Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    CLIENT AND CDM DESIGNER FINED OVER LACK OF COORDINATOR

    CDM-C would have prevented asbestos breaches on independent school project

    Construction client Sherborne School and Peter Eldridge, a director responsible for the refurbishment project have been ordered to pay almost £90,000 in fines and prosecution costs after unsafe removal of asbestos insulation boards (AIB) led to several people being exposed to asbestos.

    AIB was removed in a way which exposed building contractors and a teenage work experience student to asbestos leaving them at risk of developing serious and potentially fatal diseases later in life.

    HSE investigators found there was inadequate planning and failure to carry out a full asbestos survey from the initial design stages in May 2008 to start of the construction phase in July 2009. This despite a sample being taken from the building in 2008 which found asbestos in other parts of the school and a an asbestos register kept for the school buildings.

    The court heard that Mr Eldridge and the school failed to appoint a Coordinator (CDM-C) for the refurbishment project despite it being a requirement of the CDM Regulations 2007 for a project of such size.

    The CDM-C would have ensured a full refurbishment and demolition asbestos survey was completed in advance of construction work. Licensed asbestos contractors could then have been appointed to safely remove it.

    Risk easily avoided if competent CDM-C engaged

    Sherborne School was found guilty of breaching Regulation 4(8) of the Control of Asbestos Regulations 2006 and Regulation 14 of the Construction (Design and Management) Regulations 2007. The school was fined a total of £60,000 and ordered to pay £13,000 in costs.

    Peter Eldridge, of Long Street, Sherborne, Dorset, was found guilty by virtue of Section 37 of the Health and Safety at Work etc Act for his neglect as a director for breaches of designer Regulations 11(3) and 18(1) of the Construction (Design and Management) Regulations 2007 for contributing to the failings of his company. He was fined a total of £10,000 with costs of £6,000.

    • CDM 2007 Regulation 14 covers the appointment of a CDM co-ordinator;
    • CDM 2007 Regulation 11(3) states: “every designer shall in preparing or modifying a design which may be used in construction work in Great Britain avoid foreseeable risks to the health and safety of any person”;
    • CDM 2007 Regulation 18(1) states: “where a project is notifiable, no designer shall commence work (other than initial design work) in relation to the project unless a CDM co-ordinator has been appointed for the project.”

    Speaking after the prosecution, HSE Inspector Joanna Teasdale, said:

    “Both Peter Eldridge and Sherborne School knew about the risks posed by the presence of asbestos in the school buildings, and yet they failed to manage the risk of exposure to asbestos fibres during the refurbishment project.

    As a result several people, including at least one teenager, were put at unnecessary risk. In being exposed to asbestos fibres they could develop a serious and potentially fatal illness.

    Although Sherborne School was the client, it still had a duty to manage the control of asbestos on its site, and to be aware of the requirements of removing asbestos safely.

    This incident and the risk to those involved could have been easily avoided if competent people had been engaged during the planning of the refurbishment project to advise the school, such as a CDM coordinator.”

    Latest Construction Health and Safety News

    ROOF COLLAPSED UNDER EXCESS LOADING

    Director and company fined over roof design failures

    Read the rest of this article »

    Posted on 11th November 2018

    FORK LIFT OVERTURNED IN SCAFFOLDING YARD

    Untrained operator suffered life changing crush injuries

    Read the rest of this article »

    Posted on 10th November 2018

    STRUCTURAL SAFETY ALERT: EFFECTS OF SCALE

    SCOSS issues alert after concerns disclosed over ‘large structures’

    Read the rest of this article »

    Posted on 7th November 2018

    ASBESTOS EXPOSED BY UNTRAINED WORKERS

    Contractor failed to act properly despite HSE intervention

    Read the rest of this article »

    Posted on 7th November 2018

    GAS MAIN STRIKE REPAIR CAUSED SEVERE BURNS

    Contractor excavator damage to gas pipe ends in £1.2m fine

    Read the rest of this article »

    Posted on 7th November 2018

    REBAR FELL FROM FLT IN UNSAFE LIFTING OPERATION

    Multiple fractures caused by inappropriate use of fork lift

    Read the rest of this article »

    Posted on 7th November 2018

    HSE ENFORCEMENT WEEKLY UPDATE 7th NOV 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 7th November 2018

    POORLY PLANNED LIFT DISMANTLE INJURED WORKMAN

    Counterweight or suspension rope struck worker in lift shaft

    Read the rest of this article »

    Posted on 1st November 2018

    CONSTRUCTION INJURY AND ILL-HEALTH 2017/18

    hselogo1Fatal injury rate in long term decline whilst ill-health trend flat lining

    Read the rest of this article »

    Posted on 1st November 2018

    DUMPER DRIVEN INTO OPEN UNGUARDED EXCAVATION

    Contractor fined over absence of suitable excavation / dumper precautions

    Read the rest of this article »

    Posted on 1st November 2018

    DEATH FAILED TO TRIGGER PREVENTIVE ACTION

    Prison term for director whilst his company ordered to pay £3/4m

    Read the rest of this article »

    Posted on 29th October 2018

    FAILURE TO MAINTAIN GUARDS PROVES COSTLY

    Woodworking machinery defective despite previous HSE advice

    Read the rest of this article »

    Posted on 26th October 2018

    CISRS LAUNCH SYSTEM SCAFFOLD INSPECTION COURSES

    Training courses prompted by growing use of system scaffolding

    Read the rest of this article »

    Posted on 25th October 2018

    HSE INSPECTS CLADDING REMOVAL AND REPLACEMENT

    hselogo1Advice to Inspectors published on fire risk during work on tall buildings

    Read the rest of this article »

    Posted on 25th October 2018

    HIGHWAYS, RAIL AND WATER HEALTH & SAFETY HUBS

    Websites provide useful information, alerts and tools

    Read the rest of this article »

    Posted on 24th October 2018

    ELIMINATING CONCRETE DRILLING VIBRATION HAZARD

    Cutting specialist innovation avoids vibration exposure management

    Read the rest of this article »

    Posted on 24th October 2018

    NEW MEWP WORK AT HEIGHT RESCUE GUIDANCE

    Industry body publishes simple guidance on MEWP stranding actions

    Read the rest of this article »

    Posted on 24th October 2018

    HSE PUBLISH RIDDOR DATA VISUALISATION TOOL

    hselogo1Construction injury records made more relevant and easily used

    Read the rest of this article »

    Posted on 24th October 2018

    COUNCIL OVERLOOKED ICE RINK SLIPPING RISK

    Obvious risk of employees falling on ice rink was left uncontrolled

    Read the rest of this article »

    Posted on 22nd October 2018

    STRUCTURAL SAFETY BODY LATEST NEWSLETTER

    CROSS publishes reports and expert comment on a range of issues

    Read the rest of this article »

    Posted on 22nd October 2018

    YOUNG WORKER FELL FROM PETROL STATION CANOPY

    Steel fabricator after young construction worker falls on first day at work

    Read the rest of this article »

    Posted on 18th October 2018

    FIRM FINED OVER FAILURE AT ASSESS VIBRATION RISK

    Vibration regulations not acted upon until seven years in operation

    Read the rest of this article »

    Posted on 18th October 2018

    FAILURE TO ISOLATE LEAVES WORKMAN PARALYSED

    Conveyor guards removed before power source isolated

    Read the rest of this article »

    Posted on 16th October 2018

    TRADING STANDARDS AND HSE ACT IN CONCERT

    Director given prison term over fraud and health and safety breaches

    Read the rest of this article »

    Posted on 15th October 2018

    BUILDER ERROR CAUSED FALL OF RESIDENT

    Director prosecuted over refurb project danger to others

    Read the rest of this article »

    Posted on 12th October 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    One Response to “CLIENT AND CDM DESIGNER FINED OVER LACK OF COORDINATOR”

    1. HSE ENFORCEMENT WEEKLY UPDATE 19th SEPTEMBER 2012 | PP Construction Safety News Desk Says:

      […] CLIENT AND CDM DESIGNER FINED OVER LACK OF COORDINATOR […]