Turner Access Higher Safety Total Access
Total Access Ethentic Chipmunk Data
Chipmunk Data Turner Access Ethentic

TEMPORARY WORKS: HSE FREQUENTLY ASKED QUESTIONS

HSE provide answers to basic temporary works issues 

“Temporary works” are “engineered solutions” used to support or protect an existing structure or the permanent works during construction, or to support an item of plant or equipment, or the vertical sides or side-slopes of an excavation, or to provide access. The construction of most types of permanent works will require the use of some form of temporary works.

Temporary works is defined in BS5975: 2008 “Code of practice for temporary works procedures and the permissible stress design of falsework” as “(those) parts of the works that allow or enable construction of, protect, support or provide access to, the permanent works and which might or might not remain in place at the completion of the works”.

Examples of temporary works include, but are not limited to:

  • Earthworks – trenches, excavations, temporary slopes and stockpiles. Structures – formwork, falsework, propping, façade retention, needling, shoring, edge protection, scaffolding, temporary bridges, site hoarding and signage, site fencing, cofferdams.
  • Equipment/plant foundations – tower crane bases, supports, anchors and ties for construction hoists and mast climbing work platforms (MCWPs), groundworks to provide suitable locations for plant erection, e.g. mobile cranes and piling rigs.

HSE has now issued answers to a range of Frequently Asked Questions regarding “temporary works” which are repeated below.

More detailed information on Management of Temporary Works is also available. 

**************************

 

TEMPORARY WORKS – HSE FREQUENTLY ASKED QUESTIONS

 

What are permanent works?

Permanent works are the parts of a construction project that will be used and remain in position for a long time – e.g. 60 years. This includes buildings and structures such as bridges, roads, retaining walls, etc. The construction of most types of permanent works will require the use of some form of temporary works.

What are temporary works?

Temporary works (TW) are the parts of a construction project that are needed to enable the permanent works to be built. Usually the TW are removed after use – e.g. access scaffolds, props, shoring, excavation support, falsework and formwork, etc. Sometimes the TW is incorporated into the permanent works – e.g. haul road foundations and crane or piling platforms may be used for hardstanding or road foundations.

Are temporary works different to permanent works?

It is very important that the same degree of care and attention is given to the design and construction of temporary works (TW) as to the design and construction of the permanent works. As TW may be in place for only a short while there is a tendency to assume they are less important. This is incorrect. Lack of care with design, selection, assembly, etc leaves TW liable to fail or collapse. This places people at risk of injury and can cause the project to be delayed.

Can I organise the temporary works myself?

The person organising the temporary works needs to be aware of the problems that can occur at each stage of the process and how to prevent these. They need to coordinate design, selection of equipment, appointment of contractors, supervision of work, checking completion, authorisation to load and removal. Unless this is done in a thorough and systematic way problems are likely to occur. If you take this on yourself you must ensure each part of the process is correctly carried out.

Do I have to appoint a ‘temporary works coordinator’ (TWC)?

British Standard 5975 sets out one way of managing temporary works (TW) that has been found to work well on medium and large projects and uses the job title Temporary Works Coordinator (TWC). There is no legal requirement to use this job title or the BS recommended process, but you should remember that BS5975 provides an industry consensus view on what is considered to be good practice. The legal requirement is that the party in control must ensure that work is allocated and carried out in a manner that does not create unacceptable risk of harm to workers or members of the public. On projects with relatively simple TW needs, you may choose not to appoint a TWC. However, you must still make sure that TW are properly managed to ensure safety.

Do I need to provide calculations for every temporary works situation?

Where the situation is small scale and straightforward there may be a “standard solution” provided for the temporary works (TW). These include, for example, use of a tower or system scaffold for access; design of a basic access scaffold to a standard configuration using existing data from tables; selection of a trench box to support a 2m excavation in firm, dry ground. In each of these cases the person organising the TW will need to assess the ground to be sure it is suitable for the equipment involved, and check that any assumptions made in the calculations for the standard solution are valid for this particular situation and the conditions on site. On a simple job the supplier’s data will allow an experienced person to consider the necessary issues without further calculation.

Propping using standard equipment such as screw props (‘Acrows’) needs careful consideration. To select the type, size, number and decide spacing, information is needed about the loads that will act on the props. This will include the wall above and the additional load from any other floor or roof beams etc that enter the wall above or close to the opening. Even with proprietary equipment, the support system must be worked out by a person who knows the correct methods of assessing the loads and designing the support arrangement. Failure of TW is often found to result from the loadings being underestimated; and in particular where loadings from the sides are not considered.

Can all structural engineers design temporary works?

No. Temporary works (TW) can be very sensitive to how they are used and are easily affected by other work taking place nearby. For these reasons the TW designer needs TW training and experience.

If I get a structural engineer to design the temporary works will they be the project TWC?

No. Coordinating the temporary works (TW) is not automatically the responsibility of the engineer carrying out the design work. Coordination is a much wider role that includes planning where and when TW will be needed and ensuring that they are correctly installed, used, checked and maintained. Some design engineers may be happy to be additionally contracted to act as project Temporary Works Coordinator.

Latest Construction Health and Safety News

HSE ENFORCEMENT WEEKLY UPDATE 17th JAN 2018

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 18th January 2018

PARLIAMENT CALLS FOR WORKING AT HEIGHT ADVICE

Committee aims to understand fatal fall causes and solutions

Read the rest of this article »

Posted on 18th January 2018

FIRM FINED OVER FATAL FRAGILE ROOFLIGHT FALL

Work at height not planned, supervised or carried out safely

Read the rest of this article »

Posted on 18th January 2018

EXCAVATOR CRUSHED DUMPER OPERATOR

Reversing excavator operations not separated from pedestrians

Read the rest of this article »

Posted on 12th January 2018

REFURB CONTRACTORS FINED £1.1 MILLION

Tenant fell 5m through fragile surface whilst walking to home

Read the rest of this article »

Posted on 12th January 2018

HSE ENFORCEMENT WEEKLY UPDATE 10th JAN 2018

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 10th January 2018

STRUCTURAL SAFETY BODY LATEST NEWSLETTER

CROSS publishes reports and expert comment on a range of issues

Read the rest of this article »

Posted on 10th January 2018

HSE REACH OUT TO RESOLVE RISK MANAGEMENT

Construction Industry Advisory Network (CONIAN) launched

Read the rest of this article »

Posted on 10th January 2018

HSE ENFORCEMENT WEEKLY UPDATE 4th JAN 2018

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 4th January 2018

FAILURE TO PROTECT PUBLIC FINED £600,000

Two elderly people injured during construction of disabled ramp

Read the rest of this article »

Posted on 2nd January 2018

MAINTENANCE AND MANAGEMENT FIRM FINED

Joist failed and workman fell during flat roof replacement works

Read the rest of this article »

Posted on 2nd January 2018

FALL ON BLOCK AND BEAM FLOORING SYSTEM

Contractors failed to respond to planned fall protection problems

Read the rest of this article »

Posted on 2nd January 2018

FIRMS FAILED TO INSTALL FLOOR AS DESIGNED

Principal contractor penalised for not spotting contractor error

Read the rest of this article »

Posted on 2nd January 2018

LINTEL COLLAPSED DURING LOWERING OPERATION

Two workers injured as support props and structure topple

Read the rest of this article »

Posted on 2nd January 2018

CDM 2015: SEEING THE WOOD FOR THE TREES

End of year reflections on CDM 2015, health, safety and harm

Read the rest of this article »

Posted on 21st December 2017

FESTIVE GREETINGS TO ALL OUR READERS

Read the rest of this article »

Posted on 20th December 2017

HSE ENFORCEMENT WEEKLY UPDATE 20th DEC 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 20th December 2017

LORRY DRIVER PROSECUTED AFTER ROAD DEATH

Road worker died during motorway resurfacing project

Read the rest of this article »

Posted on 20th December 2017

MAJOR CONTRACTOR FINED £1.8M OVER ROAD DEATH

Road planer operation put roadworks pedestrians at risk of injury

Read the rest of this article »

Posted on 20th December 2017

MANAGER PROSECUTED OVER APPRENTICE INJURY

Untrained young worker fell through fragile rooflight

Read the rest of this article »

Posted on 20th December 2017

PUBLIC AND WORKERS EXPOSED TO ASBESTOS RISK

Client and contractor failed to identify and assess asbestos presence

Read the rest of this article »

Posted on 20th December 2017

RESTRAINT SAVES WORKER EJECTED FROM MEWP

Firms failed to separate crane and elevated mobile work platform

Read the rest of this article »

Posted on 20th December 2017

HSE PROSECUTE OVER POOR SILICA DUST CONTROL

Principal contractor failures led to gross exposure to RCS

Read the rest of this article »

Posted on 15th December 2017

HSE ENFORCEMENT WEEKLY UPDATE 13th DEC 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 15th December 2017

BUILDING INFORMATION MODELLING AND CDM 2015

Major contractor explains BIM risk mitigation opportunities

Read the rest of this article »

Posted on 15th December 2017
Turner Access Chipmunk Data
Total Access Ethentic
Higher Safety Turner Access