• Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    NEW INDUSTRY GUIDE ON DEMOLITION AND ASBESTOS

    NFDC publish advice on non-licenable work during demolition

    The National Federation of Demolition Contractors (NFDC) has released a guidance note entitled:  Industry guidance for non-licensed work with asbestos containing materials within a demolition or refurbishment environment

    The note is described as an “informative & concise document” which is available free of charge on download from the NFDC website. The information contained within the guidance is for non-licensed work with asbestos containing materials only.

    NFDC advise that licensable work with asbestos containing materials is to be carried out by an HSE licensed asbestos removal contractor employing fully trained operatives holding a current medical certificate. For work with any type of asbestos it is recommended that the HSE publications L143 and HSG247 should be consulted.

    Howard Button NFDC CEO said

    ‘The industry was best placed to develop this Guidance due to our technical expertise and our experience in this field. Our members were crying out for a best practice guide to ensure the industry is able to maintain the high standards we set”

    ‘Wet and Drop’ technique explained

    The Guidance includes advice on the ‘Wet and Drop’ technique for use with asbestos cement roofing and side sheeting and states that:  

    “Historical data has proven that wetting and the mechanical reduction of asbestos cement roof and side sheeting is the least likely method to cause significant operative and environmental exposure to asbestos fibres.

    This method reduces time spent working at height but is often not suitable where the work area is immediately adjacent public areas (eg less than 100 metre public exclusion zone and or beyond the predicted ‘debris zone’). Where this method is to be employed the following controlled procedures should be implemented:”

    1. The predicted drop zone must be considered as an exclusion and respirator zone which is clearly delineated and must be clear of all debris, extrusions and obstructions to facilitate a thorough environmental clean on completion of the works.
    2. The sealing of drains and establishment of a containment system is essential to ensure that there is no possibility of any contamination of water courses or surface water catchments.
    3. An adequate supply of water must be established, preferably through a holding tank. Note: the predominant asbestos fibre type in asbestos cement is Chrysotile asbestos which is classed as being ‘Hydrophilic’ lending itself to water penetration. Water sprays alone can be considered as an effective method of dust/fibre control during take down, handling and disposal operations.
    4. Water sprays must be focused on the area of AC sheeting to be removed by way of machine mounted jets or ground based equipment.
    5. Work should be carried out on a bay by bay system, cutting and dropping the sections of roof or side sheeting to the ground. Breakage of the sheets should be kept to a minimum, so far as is reasonably practicable. Fallen sheets must not be driven over.
    6. The cleaning up of AC debris, ideally, should be carried out using a rubber tyred loading shovel fitted with a plain edged bucket. Operatives assisting with the clean up works must have non-licensed work training and be trained in the safe working procedures and be equipped with suitable RPE & PPE.
    7. A routine of decontamination must be established at the end of each shift and before any meal/fatigue/toilet/smoking breaks.
    8. The resultant debris must be loaded into a sound, secure (gaps sealed) and lockable container for disposal by a licensed carrier at a registered disposal facility in accordance with the Hazardous Waste Regulations and EA/Sepa protocols. Note: Open containers may be lined with heavy duty polythene sheeting that can be wrapped and tape sealed on completion of loading. Note: It is recommended that where practical enclosed containers be employed. Where open top containers are in use they should be fully sheeted to contain the load. The use of an easy sheet system alone may be inadequate if air is allowed to circulate below the sheet and within the container. This may cause damage to the polythene lining thus allowing a potential for fibre escape. Drivers are advised to consider weather conditions and the distances to travel from pick up point to disposal point.
    9. Background reassurance and personal monitoring should be carried out at key points around the working area with results monitored and recorded. Should monitoring identify any increase in fibre levels, which may increase operative or public exposure, work should be stopped and the system of work reviewed prior to recommencement.
    10. All waste water runoff must be contained and disposed of as contaminated waste; where a surfactant is used the resultant solidified runoff may be scraped up and disposed of with the asbestos debris.

    Latest Construction Health and Safety News

    CONTRACTS MANAGER HANDED TWO YEAR PRISON TERM

    Safety fall arrest netting would have saved life of deceased workman

    Read the rest of this article »

    Posted on 15th January 2020

    WORKER FATALLY INJURED BY CONCRETE BEAM

    Lifting operation not properly planned, managed and supervised

    Read the rest of this article »

    Posted on 15th January 2020

    TREE FELLING OPERATIONS LACKED DEFINED COMMS

    Workman struck by falling tree inside “normal” exclusion zone

    Read the rest of this article »

    Posted on 14th January 2020

    CONTRACTOR ARRESTED OVER WELFARE FAILINGS

    Recalcitrant sole trader failed to attend court hearing

    Read the rest of this article »

    Posted on 14th January 2020

    MAJOR DEMOLITION CONTRACTOR FINED £500,000

    Collapse of concrete slab caused death of worker and excavator fall

    Read the rest of this article »

    Posted on 14th January 2020

    FALL FROM LADDER WHILST CARRYING BUCKET

    Contractor failed to provide basic safe lifting aids

    Read the rest of this article »

    Posted on 14th January 2020

    FAILURE TO COMPLY WITH HSE NOTICE PROVES COSTLY

    Director given suspended jail term and company fined £60,000

    Read the rest of this article »

    Posted on 14th January 2020

    DEVELOPER FAILED TO PLAN AND CHECK COMPETENCE

    Fall caused by ad-hoc working methods and lack of monitoring

    Read the rest of this article »

    Posted on 14th January 2020

    CYLINDER LEAK TEST CAUSED FATAL INJURIES

    Corrosion inhibitor triggered failure and shrapnel ejection

    Read the rest of this article »

    Posted on 14th January 2020

    FESTIVE GREETINGS TO ALL OUR READERS

    Read the rest of this article »

    Posted on 20th December 2019

    JAIL TERM FOLLOWS ROUTINE HSE SPOT CHECK

    Director of a roofing firm handed a suspended prison sentence

    Read the rest of this article »

    Posted on 19th December 2019

    TEENAGER FELL 3M DURING BLOCK AND BEAM WORK

    Workers uninstructed and left to devise own safe system of work

    Read the rest of this article »

    Posted on 19th December 2019

    PARCEL CARRIER FINED HEAVILY OVER FLT INCIDENT

    Reversing fork lift lacked segregation from pedestrians

    Read the rest of this article »

    Posted on 18th December 2019

    CONTRACTOR FINED OVER FLOOR OPENING FALL

    Thorough risk assessment and edge protection were both inadequate

    Read the rest of this article »

    Posted on 18th December 2019

    THREE WORKERS “CARRIED ALONG” IN SEWER INCIDENT

    Mentally affected and one man treated for long-term traumatic stress

    Read the rest of this article »

    Posted on 11th December 2019

    SOLAR FIRM AND DIRECTOR SENTENCED OVER DEATH

    Brother of business owner died in fall during panel installation

    Read the rest of this article »

    Posted on 10th December 2019

    DIRECTOR AND COMPANY FINED FOR ASBESTOS RISK

    HSE refurbishment campaign inspection revealed asbestos offences

    Read the rest of this article »

    Posted on 10th December 2019

    BULK BAG COLLAPSE CAUSED BY UNSAFE STACKING

    Bulk bag collapsed onto workman when struck by fork lift

    Read the rest of this article »

    Posted on 9th December 2019

    INTERLOCKED GUARD NOT WORKING TO ISOLATE POWER

    Two workmen seriously injured when plant started unexpectedly

    Read the rest of this article »

    Posted on 9th December 2019

    STREET FURNITURE RISK TO PUBLIC FINED £1.4M

    Council prosecuted following injury to child playing on hinged bollard

    Read the rest of this article »

    Posted on 9th December 2019

    WORKMEN SUFFER SERIOUS BURNS FROM CABLE STRIKE

    Assessment and system of work failed to appreciate electrical risk

    Read the rest of this article »

    Posted on 29th November 2019

    LADDERS WERE INAPPROPRIATE FOR WORK ON ROOF

    Workman paralysed after falling whilst installing roof ladder

    Read the rest of this article »

    Posted on 28th November 2019

    FIRM FAILED TO MANAGE EXHAUST VENTILATION

    HSE enforcement notices on wood dust and welding fume ignored

    Read the rest of this article »

    Posted on 27th November 2019

    RECALCITRANT DIRECTOR BARRED FROM OFFICE

    Dangerous telehandler used despite earlier fatality and enforcement

    Read the rest of this article »

    Posted on 25th November 2019

    DIRECTOR HID UNSAFE WORKING PRACTICES FROM HSE

    Workers exposed to sprayed paints containing asthma causing isocyantes

    Read the rest of this article »

    Posted on 25th November 2019
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data