    PLANNING SUPERVISOR PROSECUTED BELATEDLY UNDER CDM94

    Architect appointed as PS prosecuted alongside contractor over 2006 cable strike

    DSM Demolition Ltd (DSM) and Gould Singleton Architects Ltd (GSA) have been fined after a demolition worker was engulfed in flames whilst cutting through an 11,000 volt cable at an electricity substation in Worcester in July 2006.

    Worcester Crown Court heard that DSM was demolishing a metal casting foundry when the workman cut through a live cable connected to a switching unit on a substation. He was engulfed by flames and suffered 20 per cent burns leaving him with permanent disabilities.

    HSE investigators found that appointed Planning Supervisor GSA and demolition contractor DSM failed to make adequate checks to ensure that the power supply had been disconnected.

    GSA told DSM that all services to the site had been terminated when the power supply remained live. DSM failed to ensure the electrical services had been disconnected before starting demolition.

    CDM co-ordinators must pass on ‘correct’ information

    DSM Demolition Ltd of Birmingham breached Section 2(1) of the Health and Safety at Work etc Act and was fined £40,000 and ordered to pay £100,000 costs. Gould Singleton Architects Ltd of Halesowen breached Section 3(1) of the Health and Safety at Work etc Act 1974 and Regulation 15(3)(e) of the Construction (Design and Management) Regulations 1994. The company was fined £20,000 and ordered to pay £20,872 costs.

    Speaking after the hearing, HSE inspector Tariq Khan said:

    “Neither of the two companies prosecuted today had made adequate checks to ensure that the power supply to the cable required to be cut by Mr Harris had been terminated. Had they done so then this incident would never have happened and Mr Harris would not have suffered such serious injuries.

    Construction, design and management co-ordinators must ensure that the information they pass on to contractors which could affect the safety of their workers is correct. Likewise, demolition contractors must follow safe systems of work at all times and ensure they check information provided to them about services on site with independent, competent sources.”

    Latest Construction Health and Safety News

    LACK OF SAFE PLATFORMS FOR WORK ON CRANE

    Major crane hire company erred on work at height precautions

    Read the rest of this article »

    Posted on 22nd May 2017

    SECOND CORPORATE MANSLAUGHTER CASE IN WEEK

    Double fatality represented pattern of serious neglect

    Read the rest of this article »

    Posted on 22nd May 2017

    DIRECTORS JAILED AND FIRM FINED FOR MANSLAUGHTER

    Client paid £100,000 less than economic cost for roof work

    Read the rest of this article »

    Posted on 22nd May 2017

    SOLAR PANEL FIRM AND DIRECTOR IN COURT

    Ineffective use of fall arrest no substitute for proper precautions

    Read the rest of this article »

    Posted on 22nd May 2017

    FIRM FAILED TO SECURE COMPETENT ASSISTANCE

    Court holds manager to account over inaction on risk management

    Read the rest of this article »

    Posted on 22nd May 2017

    HSE ENFORCEMENT WEEKLY UPDATE 10th MAY 2017

    hselogo1Prosecutions and enforcement notices weekly update and analysis

    Read the rest of this article »

    Posted on 12th May 2017

    GROUND WORKER TRAPPED BY EXCAVATION COLLAPSE

    Fellow workers dug earth so injured workman could breath

    Read the rest of this article »

    Posted on 11th May 2017

    MAJOR UK FIRMS FAILED ON VEHICLE MANAGEMENT

    Worker struck and injured when towed trolley and load overturned

    Read the rest of this article »

    Posted on 9th May 2017

    MAGISTRATES FINE FIRM £250,000 OVER ROOF FALL

    Solar panel firm failed to control risk and supervise works

    Read the rest of this article »

    Posted on 9th May 2017

    HSE REFURBISHMENT CAMPAIGN ENDS £750,000 FINE

    Contractor fined under CDM after failing to act on asbestos survey

    Read the rest of this article »

    Posted on 8th May 2017

    SITE MANAGER JAILED OVER DEATH OF PASSER-BY

    Failure to secure windows led to death and manslaughter sentence

    Read the rest of this article »

    Posted on 8th May 2017

    ROGUE GAS FITTER JAILED FOR 16 MONTHS

    Work unsafe and exposed home residents at risk of harm

    Read the rest of this article »

    Posted on 3rd May 2017

    LADDER ASSOCIATION ISSUES NEW SAFETY GUIDANCE

    Guidance comes amidst concerns surrounding unsafe telescopic ladders

    Read the rest of this article »

    Posted on 3rd May 2017

    FATALITY: FALL ON NEW HOMES PROJECT

    Workman died falling from a ladder on construction project

    Read the rest of this article »

    Posted on 3rd May 2017

    FIRM ADMITS GUILT AFTER DEATH OF FOUR WORKMEN

    Guilty plea entered by company on first day of Crown Court trial

    Read the rest of this article »

    Posted on 3rd May 2017

    FIRM FINED £2 MILLION OVER WORKPLACE DEATH

    Unsafe stacking of plastic bales claimed life of cleaner

    Read the rest of this article »

    Posted on 3rd May 2017

    HSE ENFORCEMENT WEEKLY UPDATE 1st MAY 2017

    hselogo1Prosecutions and enforcement notices weekly update and analysis

    Read the rest of this article »

    Posted on 3rd May 2017

    CONCRETE STAIRCASE CAUSED FATAL CRUSHING

    Lifting operations were unsafe and poorly supervised on project

    Read the rest of this article »

    Posted on 3rd May 2017

    CALL TO HALT FALL IN HSE FRONT LINE INSPECTORS

    Union reveals 25% cut and increasing delay in concluding investigations

    Read the rest of this article »

    Posted on 3rd May 2017

    HSE ENFORCEMENT WEEKLY UPDATE 26th APRIL 2017

    hselogo1Prosecutions and enforcement notices weekly update and analysis

    Read the rest of this article »

    Posted on 27th April 2017

    FATALITY: HOMES PROJECT IN SCOTLAND

    Circumstances of construction worker death remain unclear

    Read the rest of this article »

    Posted on 24th April 2017

    HSE OPEN FEE FOR INTERVENTION CONSULTATION

    hselogo1Regulator proposal for revised FFI disputes process

    Read the rest of this article »

    Posted on 24th April 2017

    LIFTING OPERATION WITH EXCAVATOR CAUSED DEATH

    Groundworker fatally injured when struck by concrete drainage cover

    Read the rest of this article »

    Posted on 24th April 2017

    WATER FIRM FINED £1.8M AFTER WORKER DROWNED

    Workman fell through opening into sand filtration tank

    Read the rest of this article »

    Posted on 24th April 2017

    PC AND CONTRACTOR PAY PRICE FOR UNSAFE WORKING

    Dangerous working practices continued during ‘snowy’ weather

    Read the rest of this article »

    Posted on 24th April 2017
    Turner Access Chipmunk Data
    Total Access Higher Safety
  • One Response to “PLANNING SUPERVISOR PROSECUTED BELATEDLY UNDER CDM94”

    1. HSE ENFORCEMENT WEEKLY UPDATE 9TH MAY 2012 | PP Construction Safety News Desk Says:

      […] PLANNING SUPERVISOR PROSECUTED BELATEDLY UNDER CDM94 […]