• Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    EVALUATION OF CDM 2007 PILOT STUDY REPORT PUBLISHED

    Survey report data shows respondents views on CDM 2007 were ‘positive’  

    HSE has published a report describing the plan developed for the evaluation of the Construction (Design and Management) Regulations 2007 (CDM 2007), the findings from the pilot of the evaluation plan and options for a full evaluation of CDM 2007.

    The pilot evaluation showed:

    • Objectives: there are positive signs in terms of CDM 2007 meeting its objectives, with evidence of three being met and two being partially met;
    • Concerns: some respondents report concerns regarding the effectiveness of CDM 2007 in: Minimising bureaucracy; Bringing about integrated teams; Bringing about better communications and information flow between project team members; and Better competence checks by organisations who appoint other duty holders;
    • Costs: respondents were able to provide cost data. Some Clients, Designers and Principal Contractors reported no additional costs in complying with CDM 2007 on a project. The remaining Clients, Designers and Principal Contractors, and all of the Contractors did report additional costs in complying with CDM 2007 on a project; and
    • Overall: on balance, the respondents’ views on CDM were positive as the benefits were viewed as moderate, whilst the costs were viewed as moderate or lower.
    Conclusions

    The reports draws the following conclusions from the work undertaken:

    1. the full evaluation should assess the impact of all of the changes incorporated in CDM 2007;
    2. most of the respondents (87%) agreed that CDM 2007 was clearer than CDM 1994, and 96% agree that they clearly understand what their duties are under CDM 2007;
    3. respondents are using a range of contractual forms with CDM 2007 and most of the respondents (89%) agree that CDM 2007 can be used with the types of contract used in the construction industry;
    4. around half of the respondents (46%) disagree that CDM 2007 assists in minimising bureaucracy, whilst most of the respondents (85%) agree that CDM 2007 assists in managing health and safety;
    5. half of the respondents agree that CDM 2007 has helped bring about integrated teams (48%) and better communications and information flow between project team members (50%); however, a significant majority (ranging from 67% to 81% for the four relevant questions) of the respondents agree that CDM 2007 assists in facilitating coordination and cooperation;
    6. threequarters of the respondents (76%) agreed that CDM 2007 is helpful when assessing the competence of duty holders; most (83%) agreed that the client thoroughly assessed the competence of those organisations they appointed to work on the project; and most respondents (86%) agreed that the organisation who appointed them made a good job of assessing the competence of their organisation;
    7. there are positive signs in terms of CDM 2007 meeting its objectives, with evidence of three being met and two being partially met. However, some respondents have concerns about the effectiveness of CDM 2007 in: Minimising bureaucracy; Bringing about integrated teams; Bringing about better communications and information flow between project team members; and Better competence checks by organisations who appoint other duty holders;
    8. a third of the respondents (15) reported negligible costs in employing health and safety staff / advisors when they were introducing CDM 2007 into their organisations for the first time. However, nine respondents reported spending £10,000 or more; of these four were Principal Contractors;
    9. over half of the respondents (26) spent less than £5,000 on preparing health and safety management systems when they were introducing CDM 2007 into their organisations for the first time. However, five respondents reported spending £10,000 or more; of these three were Principal Contractors and two were Contractors;
    10. over half of the respondents (27) spent less than £5,000 health and safety training when they were introducing CDM 2007 into their organisations for the first time. However, eight respondents reported spending £10,000 or more; of these eight, there were two each of Coordinators, Designers, Principal Contractors and Contractors (see Section 11.4).
    11. a third of the respondents (14) reported negligible costs spent on employing health and safety staff / advisors whilst maintaining CDM 2007 in the last year. However, ten respondents reported spending £10,000 or more; of these four were Principal Contractors;
    12. over half of the respondents (27) spent less than £5,000 on their health and safety management systems whilst maintaining CDM 2007 in the last year. However, five respondents reported spending £10,000 or more; of these three were Principal Contractors and two were Contractors;
    13. over half of the respondents (25) spent less than £5,000 on health and safety training whilst maintaining CDM 2007 in the last year. However, five respondents reported spending £10,000 or more; of these two were Principal Contractors;
    14. over half of the respondents (25) rate the costs of CDM 2007 as low or lowmoderate, with another 12 rating the costs as moderate. Only seven respondents rated the costs as high or moderatehigh. Three of those respondents were contractors. Twentyone respondents viewed the benefits of CDM as 2007 as moderate. Ten respondents thought that the benefits were higher than moderate, whilst 14 thought that the benefits were less than moderate (see Section 11.7);
    15. on balance, the respondents’ views on CDM were positive as the benefits were viewed as moderate, whilst the costs were viewed as moderate or lower;
    16. half of the respondents felt that the question set was too long, and twothirds had difficulty in separating out the CDM 2007 costs from other costs. However, they found the guidance notes accompanying the question set to be helpful;
    17.  a set of seven activities has been developed for the evaluation of CDM 2007. These address the issues identified in this pilot and provide continuity from the baseline studies;

    Latest Construction Health and Safety News

    CONSTRUCTION SAFETY NEWS – END OF NEW CONTENT

    The addition of content on this website ceased on 17th April 2020.

    Material posted before this date can be found by clicking on our SEARCH NEWS DATABASE function.

    Posted on 3rd May 2020

    HSE WARN OF NEED FOR RPE FACE FIT TEST AND CHECK

    Incorrectly fitted RPE will not protect the wearer from dangers to health

    Read the rest of this article »

    Posted on 16th April 2020

    CORONA VIRUS: LATEST SITE OPERATING PROCEDURES

    Industry Bodies publish risk management guidance Version 3

    Read the rest of this article »

    Posted on 15th April 2020

    TOWER CRANE OUT OF SERVICE SAFETY ALERT

    Important advice from Construction Plant-hire Association and HSE

    Read the rest of this article »

    Posted on 30th March 2020

    FRAGILE ROOF REPLACEMENT PUT WORKERS IN DANGER

    Measures to prevent falling from or through the roof were missing

    Read the rest of this article »

    Posted on 30th March 2020

    WORKMAN FELL FROM EDGE OF MEZZANINE FLOOR

    Edge protection was absent and workman untrained for the task

    Read the rest of this article »

    Posted on 30th March 2020

    HSE PLAN AND CONSTRUCTION PRIORITIES 2020/21

    Appointed CDM 2015 Principal Designers remain focus of HSE inspections

    Read the rest of this article »

    Posted on 30th March 2020

    COVID-19 ADVICE & GUIDANCE FOR CONSTRUCTION

    BuildUK support industry with advice, guidance and information

    Read the rest of this article »

    Posted on 30th March 2020

    LATEST HSE CONVICTIONS AND NOTICES REGISTERS

    hselogo1View current online HSE registers of prosecution convictions and notices

    Read the rest of this article »

    Posted on 30th March 2020

    POORLY DESIGNED SCHOOL GATE CRUSHED CHILD

    Sliding gate over-run mechanism proved insufficiently robust

    Read the rest of this article »

    Posted on 9th March 2020

    POWER GENERATOR PROSECUTED OVER UNSAFE SYSTEM

    Maintenance workers seriously injured when energy suddenly released

    Read the rest of this article »

    Posted on 2nd March 2020

    CEILING BELOW SAVES WORKMAN IN ROOFLIGHT FALL

    Roofworker fell through roof after stepping on fragile rooflight

    Read the rest of this article »

    Posted on 2nd March 2020

    INEXPERIENCED WORKER FELL THROUGH OPENING

    No physical protection or warning of opening and fragile covering

    Read the rest of this article »

    Posted on 29th February 2020

    CDM PRINCIPAL DESIGNER IN COURT OVER FIRE RISK

    Designers and contractor prosecuted for risk management failings

    Read the rest of this article »

    Posted on 29th February 2020

    PRISON SENTENCE FOR RECALCITRANT DIRECTOR

    Prohibition and improvement notices ignored and danger persisted

    Read the rest of this article »

    Posted on 26th February 2020

    TEMPORARY WORKS HOARDING FELL ON PEDESTRIAN

    Member of the public struck when site fence collapsed suddenly

    Read the rest of this article »

    Posted on 26th February 2020

    CHILD FATALLY INJURED BY UNSECURED POLE

    Pole stored on embankment moved and trapped boy against fencing

    Read the rest of this article »

    Posted on 26th February 2020

    OWNER RESPONSE TO HSE INSPECTION ENDED IN COURT

    Police uphold HSE right to inspect without threats, aggression or abuse

    Read the rest of this article »

    Posted on 24th February 2020

    HSE TARGETING WELDING FUME CANCER RISK

    Inspections to enforce improved controls required by new risk evidence

    Read the rest of this article »

    Posted on 24th February 2020

    CONTRACTOR FAILED TO REPLACE MISSING PROTECTION

    Painter and decorator fractured hip in fall from landing

    Read the rest of this article »

    Posted on 18th February 2020

    RISK OF DERMATITIS SUFFICIENT FOR PROSECUTION

    Company failed to implement controls and surveillance required by COSHH

    Read the rest of this article »

    Posted on 18th February 2020

    COSHH FAILINGS CAUSE ASTHMA AND PROVE COSTLY

    Uncontrolled exposure to isocyanates during paint spraying operations

    Read the rest of this article »

    Posted on 18th February 2020

    POLICE EMPLOYEE SHOCKED BY DATA CABLE WORK

    South Wales Force fined over electric shock from ceiling void cable

    Read the rest of this article »

    Posted on 18th February 2020

    COLLAPSE OF PUMP SET TRAPPED WORKMAN

    Unsafe system of work transferring from pallet to a raised platform

    Read the rest of this article »

    Posted on 18th February 2020

    MODIFIED PODIUM STEPS CAUSE FALL FROM HEIGHT

    Firm failed to select and correctly assemble with necessary training

    Read the rest of this article »

    Posted on 14th February 2020
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data