• Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    TEMPORARY WORKS: HSE FREQUENTLY ASKED QUESTIONS

    HSE provide answers to basic temporary works issues 

    “Temporary works” are “engineered solutions” used to support or protect an existing structure or the permanent works during construction, or to support an item of plant or equipment, or the vertical sides or side-slopes of an excavation, or to provide access. The construction of most types of permanent works will require the use of some form of temporary works.

    Temporary works is defined in BS5975: 2008 “Code of practice for temporary works procedures and the permissible stress design of falsework” as “(those) parts of the works that allow or enable construction of, protect, support or provide access to, the permanent works and which might or might not remain in place at the completion of the works”.

    Examples of temporary works include, but are not limited to:

    • Earthworks – trenches, excavations, temporary slopes and stockpiles. Structures – formwork, falsework, propping, façade retention, needling, shoring, edge protection, scaffolding, temporary bridges, site hoarding and signage, site fencing, cofferdams.
    • Equipment/plant foundations – tower crane bases, supports, anchors and ties for construction hoists and mast climbing work platforms (MCWPs), groundworks to provide suitable locations for plant erection, e.g. mobile cranes and piling rigs.

    HSE has now issued answers to a range of Frequently Asked Questions regarding “temporary works” which are repeated below.

    More detailed information on Management of Temporary Works is also available. 

    **************************

     

    TEMPORARY WORKS – HSE FREQUENTLY ASKED QUESTIONS

     

    What are permanent works?

    Permanent works are the parts of a construction project that will be used and remain in position for a long time – e.g. 60 years. This includes buildings and structures such as bridges, roads, retaining walls, etc. The construction of most types of permanent works will require the use of some form of temporary works.

    What are temporary works?

    Temporary works (TW) are the parts of a construction project that are needed to enable the permanent works to be built. Usually the TW are removed after use – e.g. access scaffolds, props, shoring, excavation support, falsework and formwork, etc. Sometimes the TW is incorporated into the permanent works – e.g. haul road foundations and crane or piling platforms may be used for hardstanding or road foundations.

    Are temporary works different to permanent works?

    It is very important that the same degree of care and attention is given to the design and construction of temporary works (TW) as to the design and construction of the permanent works. As TW may be in place for only a short while there is a tendency to assume they are less important. This is incorrect. Lack of care with design, selection, assembly, etc leaves TW liable to fail or collapse. This places people at risk of injury and can cause the project to be delayed.

    Can I organise the temporary works myself?

    The person organising the temporary works needs to be aware of the problems that can occur at each stage of the process and how to prevent these. They need to coordinate design, selection of equipment, appointment of contractors, supervision of work, checking completion, authorisation to load and removal. Unless this is done in a thorough and systematic way problems are likely to occur. If you take this on yourself you must ensure each part of the process is correctly carried out.

    Do I have to appoint a ‘temporary works coordinator’ (TWC)?

    British Standard 5975 sets out one way of managing temporary works (TW) that has been found to work well on medium and large projects and uses the job title Temporary Works Coordinator (TWC). There is no legal requirement to use this job title or the BS recommended process, but you should remember that BS5975 provides an industry consensus view on what is considered to be good practice. The legal requirement is that the party in control must ensure that work is allocated and carried out in a manner that does not create unacceptable risk of harm to workers or members of the public. On projects with relatively simple TW needs, you may choose not to appoint a TWC. However, you must still make sure that TW are properly managed to ensure safety.

    Do I need to provide calculations for every temporary works situation?

    Where the situation is small scale and straightforward there may be a “standard solution” provided for the temporary works (TW). These include, for example, use of a tower or system scaffold for access; design of a basic access scaffold to a standard configuration using existing data from tables; selection of a trench box to support a 2m excavation in firm, dry ground. In each of these cases the person organising the TW will need to assess the ground to be sure it is suitable for the equipment involved, and check that any assumptions made in the calculations for the standard solution are valid for this particular situation and the conditions on site. On a simple job the supplier’s data will allow an experienced person to consider the necessary issues without further calculation.

    Propping using standard equipment such as screw props (‘Acrows’) needs careful consideration. To select the type, size, number and decide spacing, information is needed about the loads that will act on the props. This will include the wall above and the additional load from any other floor or roof beams etc that enter the wall above or close to the opening. Even with proprietary equipment, the support system must be worked out by a person who knows the correct methods of assessing the loads and designing the support arrangement. Failure of TW is often found to result from the loadings being underestimated; and in particular where loadings from the sides are not considered.

    Can all structural engineers design temporary works?

    No. Temporary works (TW) can be very sensitive to how they are used and are easily affected by other work taking place nearby. For these reasons the TW designer needs TW training and experience.

    If I get a structural engineer to design the temporary works will they be the project TWC?

    No. Coordinating the temporary works (TW) is not automatically the responsibility of the engineer carrying out the design work. Coordination is a much wider role that includes planning where and when TW will be needed and ensuring that they are correctly installed, used, checked and maintained. Some design engineers may be happy to be additionally contracted to act as project Temporary Works Coordinator.

    Latest Construction Health and Safety News

    PANEL STRUCK WORKMAN DURING LIFTING OPERATION

    Third party contractor falls victim of poor lift planning

    Read the rest of this article »

    Posted on 21st May 2018

    DIRECTOR LED HAZARDOUS WORK AT HEIGHT

    Three occasions when work lacked suitable and sufficient precautions

    Read the rest of this article »

    Posted on 21st May 2018

    RISK ASSESSED BUT CONTROLS FOUND WANTING

    Joiner fell through unprotected opening on roof of new building

    Read the rest of this article »

    Posted on 21st May 2018

    RIBA CRITICAL OF HACKITT REVIEW FINAL REPORT

    High rise residential review dismissed as “major missed opportunity”

    Read the rest of this article »

    Posted on 21st May 2018

    HSE ENFORCEMENT WEEKLY UPDATE 16th MAY 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 16th May 2018

    CONSTRUCTION SECTOR DEATHS: THE ‘BIG THREE’

    HSE in-year fatalities for 2017/18 may indicate upward trend

    Read the rest of this article »

    Posted on 16th May 2018

    SCAFFOLDING SITE ACCIDENTS AT RECORD LOW

    NASC Annual Report reveals all time low in 2017 incidents

    Read the rest of this article »

    Posted on 14th May 2018

    DUMPER TRUCK HAND-BRAKE NOT MAINTAINED

    Workman injured when pinned against stack of concrete blocks

    Read the rest of this article »

    Posted on 14th May 2018

    SPARE POWER INTERLOCK KEY CAUSED DEATH

    Dangerous machinery safety precautions defeated for maintenance tasks

    Read the rest of this article »

    Posted on 10th May 2018

    HSE ENFORCEMENT WEEKLY UPDATE 9th MAY 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 9th May 2018

    COLLAPSED CAR PARK WAS UNDER REPAIR

    Rusted steel supports triggered collapse of fascia and floor

    Read the rest of this article »

    Posted on 8th May 2018

    DUMPER OVERTURN CAUSED FATAL INJURIES

    Precautions during spoil heap creation were inadequate

    Read the rest of this article »

    Posted on 8th May 2018

    HARDWOOD DUST CONTROL NOT MAINTAINED

    Manufacturer failed to examine and test local extraction system

    Read the rest of this article »

    Posted on 8th May 2018

    SCAFFOLD CONTRACTOR OVERLOOKED MAJOR HAZARD

    Well-known risk unidentified during scaffold erection project

    Read the rest of this article »

    Posted on 8th May 2018

    THREE FIRMS FINED £1/2M FOR FRAGILE RISK FAILURES

    Fall through rooflight hazard poorly planned and managed

    Read the rest of this article »

    Posted on 2nd May 2018

    CONTRACTORS IGNORED ASBESTOS RISK

    Asbestos pipe lagging worked on without licence and proper precautions

    Read the rest of this article »

    Posted on 2nd May 2018

    HSE ENFORCEMENT UPDATE 2nd MAY 2018

    hselogo1Prosecutions and enforcement notices update and analysis

    Read the rest of this article »

    Posted on 2nd May 2018

    SOFT LANDING BAGS TRIGGERED A FALL!

    Fall arrest bag thrown from scaffold took workman with bag

    Read the rest of this article »

    Posted on 1st May 2018

    FAILURE TO NOTIFY HSE PREVENTED INVESTIGATION

    Regulator prosecutes over RIDDOR non-compliance

    Read the rest of this article »

    Posted on 1st May 2018

    CLIENT AND CONTRACTOR TOGETHER IN COURT

    Fragile roof fall exposes client failure to manage project

    Read the rest of this article »

    Posted on 1st May 2018

    UNTRAINED DUMPER DRIVER SURVIVES OVERTURN

    Inadequate barriers plus lack of operator and manager training

    Read the rest of this article »

    Posted on 1st May 2018

    PROJECT CLIENT PROSECUTED UNDER CDM 2015

    Building demolished without suitable precautions to prevent danger

    Read the rest of this article »

    Posted on 1st May 2018

    LORRY RUNAWAY CLAIMED LIFE OF DRIVER

    Workman died after being drawn under trailer

    Read the rest of this article »

    Posted on 25th April 2018

    PETROL VAPOUR DANGER LEFT UNCONTROLLED

    Workman suffered severe burns during refuelling equipment

    Read the rest of this article »

    Posted on 25th April 2018

    HSE ENFORCEMENT UPDATE 25th APRIL 2018

    hselogo1Prosecutions and enforcement notices update and analysis

    Read the rest of this article »

    Posted on 25th April 2018
    Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data