Turner Access Higher Safety Total Access
Total Access Ethentic Chipmunk Data
Chipmunk Data Turner Access Ethentic

CLIENT AND CDM DESIGNER FINED OVER LACK OF COORDINATOR

CDM-C would have prevented asbestos breaches on independent school project

Construction client Sherborne School and Peter Eldridge, a director responsible for the refurbishment project have been ordered to pay almost £90,000 in fines and prosecution costs after unsafe removal of asbestos insulation boards (AIB) led to several people being exposed to asbestos.

AIB was removed in a way which exposed building contractors and a teenage work experience student to asbestos leaving them at risk of developing serious and potentially fatal diseases later in life.

HSE investigators found there was inadequate planning and failure to carry out a full asbestos survey from the initial design stages in May 2008 to start of the construction phase in July 2009. This despite a sample being taken from the building in 2008 which found asbestos in other parts of the school and a an asbestos register kept for the school buildings.

The court heard that Mr Eldridge and the school failed to appoint a Coordinator (CDM-C) for the refurbishment project despite it being a requirement of the CDM Regulations 2007 for a project of such size.

The CDM-C would have ensured a full refurbishment and demolition asbestos survey was completed in advance of construction work. Licensed asbestos contractors could then have been appointed to safely remove it.

Risk easily avoided if competent CDM-C engaged

Sherborne School was found guilty of breaching Regulation 4(8) of the Control of Asbestos Regulations 2006 and Regulation 14 of the Construction (Design and Management) Regulations 2007. The school was fined a total of £60,000 and ordered to pay £13,000 in costs.

Peter Eldridge, of Long Street, Sherborne, Dorset, was found guilty by virtue of Section 37 of the Health and Safety at Work etc Act for his neglect as a director for breaches of designer Regulations 11(3) and 18(1) of the Construction (Design and Management) Regulations 2007 for contributing to the failings of his company. He was fined a total of £10,000 with costs of £6,000.

  • CDM 2007 Regulation 14 covers the appointment of a CDM co-ordinator;
  • CDM 2007 Regulation 11(3) states: “every designer shall in preparing or modifying a design which may be used in construction work in Great Britain avoid foreseeable risks to the health and safety of any person”;
  • CDM 2007 Regulation 18(1) states: “where a project is notifiable, no designer shall commence work (other than initial design work) in relation to the project unless a CDM co-ordinator has been appointed for the project.”

Speaking after the prosecution, HSE Inspector Joanna Teasdale, said:

“Both Peter Eldridge and Sherborne School knew about the risks posed by the presence of asbestos in the school buildings, and yet they failed to manage the risk of exposure to asbestos fibres during the refurbishment project.

As a result several people, including at least one teenager, were put at unnecessary risk. In being exposed to asbestos fibres they could develop a serious and potentially fatal illness.

Although Sherborne School was the client, it still had a duty to manage the control of asbestos on its site, and to be aware of the requirements of removing asbestos safely.

This incident and the risk to those involved could have been easily avoided if competent people had been engaged during the planning of the refurbishment project to advise the school, such as a CDM coordinator.”

Latest Construction Health and Safety News

SOLAR PANEL BOSS SENTENCED WITH COMPANY

Director and company given hefty sentences over worker fall

Read the rest of this article »

Posted on 22nd November 2017

BUSINESS LEFT LEGIONELLA RISK UNCONTROLLED

Effective management arrangements missing for tunnel wash

Read the rest of this article »

Posted on 22nd November 2017

HSE ENFORCEMENT WEEKLY UPDATE 22nd NOV 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 22nd November 2017

PRICE RISES FOR IGNORING HSE NOTICES

Contractor given jail term after scaffolding prohibition issued

Read the rest of this article »

Posted on 22nd November 2017

UPDATED GUIDANCE ON EXCAVATORS USED AS CRANES

Plant Forum stresses excavators should not be ‘first choice’ for lifting

Read the rest of this article »

Posted on 22nd November 2017

LORRY SHEETING ARRANGEMENTS PROVED FATAL

Driver fell 4m to death during unsafe un-sheeting of lorry

Read the rest of this article »

Posted on 16th November 2017

HSE ENFORCEMENT WEEKLY UPDATE 15th NOV 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 16th November 2017

NEW CPA GUIDANCE ON FORWARD TIPPING DUMPERS

Industry aims to help prevent overturns and collision with workers

Read the rest of this article »

Posted on 13th November 2017

DEMOLITION WORKER LOST BALANCE IN FATAL FALL

Lack of measures in place to prevent fall from mezzanine floor

Read the rest of this article »

Posted on 13th November 2017

GROUNDWORKER SET ON FIRE BY CABLE STRIKE

RAMS requirement for underground service checks not followed

Read the rest of this article »

Posted on 13th November 2017

HSE ENFORCEMENT WEEKLY UPDATE 8th NOV 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 9th November 2017

RARE SUPPLIER PROSECUTION OVER FATAL CRUSHING

Vehicle manufacturer design and unsafe user practice caused death

Read the rest of this article »

Posted on 9th November 2017

ASBESTOS SURVEY FAILED TO COVER ALL WORK AREAS

Utilities firm fined after electricians exposed to drilled asbestos

Read the rest of this article »

Posted on 8th November 2017

METAL GRID FELL FROM FLT DURING PAINTING

Steel fabricator could have used sling to safely suspend grids

Read the rest of this article »

Posted on 7th November 2017

DRIVER ESCAPES WITH LIFE AFTER POWER STRIKE

Director given suspended sentence over lorry 132kV line contact

Read the rest of this article »

Posted on 7th November 2017

SCAFFOLDER FELL ON TEMPORARY ROOF WORKS

Injured workman lacked training and fall arrest equipment

Read the rest of this article »

Posted on 7th November 2017

FALLING CONTROL PANEL CRUSHED WORKMAN

Planning lacking on how to safely move heavy electrical equipment

Read the rest of this article »

Posted on 7th November 2017

POWER DOOR INSTALLER JAILED FOR THREE YEARS

Falling electrically powered gate claimed life of resident

Read the rest of this article »

Posted on 3rd November 2017

HSE ENFORCEMENT WEEKLY UPDATE 2nd NOV 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 2nd November 2017

STEEL FIRM REMOVED BAND SAW SAFETY GUARD

Leg of worker crushed in the vice of an industrial band saw

Read the rest of this article »

Posted on 2nd November 2017

WORKMAN FELL AFTER RAIL REMOVED FOR ACCESS

Small builder failed to allow for missing guard-rail

Read the rest of this article »

Posted on 2nd November 2017

FINES RISE RAPIDLY ALONGSIDE HARM TO HEALTH

hselogo1HSE confirm lowest number of construction fatalities on record

Read the rest of this article »

Posted on 2nd November 2017

HSE ENFORCEMENT WEEKLY UPDATE OCT 25th 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 25th October 2017

GIRDERS FELL DURING UNSAFE USE OF DEMO PLANT

Workman crushed and trapped by steel moved by company MD

Read the rest of this article »

Posted on 25th October 2017

FRAGILE ROOFLIGHT HAZARD LEFT UNCONTROLLED

Principal Contractor failed ensure covers or effective scaffolding installed

Read the rest of this article »

Posted on 25th October 2017
Turner Access Chipmunk Data
Total Access Ethentic
Higher Safety Turner Access

One Response to “CLIENT AND CDM DESIGNER FINED OVER LACK OF COORDINATOR”

  1. HSE ENFORCEMENT WEEKLY UPDATE 19th SEPTEMBER 2012 | PP Construction Safety News Desk Says:

    […] CLIENT AND CDM DESIGNER FINED OVER LACK OF COORDINATOR […]