11th December 2018

    CONCRETE EJECTED BY PUMPING UNIT CLAIMED LIFE

    Company and director failed to train and supervise pumping operations

    Read the rest of this article »

    Posted on 5th December 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic