Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    EVALUATION OF CDM 2007 PILOT STUDY REPORT PUBLISHED

    Survey report data shows respondents views on CDM 2007 were ‘positive’  

    HSE has published a report describing the plan developed for the evaluation of the Construction (Design and Management) Regulations 2007 (CDM 2007), the findings from the pilot of the evaluation plan and options for a full evaluation of CDM 2007.

    The pilot evaluation showed:

    • Objectives: there are positive signs in terms of CDM 2007 meeting its objectives, with evidence of three being met and two being partially met;
    • Concerns: some respondents report concerns regarding the effectiveness of CDM 2007 in: Minimising bureaucracy; Bringing about integrated teams; Bringing about better communications and information flow between project team members; and Better competence checks by organisations who appoint other duty holders;
    • Costs: respondents were able to provide cost data. Some Clients, Designers and Principal Contractors reported no additional costs in complying with CDM 2007 on a project. The remaining Clients, Designers and Principal Contractors, and all of the Contractors did report additional costs in complying with CDM 2007 on a project; and
    • Overall: on balance, the respondents’ views on CDM were positive as the benefits were viewed as moderate, whilst the costs were viewed as moderate or lower.
    Conclusions

    The reports draws the following conclusions from the work undertaken:

    1. the full evaluation should assess the impact of all of the changes incorporated in CDM 2007;
    2. most of the respondents (87%) agreed that CDM 2007 was clearer than CDM 1994, and 96% agree that they clearly understand what their duties are under CDM 2007;
    3. respondents are using a range of contractual forms with CDM 2007 and most of the respondents (89%) agree that CDM 2007 can be used with the types of contract used in the construction industry;
    4. around half of the respondents (46%) disagree that CDM 2007 assists in minimising bureaucracy, whilst most of the respondents (85%) agree that CDM 2007 assists in managing health and safety;
    5. half of the respondents agree that CDM 2007 has helped bring about integrated teams (48%) and better communications and information flow between project team members (50%); however, a significant majority (ranging from 67% to 81% for the four relevant questions) of the respondents agree that CDM 2007 assists in facilitating coordination and cooperation;
    6. threequarters of the respondents (76%) agreed that CDM 2007 is helpful when assessing the competence of duty holders; most (83%) agreed that the client thoroughly assessed the competence of those organisations they appointed to work on the project; and most respondents (86%) agreed that the organisation who appointed them made a good job of assessing the competence of their organisation;
    7. there are positive signs in terms of CDM 2007 meeting its objectives, with evidence of three being met and two being partially met. However, some respondents have concerns about the effectiveness of CDM 2007 in: Minimising bureaucracy; Bringing about integrated teams; Bringing about better communications and information flow between project team members; and Better competence checks by organisations who appoint other duty holders;
    8. a third of the respondents (15) reported negligible costs in employing health and safety staff / advisors when they were introducing CDM 2007 into their organisations for the first time. However, nine respondents reported spending £10,000 or more; of these four were Principal Contractors;
    9. over half of the respondents (26) spent less than £5,000 on preparing health and safety management systems when they were introducing CDM 2007 into their organisations for the first time. However, five respondents reported spending £10,000 or more; of these three were Principal Contractors and two were Contractors;
    10. over half of the respondents (27) spent less than £5,000 health and safety training when they were introducing CDM 2007 into their organisations for the first time. However, eight respondents reported spending £10,000 or more; of these eight, there were two each of Coordinators, Designers, Principal Contractors and Contractors (see Section 11.4).
    11. a third of the respondents (14) reported negligible costs spent on employing health and safety staff / advisors whilst maintaining CDM 2007 in the last year. However, ten respondents reported spending £10,000 or more; of these four were Principal Contractors;
    12. over half of the respondents (27) spent less than £5,000 on their health and safety management systems whilst maintaining CDM 2007 in the last year. However, five respondents reported spending £10,000 or more; of these three were Principal Contractors and two were Contractors;
    13. over half of the respondents (25) spent less than £5,000 on health and safety training whilst maintaining CDM 2007 in the last year. However, five respondents reported spending £10,000 or more; of these two were Principal Contractors;
    14. over half of the respondents (25) rate the costs of CDM 2007 as low or lowmoderate, with another 12 rating the costs as moderate. Only seven respondents rated the costs as high or moderatehigh. Three of those respondents were contractors. Twentyone respondents viewed the benefits of CDM as 2007 as moderate. Ten respondents thought that the benefits were higher than moderate, whilst 14 thought that the benefits were less than moderate (see Section 11.7);
    15. on balance, the respondents’ views on CDM were positive as the benefits were viewed as moderate, whilst the costs were viewed as moderate or lower;
    16. half of the respondents felt that the question set was too long, and twothirds had difficulty in separating out the CDM 2007 costs from other costs. However, they found the guidance notes accompanying the question set to be helpful;
    17.  a set of seven activities has been developed for the evaluation of CDM 2007. These address the issues identified in this pilot and provide continuity from the baseline studies;

    Latest Construction Health and Safety News

    MAJOR FM FIRM FAILED TO MAINTAIN BACK-UP POWER

    Power loss at laboratory site created potential risk from biological agents

    Read the rest of this article »

    Posted on 18th November 2018

    IGNORING HSE PROHIBITIONS COST FIRM £250,000

    CDM 2015 and work at height requirements repeatedly breached

    Read the rest of this article »

    Posted on 16th November 2018

    ROOF COLLAPSED UNDER EXCESS LOADING

    Director and company fined over roof design failures

    Read the rest of this article »

    Posted on 11th November 2018

    FORK LIFT OVERTURNED IN SCAFFOLDING YARD

    Untrained operator suffered life changing crush injuries

    Read the rest of this article »

    Posted on 10th November 2018

    STRUCTURAL SAFETY ALERT: EFFECTS OF SCALE

    SCOSS issues alert after concerns disclosed over ‘large structures’

    Read the rest of this article »

    Posted on 7th November 2018

    ASBESTOS EXPOSED BY UNTRAINED WORKERS

    Contractor failed to act properly despite HSE intervention

    Read the rest of this article »

    Posted on 7th November 2018

    GAS MAIN STRIKE REPAIR CAUSED SEVERE BURNS

    Contractor excavator damage to gas pipe ends in £1.2m fine

    Read the rest of this article »

    Posted on 7th November 2018

    REBAR FELL FROM FLT IN UNSAFE LIFTING OPERATION

    Multiple fractures caused by inappropriate use of fork lift

    Read the rest of this article »

    Posted on 7th November 2018

    HSE ENFORCEMENT WEEKLY UPDATE 7th NOV 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 7th November 2018

    POORLY PLANNED LIFT DISMANTLE INJURED WORKMAN

    Counterweight or suspension rope struck worker in lift shaft

    Read the rest of this article »

    Posted on 1st November 2018

    CONSTRUCTION INJURY AND ILL-HEALTH 2017/18

    hselogo1Fatal injury rate in long term decline whilst ill-health trend flat lining

    Read the rest of this article »

    Posted on 1st November 2018

    DUMPER DRIVEN INTO OPEN UNGUARDED EXCAVATION

    Contractor fined over absence of suitable excavation / dumper precautions

    Read the rest of this article »

    Posted on 1st November 2018

    DEATH FAILED TO TRIGGER PREVENTIVE ACTION

    Prison term for director whilst his company ordered to pay £3/4m

    Read the rest of this article »

    Posted on 29th October 2018

    FAILURE TO MAINTAIN GUARDS PROVES COSTLY

    Woodworking machinery defective despite previous HSE advice

    Read the rest of this article »

    Posted on 26th October 2018

    CISRS LAUNCH SYSTEM SCAFFOLD INSPECTION COURSES

    Training courses prompted by growing use of system scaffolding

    Read the rest of this article »

    Posted on 25th October 2018

    HSE INSPECTS CLADDING REMOVAL AND REPLACEMENT

    hselogo1Advice to Inspectors published on fire risk during work on tall buildings

    Read the rest of this article »

    Posted on 25th October 2018

    HIGHWAYS, RAIL AND WATER HEALTH & SAFETY HUBS

    Websites provide useful information, alerts and tools

    Read the rest of this article »

    Posted on 24th October 2018

    ELIMINATING CONCRETE DRILLING VIBRATION HAZARD

    Cutting specialist innovation avoids vibration exposure management

    Read the rest of this article »

    Posted on 24th October 2018

    NEW MEWP WORK AT HEIGHT RESCUE GUIDANCE

    Industry body publishes simple guidance on MEWP stranding actions

    Read the rest of this article »

    Posted on 24th October 2018

    HSE PUBLISH RIDDOR DATA VISUALISATION TOOL

    hselogo1Construction injury records made more relevant and easily used

    Read the rest of this article »

    Posted on 24th October 2018

    COUNCIL OVERLOOKED ICE RINK SLIPPING RISK

    Obvious risk of employees falling on ice rink was left uncontrolled

    Read the rest of this article »

    Posted on 22nd October 2018

    STRUCTURAL SAFETY BODY LATEST NEWSLETTER

    CROSS publishes reports and expert comment on a range of issues

    Read the rest of this article »

    Posted on 22nd October 2018

    YOUNG WORKER FELL FROM PETROL STATION CANOPY

    Steel fabricator after young construction worker falls on first day at work

    Read the rest of this article »

    Posted on 18th October 2018

    FIRM FINED OVER FAILURE AT ASSESS VIBRATION RISK

    Vibration regulations not acted upon until seven years in operation

    Read the rest of this article »

    Posted on 18th October 2018

    FAILURE TO ISOLATE LEAVES WORKMAN PARALYSED

    Conveyor guards removed before power source isolated

    Read the rest of this article »

    Posted on 16th October 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic