Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    EVALUATION OF CDM 2007 PILOT STUDY REPORT PUBLISHED

    Survey report data shows respondents views on CDM 2007 were ‘positive’  

    HSE has published a report describing the plan developed for the evaluation of the Construction (Design and Management) Regulations 2007 (CDM 2007), the findings from the pilot of the evaluation plan and options for a full evaluation of CDM 2007.

    The pilot evaluation showed:

    • Objectives: there are positive signs in terms of CDM 2007 meeting its objectives, with evidence of three being met and two being partially met;
    • Concerns: some respondents report concerns regarding the effectiveness of CDM 2007 in: Minimising bureaucracy; Bringing about integrated teams; Bringing about better communications and information flow between project team members; and Better competence checks by organisations who appoint other duty holders;
    • Costs: respondents were able to provide cost data. Some Clients, Designers and Principal Contractors reported no additional costs in complying with CDM 2007 on a project. The remaining Clients, Designers and Principal Contractors, and all of the Contractors did report additional costs in complying with CDM 2007 on a project; and
    • Overall: on balance, the respondents’ views on CDM were positive as the benefits were viewed as moderate, whilst the costs were viewed as moderate or lower.
    Conclusions

    The reports draws the following conclusions from the work undertaken:

    1. the full evaluation should assess the impact of all of the changes incorporated in CDM 2007;
    2. most of the respondents (87%) agreed that CDM 2007 was clearer than CDM 1994, and 96% agree that they clearly understand what their duties are under CDM 2007;
    3. respondents are using a range of contractual forms with CDM 2007 and most of the respondents (89%) agree that CDM 2007 can be used with the types of contract used in the construction industry;
    4. around half of the respondents (46%) disagree that CDM 2007 assists in minimising bureaucracy, whilst most of the respondents (85%) agree that CDM 2007 assists in managing health and safety;
    5. half of the respondents agree that CDM 2007 has helped bring about integrated teams (48%) and better communications and information flow between project team members (50%); however, a significant majority (ranging from 67% to 81% for the four relevant questions) of the respondents agree that CDM 2007 assists in facilitating coordination and cooperation;
    6. threequarters of the respondents (76%) agreed that CDM 2007 is helpful when assessing the competence of duty holders; most (83%) agreed that the client thoroughly assessed the competence of those organisations they appointed to work on the project; and most respondents (86%) agreed that the organisation who appointed them made a good job of assessing the competence of their organisation;
    7. there are positive signs in terms of CDM 2007 meeting its objectives, with evidence of three being met and two being partially met. However, some respondents have concerns about the effectiveness of CDM 2007 in: Minimising bureaucracy; Bringing about integrated teams; Bringing about better communications and information flow between project team members; and Better competence checks by organisations who appoint other duty holders;
    8. a third of the respondents (15) reported negligible costs in employing health and safety staff / advisors when they were introducing CDM 2007 into their organisations for the first time. However, nine respondents reported spending £10,000 or more; of these four were Principal Contractors;
    9. over half of the respondents (26) spent less than £5,000 on preparing health and safety management systems when they were introducing CDM 2007 into their organisations for the first time. However, five respondents reported spending £10,000 or more; of these three were Principal Contractors and two were Contractors;
    10. over half of the respondents (27) spent less than £5,000 health and safety training when they were introducing CDM 2007 into their organisations for the first time. However, eight respondents reported spending £10,000 or more; of these eight, there were two each of Coordinators, Designers, Principal Contractors and Contractors (see Section 11.4).
    11. a third of the respondents (14) reported negligible costs spent on employing health and safety staff / advisors whilst maintaining CDM 2007 in the last year. However, ten respondents reported spending £10,000 or more; of these four were Principal Contractors;
    12. over half of the respondents (27) spent less than £5,000 on their health and safety management systems whilst maintaining CDM 2007 in the last year. However, five respondents reported spending £10,000 or more; of these three were Principal Contractors and two were Contractors;
    13. over half of the respondents (25) spent less than £5,000 on health and safety training whilst maintaining CDM 2007 in the last year. However, five respondents reported spending £10,000 or more; of these two were Principal Contractors;
    14. over half of the respondents (25) rate the costs of CDM 2007 as low or lowmoderate, with another 12 rating the costs as moderate. Only seven respondents rated the costs as high or moderatehigh. Three of those respondents were contractors. Twentyone respondents viewed the benefits of CDM as 2007 as moderate. Ten respondents thought that the benefits were higher than moderate, whilst 14 thought that the benefits were less than moderate (see Section 11.7);
    15. on balance, the respondents’ views on CDM were positive as the benefits were viewed as moderate, whilst the costs were viewed as moderate or lower;
    16. half of the respondents felt that the question set was too long, and twothirds had difficulty in separating out the CDM 2007 costs from other costs. However, they found the guidance notes accompanying the question set to be helpful;
    17.  a set of seven activities has been developed for the evaluation of CDM 2007. These address the issues identified in this pilot and provide continuity from the baseline studies;

    Latest Construction Health and Safety News

    HSE ENFORCEMENT DATABASE UPDATE 20th MAR 2019

    hselogo1Latest online register of prosecutions and enforcement notices

    Read the rest of this article »

    Posted on 20th March 2019

    BRICKLAYER FATALLY INJURED BY FALLING WALL

    Masonry collapsed during concrete back filling operation

    Read the rest of this article »

    Posted on 18th March 2019

    BASIC LADDER SAFETY FAILURES FINED £150,000

    Repair and maintenance firm had no excuse for errors causing injury

    Read the rest of this article »

    Posted on 18th March 2019

    HSE ISSUES REMINDER ON SAFE SCAFFOLD DESIGN

    Recent incidents and high winds prompt warning from regulator

    Read the rest of this article »

    Posted on 12th March 2019

    LORRY DRIVER DIED IN OVERHEAD POWER STRIKE

    Major company failed to communicate precautions to grab arm operator

    Read the rest of this article »

    Posted on 12th March 2019

    ASSESSMENT SHOWED RISK – PRECAUTIONS NOT TAKEN

    Workman seriously injured when falling into open unguarded stairwell

    Read the rest of this article »

    Posted on 1st March 2019

    MAJOR FIRM FAILED TO IMPLEMENT SAFE SYSTEM

    Procedures for safe plant refuelling failed to prevent death of workman

    Read the rest of this article »

    Posted on 26th February 2019

    CLIENT PROSECUTED OVER CONTRACTOR FATAL FALL

    Company breached duty to protect contractors as well as employees

    Read the rest of this article »

    Posted on 26th February 2019

    FOURTEEN YEAR FAILURE TO MANAGE ASBESTOS

    Firm failed to implement asbestos management plan following survey

    Read the rest of this article »

    Posted on 25th February 2019

    CHILD INJURED BY WALL COLLAPSE INCIDENT

    Council failed to carry out “intelligence led” condition inspections

    Read the rest of this article »

    Posted on 18th February 2019

    BOTTLE JACK SUPPORT FAILED TO PREVENT DEATH

    Director sentenced alongside company over death of engineer

    Read the rest of this article »

    Posted on 18th February 2019

    TEMPORARY WORKS FAILURES CAUSED FATAL FALL

    Platform not designed and system for installation and inspection inadequate

    Read the rest of this article »

    Posted on 18th February 2019

    SOLVENT IGNITED DURING FLOOR CLEANING WORKS

    Flammable solvent fire fought with water spreading fire further

    Read the rest of this article »

    Posted on 13th February 2019

    INEVITABLE COLLAPSE OF SCAFFOLD ON TO SCHOOL

    Scaffold not designed or installed to withstand foreseeable loads

    Read the rest of this article »

    Posted on 13th February 2019

    OIL DRUM EXPLODED DURING HOT CUTTING WORK

    Firm fined £400k after drum lid ejected causing loss of leg

    Read the rest of this article »

    Posted on 12th February 2019

    ROOFLIGHT FALL ON NUCLEAR POWER SITE

    Energy generating company and maintenance contractor fined

    Read the rest of this article »

    Posted on 12th February 2019

    DIRECTOR PROSECUTED AFTER 6METRE ROOF FALL

    Untrained worker fell through rooflight in fragile asbestos roof

    Read the rest of this article »

    Posted on 12th February 2019

    HSE ALERT: MILD STEEL WELDING CANCER RISK

    HSE announces enforcement action change based on new cancer evidence

    Read the rest of this article »

    Posted on 11th February 2019

    LORRY MOUNTED LIFTING OPERATION PROVED FATAL

    Steel staircase toppled from vehicle after sling snagged

    Read the rest of this article »

    Posted on 7th February 2019

    DIRECTOR AND BUSINESS IN COURT OVER DEATH

    Scaffold not priced for on domestic roof-line refurbishment work

    Read the rest of this article »

    Posted on 6th February 2019

    FRAGILE ROOFLIGHT HAZARD PROTECTION MISSING

    Two businesses prosecuted after a worker fell through a fragile rooflight

    Read the rest of this article »

    Posted on 5th February 2019

    STRUCTURAL SAFETY BODY LATEST NEWSLETTER

    CROSS publishes reports and expert comment on a range of issues

    Read the rest of this article »

    Posted on 4th February 2019

    FINGERS CRUSHED BY METAL FOLDING MACHINE

    Steel cladding firm fined £600k over failure guard access to danger

    Read the rest of this article »

    Posted on 4th February 2019

    ASBESTOS ILLEGALLY REMOVED AFTER SURVEY

    Surveyor pricing asbestos work found contractor jumped the gun

    Read the rest of this article »

    Posted on 4th February 2019

    SITE DUMPER PRECAUTIONS FAILED TO PREVENT DEATH

    Contractor fined £600k for poor management of vehicle/people interface

    Read the rest of this article »

    Posted on 4th February 2019
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic