Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    NEW INDUSTRY GUIDE ON DEMOLITION AND ASBESTOS

    NFDC publish advice on non-licenable work during demolition

    The National Federation of Demolition Contractors (NFDC) has released a guidance note entitled:  Industry guidance for non-licensed work with asbestos containing materials within a demolition or refurbishment environment

    The note is described as an “informative & concise document” which is available free of charge on download from the NFDC website. The information contained within the guidance is for non-licensed work with asbestos containing materials only.

    NFDC advise that licensable work with asbestos containing materials is to be carried out by an HSE licensed asbestos removal contractor employing fully trained operatives holding a current medical certificate. For work with any type of asbestos it is recommended that the HSE publications L143 and HSG247 should be consulted.

    Howard Button NFDC CEO said

    ‘The industry was best placed to develop this Guidance due to our technical expertise and our experience in this field. Our members were crying out for a best practice guide to ensure the industry is able to maintain the high standards we set”

    ‘Wet and Drop’ technique explained

    The Guidance includes advice on the ‘Wet and Drop’ technique for use with asbestos cement roofing and side sheeting and states that:  

    “Historical data has proven that wetting and the mechanical reduction of asbestos cement roof and side sheeting is the least likely method to cause significant operative and environmental exposure to asbestos fibres.

    This method reduces time spent working at height but is often not suitable where the work area is immediately adjacent public areas (eg less than 100 metre public exclusion zone and or beyond the predicted ‘debris zone’). Where this method is to be employed the following controlled procedures should be implemented:”

    1. The predicted drop zone must be considered as an exclusion and respirator zone which is clearly delineated and must be clear of all debris, extrusions and obstructions to facilitate a thorough environmental clean on completion of the works.
    2. The sealing of drains and establishment of a containment system is essential to ensure that there is no possibility of any contamination of water courses or surface water catchments.
    3. An adequate supply of water must be established, preferably through a holding tank. Note: the predominant asbestos fibre type in asbestos cement is Chrysotile asbestos which is classed as being ‘Hydrophilic’ lending itself to water penetration. Water sprays alone can be considered as an effective method of dust/fibre control during take down, handling and disposal operations.
    4. Water sprays must be focused on the area of AC sheeting to be removed by way of machine mounted jets or ground based equipment.
    5. Work should be carried out on a bay by bay system, cutting and dropping the sections of roof or side sheeting to the ground. Breakage of the sheets should be kept to a minimum, so far as is reasonably practicable. Fallen sheets must not be driven over.
    6. The cleaning up of AC debris, ideally, should be carried out using a rubber tyred loading shovel fitted with a plain edged bucket. Operatives assisting with the clean up works must have non-licensed work training and be trained in the safe working procedures and be equipped with suitable RPE & PPE.
    7. A routine of decontamination must be established at the end of each shift and before any meal/fatigue/toilet/smoking breaks.
    8. The resultant debris must be loaded into a sound, secure (gaps sealed) and lockable container for disposal by a licensed carrier at a registered disposal facility in accordance with the Hazardous Waste Regulations and EA/Sepa protocols. Note: Open containers may be lined with heavy duty polythene sheeting that can be wrapped and tape sealed on completion of loading. Note: It is recommended that where practical enclosed containers be employed. Where open top containers are in use they should be fully sheeted to contain the load. The use of an easy sheet system alone may be inadequate if air is allowed to circulate below the sheet and within the container. This may cause damage to the polythene lining thus allowing a potential for fibre escape. Drivers are advised to consider weather conditions and the distances to travel from pick up point to disposal point.
    9. Background reassurance and personal monitoring should be carried out at key points around the working area with results monitored and recorded. Should monitoring identify any increase in fibre levels, which may increase operative or public exposure, work should be stopped and the system of work reviewed prior to recommencement.
    10. All waste water runoff must be contained and disposed of as contaminated waste; where a surfactant is used the resultant solidified runoff may be scraped up and disposed of with the asbestos debris.

    Latest Construction Health and Safety News

    HSE ENFORCEMENT WEEKLY UPDATE 12th DEC 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 12th December 2018

    HSE SAFETY ALERT: TOWER CRANE BRAKES

    Collapse of tower crane jib in high winds prompts HSE warning

    Read the rest of this article »

    Posted on 11th December 2018

    VISITING ENGINEER CRUSHED BY SCAFFOLD TUBES

    Principal contractor “signed off” contractor storage arrangements

    Read the rest of this article »

    Posted on 11th December 2018

    CONCRETE EJECTED BY PUMPING UNIT CLAIMED LIFE

    Company and director failed to train and supervise pumping operations

    Read the rest of this article »

    Posted on 5th December 2018

    REFRESHED GUIDANCE ON FITNESS TO OPERATE PLANT

    Construction plant medical fitness Good Practice Guide

    Read the rest of this article »

    Posted on 4th December 2018

    MAJOR CONTRACTOR & LUL USED UNSAFE SYSTEM

    Work method to eliminate moving vehicle hazard not adopted

    Read the rest of this article »

    Posted on 4th December 2018

    OVERTURNING LORRY CAUSED DEATH OF DRIVER

    Groundworks project stockpiling arrangements not properly managed

    Read the rest of this article »

    Posted on 3rd December 2018

    FORTH BRIDGE LIFTING OPERATION NOT PLANNED

    Major project PC failed to plan, supervise and carry out lift safely

    Read the rest of this article »

    Posted on 3rd December 2018

    DEVELOPER FAILED ON ASBESTOS ASSESSMENT

    HSE inspection revealed refurb works without asbestos survey

    Read the rest of this article »

    Posted on 28th November 2018

    POST DRIVER HAMMER CRUSHED HAND OF WORKMAN

    Unsafe system of work for vehicle crash barrier installation

    Read the rest of this article »

    Posted on 28th November 2018

    WORKER FELL FROM LOFT THROUGH CEILING

    Major house builder lacked understanding of loft fragile surfaces risk

    Read the rest of this article »

    Posted on 28th November 2018

    NEW SITE DUMPER SAFETY GUIDANCE ISSUED

    Construction plant sector concerns prompts CPA consults on draft

    Read the rest of this article »

    Posted on 28th November 2018

    CCTV INSTALLER FELL THROUGH FRAGILE ROOFLIGHT

    Contractor failed to properly plan and control the risks

    Read the rest of this article »

    Posted on 28th November 2018

    VISITOR DIED FALLING INTO CONCEALED BASEMENT

    Contractor failed to protect basement void on domestic project

    Read the rest of this article »

    Posted on 28th November 2018

    RACKING FALL REVEALED UNSAFE SYSTEM OF WORK

    European firm fined £300,000 after UK sub-contractor employee fell

    Read the rest of this article »

    Posted on 18th November 2018

    FAILURE TO ACT ON VIBRATION AND SILICA HAZARDS

    Worker health put at risk during stripping of furnace lining

    Read the rest of this article »

    Posted on 18th November 2018

    MAJOR FM FIRM FAILED TO MAINTAIN BACK-UP POWER

    Power loss at laboratory site created potential risk from biological agents

    Read the rest of this article »

    Posted on 18th November 2018

    IGNORING HSE PROHIBITIONS COST FIRM £250,000

    CDM 2015 and work at height requirements repeatedly breached

    Read the rest of this article »

    Posted on 16th November 2018

    ROOF COLLAPSED UNDER EXCESS LOADING

    Director and company fined over roof design failures

    Read the rest of this article »

    Posted on 11th November 2018

    FORK LIFT OVERTURNED IN SCAFFOLDING YARD

    Untrained operator suffered life changing crush injuries

    Read the rest of this article »

    Posted on 10th November 2018

    STRUCTURAL SAFETY ALERT: EFFECTS OF SCALE

    SCOSS issues alert after concerns disclosed over ‘large structures’

    Read the rest of this article »

    Posted on 7th November 2018

    ASBESTOS EXPOSED BY UNTRAINED WORKERS

    Contractor failed to act properly despite HSE intervention

    Read the rest of this article »

    Posted on 7th November 2018

    GAS MAIN STRIKE REPAIR CAUSED SEVERE BURNS

    Contractor excavator damage to gas pipe ends in £1.2m fine

    Read the rest of this article »

    Posted on 7th November 2018

    REBAR FELL FROM FLT IN UNSAFE LIFTING OPERATION

    Multiple fractures caused by inappropriate use of fork lift

    Read the rest of this article »

    Posted on 7th November 2018

    POORLY PLANNED LIFT DISMANTLE INJURED WORKMAN

    Counterweight or suspension rope struck worker in lift shaft

    Read the rest of this article »

    Posted on 1st November 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic