Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    EVALUATION OF CDM 2007 PILOT STUDY REPORT PUBLISHED

    Survey report data shows respondents views on CDM 2007 were ‘positive’  

    HSE has published a report describing the plan developed for the evaluation of the Construction (Design and Management) Regulations 2007 (CDM 2007), the findings from the pilot of the evaluation plan and options for a full evaluation of CDM 2007.

    The pilot evaluation showed:

    • Objectives: there are positive signs in terms of CDM 2007 meeting its objectives, with evidence of three being met and two being partially met;
    • Concerns: some respondents report concerns regarding the effectiveness of CDM 2007 in: Minimising bureaucracy; Bringing about integrated teams; Bringing about better communications and information flow between project team members; and Better competence checks by organisations who appoint other duty holders;
    • Costs: respondents were able to provide cost data. Some Clients, Designers and Principal Contractors reported no additional costs in complying with CDM 2007 on a project. The remaining Clients, Designers and Principal Contractors, and all of the Contractors did report additional costs in complying with CDM 2007 on a project; and
    • Overall: on balance, the respondents’ views on CDM were positive as the benefits were viewed as moderate, whilst the costs were viewed as moderate or lower.
    Conclusions

    The reports draws the following conclusions from the work undertaken:

    1. the full evaluation should assess the impact of all of the changes incorporated in CDM 2007;
    2. most of the respondents (87%) agreed that CDM 2007 was clearer than CDM 1994, and 96% agree that they clearly understand what their duties are under CDM 2007;
    3. respondents are using a range of contractual forms with CDM 2007 and most of the respondents (89%) agree that CDM 2007 can be used with the types of contract used in the construction industry;
    4. around half of the respondents (46%) disagree that CDM 2007 assists in minimising bureaucracy, whilst most of the respondents (85%) agree that CDM 2007 assists in managing health and safety;
    5. half of the respondents agree that CDM 2007 has helped bring about integrated teams (48%) and better communications and information flow between project team members (50%); however, a significant majority (ranging from 67% to 81% for the four relevant questions) of the respondents agree that CDM 2007 assists in facilitating coordination and cooperation;
    6. threequarters of the respondents (76%) agreed that CDM 2007 is helpful when assessing the competence of duty holders; most (83%) agreed that the client thoroughly assessed the competence of those organisations they appointed to work on the project; and most respondents (86%) agreed that the organisation who appointed them made a good job of assessing the competence of their organisation;
    7. there are positive signs in terms of CDM 2007 meeting its objectives, with evidence of three being met and two being partially met. However, some respondents have concerns about the effectiveness of CDM 2007 in: Minimising bureaucracy; Bringing about integrated teams; Bringing about better communications and information flow between project team members; and Better competence checks by organisations who appoint other duty holders;
    8. a third of the respondents (15) reported negligible costs in employing health and safety staff / advisors when they were introducing CDM 2007 into their organisations for the first time. However, nine respondents reported spending £10,000 or more; of these four were Principal Contractors;
    9. over half of the respondents (26) spent less than £5,000 on preparing health and safety management systems when they were introducing CDM 2007 into their organisations for the first time. However, five respondents reported spending £10,000 or more; of these three were Principal Contractors and two were Contractors;
    10. over half of the respondents (27) spent less than £5,000 health and safety training when they were introducing CDM 2007 into their organisations for the first time. However, eight respondents reported spending £10,000 or more; of these eight, there were two each of Coordinators, Designers, Principal Contractors and Contractors (see Section 11.4).
    11. a third of the respondents (14) reported negligible costs spent on employing health and safety staff / advisors whilst maintaining CDM 2007 in the last year. However, ten respondents reported spending £10,000 or more; of these four were Principal Contractors;
    12. over half of the respondents (27) spent less than £5,000 on their health and safety management systems whilst maintaining CDM 2007 in the last year. However, five respondents reported spending £10,000 or more; of these three were Principal Contractors and two were Contractors;
    13. over half of the respondents (25) spent less than £5,000 on health and safety training whilst maintaining CDM 2007 in the last year. However, five respondents reported spending £10,000 or more; of these two were Principal Contractors;
    14. over half of the respondents (25) rate the costs of CDM 2007 as low or lowmoderate, with another 12 rating the costs as moderate. Only seven respondents rated the costs as high or moderatehigh. Three of those respondents were contractors. Twentyone respondents viewed the benefits of CDM as 2007 as moderate. Ten respondents thought that the benefits were higher than moderate, whilst 14 thought that the benefits were less than moderate (see Section 11.7);
    15. on balance, the respondents’ views on CDM were positive as the benefits were viewed as moderate, whilst the costs were viewed as moderate or lower;
    16. half of the respondents felt that the question set was too long, and twothirds had difficulty in separating out the CDM 2007 costs from other costs. However, they found the guidance notes accompanying the question set to be helpful;
    17.  a set of seven activities has been developed for the evaluation of CDM 2007. These address the issues identified in this pilot and provide continuity from the baseline studies;

    Latest Construction Health and Safety News

    HSE TARGETS HEALTH ON LONDON PROJECTS

    Regulator starts inspection ‘blitz’ on construction sites

    Read the rest of this article »

    Posted on 23rd January 2019

    HSE ENFORCEMENT WEEKLY UPDATE 21st JAN 2019

    hselogo1HSE online register of prosecutions and enforcement notices

    Read the rest of this article »

    Posted on 22nd January 2019

    WORKMAN FELL FROM UNSECURED LADDER

    Industrial cladding company failed to assess and control WAH

    Read the rest of this article »

    Posted on 18th January 2019

    SCAFFOLDER FELL THROUGH FRAGILE ROOFLIGHT

    Fall through roof leaves workman with life-changing injuries

    Read the rest of this article »

    Posted on 18th January 2019

    ARM DRAGGED INTO CONVEYOR BELT DANGER

    Workman seriously injured on first day at work in quarry

    Read the rest of this article »

    Posted on 16th January 2019

    ROOF TRUSSES TOPPLED TRAPPING WORKMAN

    Principal contractor failed to plan, manage and monitor project

    Read the rest of this article »

    Posted on 16th January 2019

    SCAFFOLDING AWARENESS TRAINING FOR ALL

    CISRS set to target painters, bricklayers, electricians and plumbers

    Read the rest of this article »

    Posted on 16th January 2019

    POOR LIFT MAINTENANCE CLAIMED LIFE OF CHILD

    Affordable housing business and contractor fined over £1.5m

    Read the rest of this article »

    Posted on 15th January 2019

    NEW CPA CRANE SAFETY GUIDANCE ISSUED

    Guide covers use of mobile lifting appliances beside railways

    Read the rest of this article »

    Posted on 14th January 2019

    RIBA CONDEMNS RISKIER PROCUREMENT OUTCOMES

    Holistic focus on safety is required and not just cost cutting

    Read the rest of this article »

    Posted on 8th January 2019

    DIRECTOR JAILED OVER PAINT STRIPPER ILLEGAL SALE

    Banned and restricted chemicals sold contrary to legal requirements

    Read the rest of this article »

    Posted on 5th January 2019

    CLIENT FAILED TO PROCURE ASBESTOS SURVEY

    Demolition work released large quantities of asbestos fibres

    Read the rest of this article »

    Posted on 2nd January 2019

    LIVE WORKING IGNITED CLOTHES OF ELECTRICIAN

    Spanner came into contact with live terminal causing life-changing burns

    Read the rest of this article »

    Posted on 31st December 2018

    WORKMEN FELL FROM ‘BIN’ ATTACHED TO EXCAVATOR

    Premature removal of scissor lift prompted unsafe system of work

    Read the rest of this article »

    Posted on 31st December 2018

    MANY SITES FAIL HSE HEALTH RISK CONTROL TEST

    HSE Construction site ‘blitz’ finds breaches at 43% of site visits

    Read the rest of this article »

    Posted on 31st December 2018

    MAKESHIFT FALL ARREST SYSTEM CAUGHT ON CAMERA

    Contactors fined for using harness not attached to suitable anchor

    Read the rest of this article »

    Posted on 31st December 2018

    HYDRAULIC RAM SEVERED HAND OF WORKMAN

    Major contractor failed to follow own policies and procedures

    Read the rest of this article »

    Posted on 31st December 2018

    ALL WORK AREAS NOT INCLUDED IN ASBESTOS SURVEY

    Company fined after asbestos containing materials were released

    Read the rest of this article »

    Posted on 31st December 2018

    FESTIVE GREETINGS TO ALL OUR READERS

    Read the rest of this article »

    Posted on 18th December 2018

    POSITIVE STORY ON FRAGILE SURFACE HAZARDS

    Major roofing contractor testifies to working from below roof

    Read the rest of this article »

    Posted on 18th December 2018

    LEISURE CENTRE USER FELL ILL AFTER SHOWER USE

    Legionella risk assessment and control measures found wanting

    Read the rest of this article »

    Posted on 18th December 2018

    STONE CUTTING MACHINE GUARDS FAILED HSE TEST

    Precautions taken following HSE enforcement fell into disuse

    Read the rest of this article »

    Posted on 18th December 2018

    ROOFWORK CREATED CARBON MONOXIDE RISK

    Falling rubble damaged and blocked home chimney flue

    Read the rest of this article »

    Posted on 18th December 2018

    HSE SAFETY ALERT: TOWER CRANE BRAKES

    Collapse of tower crane jib in high winds prompts HSE warning

    Read the rest of this article »

    Posted on 11th December 2018

    VISITING ENGINEER CRUSHED BY SCAFFOLD TUBES

    Principal contractor “signed off” contractor storage arrangements

    Read the rest of this article »

    Posted on 11th December 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic