• Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    CLIENT AND CDM DESIGNER FINED OVER LACK OF COORDINATOR

    CDM-C would have prevented asbestos breaches on independent school project

    Construction client Sherborne School and Peter Eldridge, a director responsible for the refurbishment project have been ordered to pay almost £90,000 in fines and prosecution costs after unsafe removal of asbestos insulation boards (AIB) led to several people being exposed to asbestos.

    AIB was removed in a way which exposed building contractors and a teenage work experience student to asbestos leaving them at risk of developing serious and potentially fatal diseases later in life.

    HSE investigators found there was inadequate planning and failure to carry out a full asbestos survey from the initial design stages in May 2008 to start of the construction phase in July 2009. This despite a sample being taken from the building in 2008 which found asbestos in other parts of the school and a an asbestos register kept for the school buildings.

    The court heard that Mr Eldridge and the school failed to appoint a Coordinator (CDM-C) for the refurbishment project despite it being a requirement of the CDM Regulations 2007 for a project of such size.

    The CDM-C would have ensured a full refurbishment and demolition asbestos survey was completed in advance of construction work. Licensed asbestos contractors could then have been appointed to safely remove it.

    Risk easily avoided if competent CDM-C engaged

    Sherborne School was found guilty of breaching Regulation 4(8) of the Control of Asbestos Regulations 2006 and Regulation 14 of the Construction (Design and Management) Regulations 2007. The school was fined a total of £60,000 and ordered to pay £13,000 in costs.

    Peter Eldridge, of Long Street, Sherborne, Dorset, was found guilty by virtue of Section 37 of the Health and Safety at Work etc Act for his neglect as a director for breaches of designer Regulations 11(3) and 18(1) of the Construction (Design and Management) Regulations 2007 for contributing to the failings of his company. He was fined a total of £10,000 with costs of £6,000.

    • CDM 2007 Regulation 14 covers the appointment of a CDM co-ordinator;
    • CDM 2007 Regulation 11(3) states: “every designer shall in preparing or modifying a design which may be used in construction work in Great Britain avoid foreseeable risks to the health and safety of any person”;
    • CDM 2007 Regulation 18(1) states: “where a project is notifiable, no designer shall commence work (other than initial design work) in relation to the project unless a CDM co-ordinator has been appointed for the project.”

    Speaking after the prosecution, HSE Inspector Joanna Teasdale, said:

    “Both Peter Eldridge and Sherborne School knew about the risks posed by the presence of asbestos in the school buildings, and yet they failed to manage the risk of exposure to asbestos fibres during the refurbishment project.

    As a result several people, including at least one teenager, were put at unnecessary risk. In being exposed to asbestos fibres they could develop a serious and potentially fatal illness.

    Although Sherborne School was the client, it still had a duty to manage the control of asbestos on its site, and to be aware of the requirements of removing asbestos safely.

    This incident and the risk to those involved could have been easily avoided if competent people had been engaged during the planning of the refurbishment project to advise the school, such as a CDM coordinator.”

    Latest Construction Health and Safety News

    PANEL STRUCK WORKMAN DURING LIFTING OPERATION

    Third party contractor falls victim of poor lift planning

    Read the rest of this article »

    Posted on 21st May 2018

    DIRECTOR LED HAZARDOUS WORK AT HEIGHT

    Three occasions when work lacked suitable and sufficient precautions

    Read the rest of this article »

    Posted on 21st May 2018

    RISK ASSESSED BUT CONTROLS FOUND WANTING

    Joiner fell through unprotected opening on roof of new building

    Read the rest of this article »

    Posted on 21st May 2018

    RIBA CRITICAL OF HACKITT REVIEW FINAL REPORT

    High rise residential review dismissed as “major missed opportunity”

    Read the rest of this article »

    Posted on 21st May 2018

    HSE ENFORCEMENT WEEKLY UPDATE 16th MAY 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 16th May 2018

    CONSTRUCTION SECTOR DEATHS: THE ‘BIG THREE’

    HSE in-year fatalities for 2017/18 may indicate upward trend

    Read the rest of this article »

    Posted on 16th May 2018

    SCAFFOLDING SITE ACCIDENTS AT RECORD LOW

    NASC Annual Report reveals all time low in 2017 incidents

    Read the rest of this article »

    Posted on 14th May 2018

    DUMPER TRUCK HAND-BRAKE NOT MAINTAINED

    Workman injured when pinned against stack of concrete blocks

    Read the rest of this article »

    Posted on 14th May 2018

    SPARE POWER INTERLOCK KEY CAUSED DEATH

    Dangerous machinery safety precautions defeated for maintenance tasks

    Read the rest of this article »

    Posted on 10th May 2018

    HSE ENFORCEMENT WEEKLY UPDATE 9th MAY 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 9th May 2018

    COLLAPSED CAR PARK WAS UNDER REPAIR

    Rusted steel supports triggered collapse of fascia and floor

    Read the rest of this article »

    Posted on 8th May 2018

    DUMPER OVERTURN CAUSED FATAL INJURIES

    Precautions during spoil heap creation were inadequate

    Read the rest of this article »

    Posted on 8th May 2018

    HARDWOOD DUST CONTROL NOT MAINTAINED

    Manufacturer failed to examine and test local extraction system

    Read the rest of this article »

    Posted on 8th May 2018

    SCAFFOLD CONTRACTOR OVERLOOKED MAJOR HAZARD

    Well-known risk unidentified during scaffold erection project

    Read the rest of this article »

    Posted on 8th May 2018

    THREE FIRMS FINED £1/2M FOR FRAGILE RISK FAILURES

    Fall through rooflight hazard poorly planned and managed

    Read the rest of this article »

    Posted on 2nd May 2018

    CONTRACTORS IGNORED ASBESTOS RISK

    Asbestos pipe lagging worked on without licence and proper precautions

    Read the rest of this article »

    Posted on 2nd May 2018

    HSE ENFORCEMENT UPDATE 2nd MAY 2018

    hselogo1Prosecutions and enforcement notices update and analysis

    Read the rest of this article »

    Posted on 2nd May 2018

    SOFT LANDING BAGS TRIGGERED A FALL!

    Fall arrest bag thrown from scaffold took workman with bag

    Read the rest of this article »

    Posted on 1st May 2018

    FAILURE TO NOTIFY HSE PREVENTED INVESTIGATION

    Regulator prosecutes over RIDDOR non-compliance

    Read the rest of this article »

    Posted on 1st May 2018

    CLIENT AND CONTRACTOR TOGETHER IN COURT

    Fragile roof fall exposes client failure to manage project

    Read the rest of this article »

    Posted on 1st May 2018

    UNTRAINED DUMPER DRIVER SURVIVES OVERTURN

    Inadequate barriers plus lack of operator and manager training

    Read the rest of this article »

    Posted on 1st May 2018

    PROJECT CLIENT PROSECUTED UNDER CDM 2015

    Building demolished without suitable precautions to prevent danger

    Read the rest of this article »

    Posted on 1st May 2018

    LORRY RUNAWAY CLAIMED LIFE OF DRIVER

    Workman died after being drawn under trailer

    Read the rest of this article »

    Posted on 25th April 2018

    PETROL VAPOUR DANGER LEFT UNCONTROLLED

    Workman suffered severe burns during refuelling equipment

    Read the rest of this article »

    Posted on 25th April 2018

    HSE ENFORCEMENT UPDATE 25th APRIL 2018

    hselogo1Prosecutions and enforcement notices update and analysis

    Read the rest of this article »

    Posted on 25th April 2018
    Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • One Response to “CLIENT AND CDM DESIGNER FINED OVER LACK OF COORDINATOR”

    1. HSE ENFORCEMENT WEEKLY UPDATE 19th SEPTEMBER 2012 | PP Construction Safety News Desk Says:

      […] CLIENT AND CDM DESIGNER FINED OVER LACK OF COORDINATOR […]