    IMPROVING SITE SAFETY WHILST CUTTING PROJECT COSTS

    Effective coordination early in project design secures safety of all at lower cost

    Construction Index has published a Case Study from Combisafe International demonstrating how the cost of edge protection was reduced on a major construction project.

    This was achieved by connecting the steel fabricator and edge protection supplier at an early stage in the project design thereby enabling selection of an edge protection system which satisfied the needs of all trades throughout the project.

    The article is reproduced verbatim below.

    Cut the cost of edge protection

    On most construction projects, the Client pays at least three times for edge protection. The frame package normally includes the requirement to provide the edge protection first.

    This is installed at minimum cost and inconvenience to the installing trade, as they gain no benefit from it. Invariably the edge protection then hinders the first protected trade and gets moved. There is often a delay period between slab completion and cladding arriving, and responsibility for the edge protected area changes. At this point the equipment being used is reviewed and frequently changed or adjusted. Finally the cladding activity arrives and the edge protection is in the way again, frustrating access to the building edge. This regularly results in another change or move. All this costs money, and it is primarily due to a lack of detailed planning, limited flexibility within the edge protection provided, and invariably poor communication between the trades.

    For Ormiston Academy, a six-storey specialist BSF Academy for media studies being built in steel within a regeneration area in Birmingham, Bovis Lend Lease decided to challenge this general situation. By connecting Elland Steel Structures, the steel fabricator, and Combisafe, Europe’s leading edge protection supplier, at an early stage in the project design, a significantly flexible edge protection system was selected, that satisfied the needs of all the protected trades at every stage of the project. This early decision also allowed the steel design to accommodate the fixing needs of the edge protection selected.

    The project demanded an edge protection system to meet the European Standard, EN 13374 Class A. It needed to be up to 2m high to contain windblown debris and materials, and required a mesh panel and toe board. It also needed to allow access to the building edge for installation of the cladding system fixing cleats, preferably whilst protecting the cladding installers.

    The site team decided to use a 2m high system based upon the Combisafe SMB (Steel Mesh Barrier). This satisfied both the compliance and the containment issues. The system could be pre-installed into sockets or bolt holes pre-positioned by Elland within the perimeter steel work, thus minimising work at height during installation. By additionally specifying the Combisafe SMB Beam Holders to be used in all locations, the whole edge protection system attracted substantial additional flexibility.

    These SMB Beam Holders allow a double guard rail beam to be positioned outside the line of the SMB and to be supported on the same posts. The SMB Beams are put in place over the existing system, whilst at all times the installer is protected from falling by the previously installed SMB. The beams can be used in isolated locations, on various levels, or along whole elevations. Once the SBM Beam is in place, the SMB panel can be removed from the inside, allowing protected free access to the edge of the building, and allowing the cladding contractor to reach through the SMB Beam to position and fix the cladding cleats.

    The project was a total success, with high productivity in both the frame erection and the cladding installation. The foresight shown by Bovis Lend Lease, in connecting Elland Steel Structures and Combisafe’s engineering service at so early a stage in the project, ensured that in this unique situation the Client only paid once.

    In this way the edge protection was initially installed to the perimeter steel work at ground level, and subsequently could be adjusted in position and worked through, in any location on the project. At all times the installers and other trades were collectively prevented from falling, and at no time needed to use a harness and lanyard.

    Latest Construction Health and Safety News

    CONSTRUCTION SAFETY NEWS – END OF NEW CONTENT

    The addition of content on this website ceased on 17th April 2020.

    Material posted before this date can be found by clicking on our SEARCH NEWS DATABASE function.

    Posted on 3rd May 2020

    CDM REGULATIONS 2015: GUIDES AND TEMPLATES

    Summary of our advice and tools to aid CDM 2015 compliance

    Read the rest of this article »

    Posted on 21st April 2020

    HSE WARN OF NEED FOR RPE FACE FIT TEST AND CHECK

    Incorrectly fitted RPE will not protect the wearer from dangers to health

    Read the rest of this article »

    Posted on 16th April 2020

    CORONA VIRUS: LATEST SITE OPERATING PROCEDURES

    Industry Bodies publish risk management guidance Version 3

    Read the rest of this article »

    Posted on 15th April 2020

    TOWER CRANE OUT OF SERVICE SAFETY ALERT

    Important advice from Construction Plant-hire Association and HSE

    Read the rest of this article »

    Posted on 30th March 2020

    HSE PLAN AND CONSTRUCTION PRIORITIES 2020/21

    Appointed CDM 2015 Principal Designers remain focus of HSE inspections

    Read the rest of this article »

    Posted on 30th March 2020

    COVID-19 ADVICE & GUIDANCE FOR CONSTRUCTION

    BuildUK support industry with advice, guidance and information

    Read the rest of this article »

    Posted on 30th March 2020

    HSE TARGETING WELDING FUME CANCER RISK

    Inspections to enforce improved controls required by new risk evidence

    Read the rest of this article »

    Posted on 24th February 2020

    HSE TO OVERSEE NEW BUILDING SAFETY REGIME

    Government to deliver biggest change in building safety for a generation

    Read the rest of this article »

    Posted on 21st January 2020

    SELECTED NEWS POSTED RECENTLY ON TWITTER

    PP Construction Safety logo and link to home page [1]Links to other construction health and safety related news reports

    Read the rest of this article »

    Posted on 18th November 2019

    HSE LOOK TO LOCAL AUTHORITIES FOR CDM SUPPORT

    Council Inspectors focus on CDM client duties – asbestos, fragility and RCS

    Read the rest of this article »

    Posted on 14th November 2019

    HSE WELDING FUME REVISED GUIDANCE PUBLISHED

    New research evidence on cancer link prompts revision on welding fume

    Read the rest of this article »

    Posted on 14th November 2019

    STRUCTURAL SAFETY BODY LATEST NEWSLETTER

    CROSS publishes reports and expert comment on a range of issues

    Read the rest of this article »

    Posted on 18th October 2019

    HSE RISK REDUCTION THROUGH DESIGN AWARD

    Regulator seeks to promote hazard avoidance and risk minimisation

    Read the rest of this article »

    Posted on 18th October 2019

    HSE START PROJECT HEALTH RISK INTERVENTIONS

    Regulator set to check health risks assessed and controls in place

    Read the rest of this article »

    Posted on 30th September 2019

    AIF NATIONAL WORKING AT HEIGHT CONFERENCE

    HSE Construction Head to speak at Access Industry Forum conference

    Read the rest of this article »

    Posted on 23rd September 2019

    NEW HSE HAVS CALCULATOR TO HELP CONTROL RISK

    New calculator includes “cautious estimates” for common tools

    Read the rest of this article »

    Posted on 23rd September 2019

    IMPROVING CDM DESIGNER HAZARD AWARENESS

    Research explores power of “multi-media digital tool” for design hazards

    Read the rest of this article »

    Posted on 27th August 2019

    DEMOLITION FEDERATION ON RECENT INCIDENTS

    NFDC ‘statement of awareness’ follows unplanned collapses

    Read the rest of this article »

    Posted on 27th August 2019

    RAISING COMPETENCE AND MAKING BUILDINGS SAFER

    Life-safety-critical disciplines urged to act on Interim Report

    Read the rest of this article »

    Posted on 27th August 2019

    BUILDING WORKS COMPROMISED GAS SAFETY

    Company and director fined after work created risk to residents

    Read the rest of this article »

    Posted on 27th August 2019

    HSE SPEAK AT ACCESS INDUSTRY CONFERENCE 2019

    AIF National Working at Height Conference November 2019

    Read the rest of this article »

    Posted on 6th August 2019

    STRUCTURAL SAFETY BODY LATEST NEWSLETTER

    CROSS publishes reports and expert comment on a range of issues

    Read the rest of this article »

    Posted on 23rd July 2019

    CONSIDERING TEMP WORKS IN PERMANENT DESIGN

    Useful overview for civil and structural engineers on contemporary practice

    Read the rest of this article »

    Posted on 23rd July 2019

    ‘VICTORIAN’ SAFETY AND FATIGUE BEHIND RAIL DEATH

    Investigation report links zero hours contracts to hazardous fatigue

    Read the rest of this article »

    Posted on 13th July 2019
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data