Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    CLIENT AND CDM DESIGNER FINED OVER LACK OF COORDINATOR

    CDM-C would have prevented asbestos breaches on independent school project

    Construction client Sherborne School and Peter Eldridge, a director responsible for the refurbishment project have been ordered to pay almost £90,000 in fines and prosecution costs after unsafe removal of asbestos insulation boards (AIB) led to several people being exposed to asbestos.

    AIB was removed in a way which exposed building contractors and a teenage work experience student to asbestos leaving them at risk of developing serious and potentially fatal diseases later in life.

    HSE investigators found there was inadequate planning and failure to carry out a full asbestos survey from the initial design stages in May 2008 to start of the construction phase in July 2009. This despite a sample being taken from the building in 2008 which found asbestos in other parts of the school and a an asbestos register kept for the school buildings.

    The court heard that Mr Eldridge and the school failed to appoint a Coordinator (CDM-C) for the refurbishment project despite it being a requirement of the CDM Regulations 2007 for a project of such size.

    The CDM-C would have ensured a full refurbishment and demolition asbestos survey was completed in advance of construction work. Licensed asbestos contractors could then have been appointed to safely remove it.

    Risk easily avoided if competent CDM-C engaged

    Sherborne School was found guilty of breaching Regulation 4(8) of the Control of Asbestos Regulations 2006 and Regulation 14 of the Construction (Design and Management) Regulations 2007. The school was fined a total of £60,000 and ordered to pay £13,000 in costs.

    Peter Eldridge, of Long Street, Sherborne, Dorset, was found guilty by virtue of Section 37 of the Health and Safety at Work etc Act for his neglect as a director for breaches of designer Regulations 11(3) and 18(1) of the Construction (Design and Management) Regulations 2007 for contributing to the failings of his company. He was fined a total of £10,000 with costs of £6,000.

    • CDM 2007 Regulation 14 covers the appointment of a CDM co-ordinator;
    • CDM 2007 Regulation 11(3) states: “every designer shall in preparing or modifying a design which may be used in construction work in Great Britain avoid foreseeable risks to the health and safety of any person”;
    • CDM 2007 Regulation 18(1) states: “where a project is notifiable, no designer shall commence work (other than initial design work) in relation to the project unless a CDM co-ordinator has been appointed for the project.”

    Speaking after the prosecution, HSE Inspector Joanna Teasdale, said:

    “Both Peter Eldridge and Sherborne School knew about the risks posed by the presence of asbestos in the school buildings, and yet they failed to manage the risk of exposure to asbestos fibres during the refurbishment project.

    As a result several people, including at least one teenager, were put at unnecessary risk. In being exposed to asbestos fibres they could develop a serious and potentially fatal illness.

    Although Sherborne School was the client, it still had a duty to manage the control of asbestos on its site, and to be aware of the requirements of removing asbestos safely.

    This incident and the risk to those involved could have been easily avoided if competent people had been engaged during the planning of the refurbishment project to advise the school, such as a CDM coordinator.”

    Latest Construction Health and Safety News

    WORKMAN FELL FROM UNSECURED LADDER

    Industrial cladding company failed to assess and control WAH

    Read the rest of this article »

    Posted on 18th January 2019

    SCAFFOLDER FELL THROUGH FRAGILE ROOFLIGHT

    Fall through roof leaves workman with life-changing injuries

    Read the rest of this article »

    Posted on 18th January 2019

    ARM DRAGGED INTO CONVEYOR BELT DANGER

    Workman seriously injured on first day at work in quarry

    Read the rest of this article »

    Posted on 16th January 2019

    ROOF TRUSSES TOPPLED TRAPPING WORKMAN

    Principal contractor failed to plan, manage and monitor project

    Read the rest of this article »

    Posted on 16th January 2019

    SCAFFOLDING AWARENESS TRAINING FOR ALL

    CISRS set to target painters, bricklayers, electricians and plumbers

    Read the rest of this article »

    Posted on 16th January 2019

    HSE ENFORCEMENT DATABASE REMAINS OFFLINE

    hselogo1Access to HSE prosecutions and notices register mysteriously unavailable

    Read the rest of this article »

    Posted on 15th January 2019

    POOR LIFT MAINTENANCE CLAIMED LIFE OF CHILD

    Affordable housing business and contractor fined over £1.5m

    Read the rest of this article »

    Posted on 15th January 2019

    NEW CPA CRANE SAFETY GUIDANCE ISSUED

    Guide covers use of mobile lifting appliances beside railways

    Read the rest of this article »

    Posted on 14th January 2019

    RIBA CONDEMNS RISKIER PROCUREMENT OUTCOMES

    Holistic focus on safety is required and not just cost cutting

    Read the rest of this article »

    Posted on 8th January 2019

    DIRECTOR JAILED OVER PAINT STRIPPER ILLEGAL SALE

    Banned and restricted chemicals sold contrary to legal requirements

    Read the rest of this article »

    Posted on 5th January 2019

    CLIENT FAILED TO PROCURE ASBESTOS SURVEY

    Demolition work released large quantities of asbestos fibres

    Read the rest of this article »

    Posted on 2nd January 2019

    LIVE WORKING IGNITED CLOTHES OF ELECTRICIAN

    Spanner came into contact with live terminal causing life-changing burns

    Read the rest of this article »

    Posted on 31st December 2018

    WORKMEN FELL FROM ‘BIN’ ATTACHED TO EXCAVATOR

    Premature removal of scissor lift prompted unsafe system of work

    Read the rest of this article »

    Posted on 31st December 2018

    MANY SITES FAIL HSE HEALTH RISK CONTROL TEST

    HSE Construction site ‘blitz’ finds breaches at 43% of site visits

    Read the rest of this article »

    Posted on 31st December 2018

    MAKESHIFT FALL ARREST SYSTEM CAUGHT ON CAMERA

    Contactors fined for using harness not attached to suitable anchor

    Read the rest of this article »

    Posted on 31st December 2018

    HYDRAULIC RAM SEVERED HAND OF WORKMAN

    Major contractor failed to follow own policies and procedures

    Read the rest of this article »

    Posted on 31st December 2018

    ALL WORK AREAS NOT INCLUDED IN ASBESTOS SURVEY

    Company fined after asbestos containing materials were released

    Read the rest of this article »

    Posted on 31st December 2018

    FESTIVE GREETINGS TO ALL OUR READERS

    Read the rest of this article »

    Posted on 18th December 2018

    POSITIVE STORY ON FRAGILE SURFACE HAZARDS

    Major roofing contractor testifies to working from below roof

    Read the rest of this article »

    Posted on 18th December 2018

    LEISURE CENTRE USER FELL ILL AFTER SHOWER USE

    Legionella risk assessment and control measures found wanting

    Read the rest of this article »

    Posted on 18th December 2018

    STONE CUTTING MACHINE GUARDS FAILED HSE TEST

    Precautions taken following HSE enforcement fell into disuse

    Read the rest of this article »

    Posted on 18th December 2018

    ROOFWORK CREATED CARBON MONOXIDE RISK

    Falling rubble damaged and blocked home chimney flue

    Read the rest of this article »

    Posted on 18th December 2018

    HSE SAFETY ALERT: TOWER CRANE BRAKES

    Collapse of tower crane jib in high winds prompts HSE warning

    Read the rest of this article »

    Posted on 11th December 2018

    VISITING ENGINEER CRUSHED BY SCAFFOLD TUBES

    Principal contractor “signed off” contractor storage arrangements

    Read the rest of this article »

    Posted on 11th December 2018

    CONCRETE EJECTED BY PUMPING UNIT CLAIMED LIFE

    Company and director failed to train and supervise pumping operations

    Read the rest of this article »

    Posted on 5th December 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    One Response to “CLIENT AND CDM DESIGNER FINED OVER LACK OF COORDINATOR”

    1. HSE ENFORCEMENT WEEKLY UPDATE 19th SEPTEMBER 2012 | PP Construction Safety News Desk Says:

      […] CLIENT AND CDM DESIGNER FINED OVER LACK OF COORDINATOR […]