Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    CLIENT AND CDM DESIGNER FINED OVER LACK OF COORDINATOR

    CDM-C would have prevented asbestos breaches on independent school project

    Construction client Sherborne School and Peter Eldridge, a director responsible for the refurbishment project have been ordered to pay almost £90,000 in fines and prosecution costs after unsafe removal of asbestos insulation boards (AIB) led to several people being exposed to asbestos.

    AIB was removed in a way which exposed building contractors and a teenage work experience student to asbestos leaving them at risk of developing serious and potentially fatal diseases later in life.

    HSE investigators found there was inadequate planning and failure to carry out a full asbestos survey from the initial design stages in May 2008 to start of the construction phase in July 2009. This despite a sample being taken from the building in 2008 which found asbestos in other parts of the school and a an asbestos register kept for the school buildings.

    The court heard that Mr Eldridge and the school failed to appoint a Coordinator (CDM-C) for the refurbishment project despite it being a requirement of the CDM Regulations 2007 for a project of such size.

    The CDM-C would have ensured a full refurbishment and demolition asbestos survey was completed in advance of construction work. Licensed asbestos contractors could then have been appointed to safely remove it.

    Risk easily avoided if competent CDM-C engaged

    Sherborne School was found guilty of breaching Regulation 4(8) of the Control of Asbestos Regulations 2006 and Regulation 14 of the Construction (Design and Management) Regulations 2007. The school was fined a total of £60,000 and ordered to pay £13,000 in costs.

    Peter Eldridge, of Long Street, Sherborne, Dorset, was found guilty by virtue of Section 37 of the Health and Safety at Work etc Act for his neglect as a director for breaches of designer Regulations 11(3) and 18(1) of the Construction (Design and Management) Regulations 2007 for contributing to the failings of his company. He was fined a total of £10,000 with costs of £6,000.

    • CDM 2007 Regulation 14 covers the appointment of a CDM co-ordinator;
    • CDM 2007 Regulation 11(3) states: “every designer shall in preparing or modifying a design which may be used in construction work in Great Britain avoid foreseeable risks to the health and safety of any person”;
    • CDM 2007 Regulation 18(1) states: “where a project is notifiable, no designer shall commence work (other than initial design work) in relation to the project unless a CDM co-ordinator has been appointed for the project.”

    Speaking after the prosecution, HSE Inspector Joanna Teasdale, said:

    “Both Peter Eldridge and Sherborne School knew about the risks posed by the presence of asbestos in the school buildings, and yet they failed to manage the risk of exposure to asbestos fibres during the refurbishment project.

    As a result several people, including at least one teenager, were put at unnecessary risk. In being exposed to asbestos fibres they could develop a serious and potentially fatal illness.

    Although Sherborne School was the client, it still had a duty to manage the control of asbestos on its site, and to be aware of the requirements of removing asbestos safely.

    This incident and the risk to those involved could have been easily avoided if competent people had been engaged during the planning of the refurbishment project to advise the school, such as a CDM coordinator.”

    Latest Construction Health and Safety News

    HSE SEEKS CONSTRUCTION ‘DUST BUSTER’ PARTNERS

    Regulator uses social media to raise dust dangers and using right controls

    Read the rest of this article »

    Posted on 24th September 2018

    MAJOR HOMES BUSINESS EXPOSED PUBLIC TO RISK

    Residential propert refurb project created carbon monoxide danger

    Read the rest of this article »

    Posted on 24th September 2018

    HSE CONSTRUCTION DUST CONTROL ‘BLITZ’ STARTS

    Regulator inspections will check health taken as seriously as safety

    Read the rest of this article »

    Posted on 20th September 2018

    FLOOR CONSTRUCTION SYSTEM OF WORK UNSAFE

    Welder fell 3m from mezzanine area through purlin openings

    Read the rest of this article »

    Posted on 20th September 2018

    WORKER SUFFERS FATAL BURNS IN OXYGEN RICH AREA

    Sparks from angle grinder ignited clothing of workman in confined space

    Read the rest of this article »

    Posted on 19th September 2018

    RIBA PUBLISH DRAFT POST GRENFELL FIRE SAFETY PLAN

    Architects institute consults on ‘golden thread of fire safety information’

    Read the rest of this article »

    Posted on 19th September 2018

    MAJOR UK CONTRACTORS HIT BY MAJOR FINES

    Firms ordered to pay over £3m after foot trapped in rotating ‘screw’

    Read the rest of this article »

    Posted on 19th September 2018

    HSE ENFORCEMENT WEEKLY UPDATE 19th SEPT 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 19th September 2018

    DRIVER DIED TRAPPED BETWEEN TRAILER AND VEHICLE

    Firm fined £1.5 million over failure to assess coupling operations

    Read the rest of this article »

    Posted on 14th September 2018

    ACTUAL SYSTEM OF WORK WAS OPPOSITE OF RAMS

    Workman fell 4m through fragile asbestos roof sheet

    Read the rest of this article »

    Posted on 13th September 2018

    CDM PRINCIPAL DESIGNER FUNCTION MISUNDERSTOOD?

    Consultants claim CDM 2015 design risk management has ‘gone backwards’

    Read the rest of this article »

    Posted on 8th September 2018

    RISK ASSESSED PRECAUTIONS NOT IMPLEMENTED

    Action not paperwork essential to prevent fall during lifting operation

    Read the rest of this article »

    Posted on 7th September 2018

    CROSSRAIL PUBLISH BEST PRACTICE H&S GUIDES

    Sharing major project best practice can leave a lasting legacy

    Read the rest of this article »

    Posted on 5th September 2018

    SCHOOL STAFF LACKED ASBESTOS AWARENESS TRAINING

    Council fined £200k over asbestos flue and gasket rope failures

    Read the rest of this article »

    Posted on 5th September 2018

    INCIDENT: MEWP OVERTURN IN CITY CENTRE

    Images show aftermath of mobile elevating platform collapse

    Read the rest of this article »

    Posted on 5th September 2018

    SAFETY ALERT: DEFECTIVE SCAFFOLD COUPLER

    National Access and Scaffolding Confederation issues warning

    Read the rest of this article »

    Posted on 31st August 2018

    DEMOLISHING INTERNAL WALL REVEALED ASBESTOS

    Firm lacked survey and asbestos management plan for premises

    Read the rest of this article »

    Posted on 31st August 2018

    NEW HEALTH AND SAFETY TEST FOR ARCHITECTS

    RIBA raise the bar for members on design risk management and ‘life safety’

    Read the rest of this article »

    Posted on 31st August 2018

    POWER BUSINESSES FAILED ON LIFTING OPERATION

    Panel fell on workman during turbine maintenance project

    Read the rest of this article »

    Posted on 31st August 2018

    MAJOR INFRASTRUCTURE FIRM COMMITS TO ZERO HARM

    Behaviours to deliver zero lost time injury incident rate by 2021

    Read the rest of this article »

    Posted on 31st August 2018

    MANAGING TOWER CRANE FALLING OBJECT RISK

    CPA issues new technical information note

    Read the rest of this article »

    Posted on 31st August 2018

    POST EXPLOSION ASBESTOS WORK WAS UNSAFE

    Asbestos cement panels removed and cut with power tools

    Read the rest of this article »

    Posted on 31st August 2018

    FALL THROUGH UNFLOORED FACTORY ROOF SPACE

    Non-routine tasks require assessment and clear risk controls

    Read the rest of this article »

    Posted on 31st August 2018

    SEVENTH LONDON CYCLIST DEATH DURING 2018

    Building products vehicle involved in death of Queens doctor

    Read the rest of this article »

    Posted on 17th August 2018

    MAJOR CONTRACTOR FAILED TO SUPERVISE LIFT

    Errors whilst lifting pre-cast concrete blocks fined £600,000

    Read the rest of this article »

    Posted on 14th August 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    One Response to “CLIENT AND CDM DESIGNER FINED OVER LACK OF COORDINATOR”

    1. HSE ENFORCEMENT WEEKLY UPDATE 19th SEPTEMBER 2012 | PP Construction Safety News Desk Says:

      […] CLIENT AND CDM DESIGNER FINED OVER LACK OF COORDINATOR […]