Turner Access Higher Safety Total Access
Total Access Ethentic Chipmunk Data
Chipmunk Data Turner Access Ethentic

TEMPORARY WORKS: HSE FREQUENTLY ASKED QUESTIONS

HSE provide answers to basic temporary works issues 

“Temporary works” are “engineered solutions” used to support or protect an existing structure or the permanent works during construction, or to support an item of plant or equipment, or the vertical sides or side-slopes of an excavation, or to provide access. The construction of most types of permanent works will require the use of some form of temporary works.

Temporary works is defined in BS5975: 2008 “Code of practice for temporary works procedures and the permissible stress design of falsework” as “(those) parts of the works that allow or enable construction of, protect, support or provide access to, the permanent works and which might or might not remain in place at the completion of the works”.

Examples of temporary works include, but are not limited to:

  • Earthworks – trenches, excavations, temporary slopes and stockpiles. Structures – formwork, falsework, propping, façade retention, needling, shoring, edge protection, scaffolding, temporary bridges, site hoarding and signage, site fencing, cofferdams.
  • Equipment/plant foundations – tower crane bases, supports, anchors and ties for construction hoists and mast climbing work platforms (MCWPs), groundworks to provide suitable locations for plant erection, e.g. mobile cranes and piling rigs.

HSE has now issued answers to a range of Frequently Asked Questions regarding “temporary works” which are repeated below.

More detailed information on Management of Temporary Works is also available. 

**************************

 

TEMPORARY WORKS – HSE FREQUENTLY ASKED QUESTIONS

 

What are permanent works?

Permanent works are the parts of a construction project that will be used and remain in position for a long time – e.g. 60 years. This includes buildings and structures such as bridges, roads, retaining walls, etc. The construction of most types of permanent works will require the use of some form of temporary works.

What are temporary works?

Temporary works (TW) are the parts of a construction project that are needed to enable the permanent works to be built. Usually the TW are removed after use – e.g. access scaffolds, props, shoring, excavation support, falsework and formwork, etc. Sometimes the TW is incorporated into the permanent works – e.g. haul road foundations and crane or piling platforms may be used for hardstanding or road foundations.

Are temporary works different to permanent works?

It is very important that the same degree of care and attention is given to the design and construction of temporary works (TW) as to the design and construction of the permanent works. As TW may be in place for only a short while there is a tendency to assume they are less important. This is incorrect. Lack of care with design, selection, assembly, etc leaves TW liable to fail or collapse. This places people at risk of injury and can cause the project to be delayed.

Can I organise the temporary works myself?

The person organising the temporary works needs to be aware of the problems that can occur at each stage of the process and how to prevent these. They need to coordinate design, selection of equipment, appointment of contractors, supervision of work, checking completion, authorisation to load and removal. Unless this is done in a thorough and systematic way problems are likely to occur. If you take this on yourself you must ensure each part of the process is correctly carried out.

Do I have to appoint a ‘temporary works coordinator’ (TWC)?

British Standard 5975 sets out one way of managing temporary works (TW) that has been found to work well on medium and large projects and uses the job title Temporary Works Coordinator (TWC). There is no legal requirement to use this job title or the BS recommended process, but you should remember that BS5975 provides an industry consensus view on what is considered to be good practice. The legal requirement is that the party in control must ensure that work is allocated and carried out in a manner that does not create unacceptable risk of harm to workers or members of the public. On projects with relatively simple TW needs, you may choose not to appoint a TWC. However, you must still make sure that TW are properly managed to ensure safety.

Do I need to provide calculations for every temporary works situation?

Where the situation is small scale and straightforward there may be a “standard solution” provided for the temporary works (TW). These include, for example, use of a tower or system scaffold for access; design of a basic access scaffold to a standard configuration using existing data from tables; selection of a trench box to support a 2m excavation in firm, dry ground. In each of these cases the person organising the TW will need to assess the ground to be sure it is suitable for the equipment involved, and check that any assumptions made in the calculations for the standard solution are valid for this particular situation and the conditions on site. On a simple job the supplier’s data will allow an experienced person to consider the necessary issues without further calculation.

Propping using standard equipment such as screw props (‘Acrows’) needs careful consideration. To select the type, size, number and decide spacing, information is needed about the loads that will act on the props. This will include the wall above and the additional load from any other floor or roof beams etc that enter the wall above or close to the opening. Even with proprietary equipment, the support system must be worked out by a person who knows the correct methods of assessing the loads and designing the support arrangement. Failure of TW is often found to result from the loadings being underestimated; and in particular where loadings from the sides are not considered.

Can all structural engineers design temporary works?

No. Temporary works (TW) can be very sensitive to how they are used and are easily affected by other work taking place nearby. For these reasons the TW designer needs TW training and experience.

If I get a structural engineer to design the temporary works will they be the project TWC?

No. Coordinating the temporary works (TW) is not automatically the responsibility of the engineer carrying out the design work. Coordination is a much wider role that includes planning where and when TW will be needed and ensuring that they are correctly installed, used, checked and maintained. Some design engineers may be happy to be additionally contracted to act as project Temporary Works Coordinator.

Latest Construction Health and Safety News

FATALITY: CRANE COLLAPSE ON HOMES PROJECT

Two workmen die in crane collapse in Crewe

Read the rest of this article »

Posted on 23rd June 2017

BUILD UK EXPLAINS PROJECT H&S TRAINING STANDARD

UK contractors clarify skill cards needed on CDM 2015 projects

Read the rest of this article »

Posted on 21st June 2017

HSE ENFORCEMENT WEEKLY UPDATE 21 JUNE 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 21st June 2017

CIVILS FIRMS PAYS PRICE OVER PUBLIC DANGER

Fencing wire struck member of public relaxing in own garden

Read the rest of this article »

Posted on 20th June 2017

DELAYED RESCUE CONTRIBUTED TO DEATH AT HEIGHT

MEWP operator died trapped between controls and roof beam

Read the rest of this article »

Posted on 20th June 2017

CLIENT FINED UNDER CDM 2007 & CDM 2015

Construction work must be properly managed from outset

Read the rest of this article »

Posted on 19th June 2017

WORKMAN BURNED WHILST CUTTING LIVE CABLE

Firms to pay £500,000 over unsafe system for electrical work

Read the rest of this article »

Posted on 19th June 2017

WORKMAN CHEATS DEATH IN 8M ROOFLIGHT FALL

Steel fabricators fined over unsafe short-term roofwork

Read the rest of this article »

Posted on 19th June 2017

HOMES FIRM DIRECTOR CONVICTED OF MANSLAUGHTER

Excavation collapse dangers ignored by director and digger operator

Read the rest of this article »

Posted on 14th June 2017

HSE ENFORCEMENT WEEKLY UPDATE 14th JUNE 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 14th June 2017

BOSS AND FOREMAN CONVICTED OF MANSLAUGHTER

Safety standards allowed to fall despite HSE enforcement action

Read the rest of this article »

Posted on 10th June 2017

WORK AT HEIGHT ADVANCES HIGHLIGHTED AT EXPO

Access Industry Forum (AIF) puts height safety first at Expo 2017

Read the rest of this article »

Posted on 9th June 2017

PRICE OF NON-COMPLIANCE RISES STEADILY

Roofing company fined £80,000 for ignoring advice and HSE notice

Read the rest of this article »

Posted on 9th June 2017

MANUAL HANDLING OFFENCE FINED £67,000

Significant risk in handling excavator wheel not avoided or assessed

Read the rest of this article »

Posted on 8th June 2017

COMPANY RELIED UPON EXPERIENCED WORKERS

Lack of precautions to prevent fall through fragile rooflight

Read the rest of this article »

Posted on 7th June 2017

CLIENT FAILED TO APPOINT COMPETENT CONTRACTOR

Contractor receives prison term whilst CDM client fined £160,000

Read the rest of this article »

Posted on 7th June 2017

PUZZLES HELP DELIVER CITB AND NEBOSH COURSES

Innovative new tool available to support effective H&S training

Read the rest of this article »

Posted on 7th June 2017

NEW DUMPER TO IMPROVE SAFETY AND EFFICIENCY

Manufacturer promises greater visibility, stability and operator protection

Read the rest of this article »

Posted on 7th June 2017

HSE ENFORCEMENT WEEKLY UPDATE 7th JUNE 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 7th June 2017

NEW GUIDE ON GUILTY PLEA SENTENCING

Sentencing Council guidelines may assist corporate H&S offenders

Read the rest of this article »

Posted on 6th June 2017

MAJOR CONTRACTOR RESPONDS TO ‘BEARDS BAN’ BLAST

Union calls for dust elimination and consultation before imposing ban

Read the rest of this article »

Posted on 5th June 2017

CONSTRUCTION DEATHS TUMBLE IN 2016/17

Latest HSE latest records suggests substantial drop in worker fatalities

Read the rest of this article »

Posted on 5th June 2017

WRONGLY INSTALLED MACHINE SEVERED HAND

Manufacturer instructions not followed during saw installation

Read the rest of this article »

Posted on 2nd June 2017

LACK OF SITE FENCING LED TO TRENCH DROWNING

Vulnerable member of the public died in flooded excavation

Read the rest of this article »

Posted on 2nd June 2017

NEW HSE ENDORSED MEWP GUIDANCE FOR MANAGERS

Securing safe plant and operation set out in new industry guide

Read the rest of this article »

Posted on 2nd June 2017
Turner Access Chipmunk Data
Total Access Ethentic
Higher Safety Turner Access