• Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    OLYMPIC STADIUM CONSTRUCTORS PRAISED FOR PERFORMANCE

    Stadium on time, under budget and with an exemplary safety record 

    The last piece of turf has been laid today on the Olympic Stadium’s field of play, marking the completion of construction on the flagship venue. 

    Construction started on the Olympic Stadium three years ago and has been completed “on time, under budget and with an exemplary safety record“. Over 240 UK businesses won contracts for construction of the Stadium and over 5250 people worked on the project. 

    ODA chairman John Armitt praised the design and construction team led by Sir Robert McAlpine saying:

    “The Olympic Stadium has been finished on time and under budget. To complete a complicated project such as this in less than three years is testament to the skill and professionalism of the UK construction industry. I would like to thank the Team Stadium consortium and all of the workers for their hard work and commitment.”

    Secretary of State for Culture, Olympics, Media and Sport Jeremy Hunt said:

    “The Olympic Stadium is the stunning centrepiece of the Olympic Park. Hundreds of businesses from across the UK have been involved in its creation. This is another landmark day for the London 2012 project and shows that Britain is at the forefront of the construction world.”

    Construction facts and figures
    • Construction started in May 2008 and has been completed in just under three years.
    • Design and construction team led by Sir Robert McAlpine
    • Over 5250 people have worked on the project over the past three years with the operatives workforce peaking at 650
    • Over 240 businesses, from Devon to Scotland, have worked on the construction of the Stadium.
    • More than 5,000 reinforced concrete columns were installed into the ground, up to 20m deep, to provide the foundations to support the Stadium structure
    • 112 steel rakers and 12,000 pre-cast concrete terracing units hold the spectator seating in place
    • Roof compression truss is made up of 28 steel sections, each one is 15m high by 30m long and weigh 85 tonne. A 1,350-tonne super lift crane was assembled in the field of play to lift them into place between January and July in 2009.
    • Cable net roof provides the correct conditions for athletes on the field of play and covering two-thirds of spectators. The roof is covered by 112 panels of white material, totalling 25,000 m². The fabric was fitted by a team of 23 expert abseilers.
    • Stadium is lit by 532 individual floodlights housed in 14 towers. The top of the towers reach 70m above the field of play.
    • 14 lighting tower weigh 34 tonnes each and are 28m high. They were lifted into place by a 650 tonne crane over a period of 14 days in March 2010.
    • 700 rooms and spaces within the Stadium, including changing rooms and toilets. The fit-out work has required15,000sqm of plasterboard, 140,000 blocks to create walls, 11km of pipes for drainage, 338km of power cables plus 33km of other data systems cabling and 12km of ventilation ducts.
    • Turf for the field of play was grown in Scunthorpe and was laid over a period of three days in March 2011.
    • Track will be laid later this year to allow for LOCOG to carry out temporary overlay work which may need cranes and so could damage the track if it was laid now.
    • Black and white spectator seats were designed in the UK and manufactured in a factory in Luton. They were fitted between May and December 2010.
    • Toilets for spectators are spread out across 32 separate buildings on the podium level and are all now functional.

    Latest Construction Health and Safety News

    HSE ENFORCEMENT WEEKLY UPDATE 18th JULY 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 18th July 2018

    MASSIVE FINE OVER USE OF UNSAFE GAS FITTINGS

    College gas installation contractor exposed after multiple gas leaks

    Read the rest of this article »

    Posted on 17th July 2018

    TEMP WORKS DESIGNED BY MANAGER AND UNCHECKED

    Collapse of platform highlighted failure in temporary works management

    Read the rest of this article »

    Posted on 17th July 2018

    RAISING SAFETY STANDARDS FOR CRANE LIFTING OPS

    Major crane seminar seeks to raise standards and share best practice

    Read the rest of this article »

    Posted on 17th July 2018

    WORKMAN SURVIVES 6m FALL THROUGH ROOFLIGHT

    Unsecured boards provided to cover nearby fragile materials

    Read the rest of this article »

    Posted on 17th July 2018

    MAJOR FACILITIES FIRM FAILED ON FLAT ROOF SAFETY

    Site specific planning lacking and safety standards not monitored

    Read the rest of this article »

    Posted on 17th July 2018

    HSE ALERT: UNAUTHORISED ACCESS TO SCAFFOLDS

    hselogo1Regulator sets out new guidance to protect children and the public

    Read the rest of this article »

    Posted on 17th July 2018

    ASSUMING OTHERS WILL ACT IS NO DEFENCE

    Incomplete edge protection caused 8m fall from roof

    Read the rest of this article »

    Posted on 17th July 2018

    LEADING ROOFING SPECIALIST FOUND WANTING

    Risk to employees and the public after failure to meet required standard

    Read the rest of this article »

    Posted on 17th July 2018

    SCAFFOLDER DEVELOPMENT EMBRACED BY INDUSTRY

    CPD training attracts over 2500 scaffolders during first year of operation

    Read the rest of this article »

    Posted on 11th July 2018

    SECURITY PANELS FELL DESPITE EARLY WARNING

    Firm fined £1/4 million after worker crushed by falling fencing

    Read the rest of this article »

    Posted on 10th July 2018

    VEHICLE STRIKE TRIGGERED FALL OF ROOF TRUSSES

    Manufacturer failed to identify a suitable safe system of work

    Read the rest of this article »

    Posted on 10th July 2018

    INCIDENT: CHILD STRUCK BY FALLING OBJECT

    Wood falling from scaffold triggers arrest of two on construction site

    Read the rest of this article »

    Posted on 10th July 2018

    IGNITION OF THINNERS VAPOUR CLAIMED TWO LIVES

    Refurbishment project director jailed over fatal use of flammable solvent

    Read the rest of this article »

    Posted on 10th July 2018

    HSE LONDON REFURBISHMENT CAMPAIGN FINDINGS

    hselogo1Material breaches of law found at over 50% of London sites visited

    Read the rest of this article »

    Posted on 4th July 2018

    CURFEW AND TAGGING FOR RECALCITRANT SCAFFOLDER

    Suspended jail sentence handed down after unsafe work at height

    Read the rest of this article »

    Posted on 4th July 2018

    CONSTRUCTION SECTOR DEATHS RISE SHARPLY

    HSE report construction worker deaths increase by 27% during 2017/18

    Read the rest of this article »

    Posted on 4th July 2018

    BUILD UK UPDATE KEY CONSTRUCTION H&S ADVICE

    Majors industry body endorses “go to” source of H&S information

    Read the rest of this article »

    Posted on 2nd July 2018

    OXYGEN CYLINDER “FIRED” INTO WORKSHOP

    Violent discharge of gas bottle seriously injured two engineers

    Read the rest of this article »

    Posted on 2nd July 2018

    PRISON SENTENCE OVER FAILURE TO MANAGE RISK

    Sole trader contractor ignored HSE advice once too often

    Read the rest of this article »

    Posted on 2nd July 2018

    DEATH EXPOSED MINIMAL MEWP MAINTENANCE

    Court told about “almost complete” lack of MEWP maintenance

    Read the rest of this article »

    Posted on 21st June 2018

    CONTRACTOR FAILED TO IDENTIFY ASBESTOS PRESENCE

    ACMs disturbed during works and firm failed to take suitable actions

    Read the rest of this article »

    Posted on 21st June 2018

    FALL THROUGH ROOF ON LOCAL COUNCIL BUILDING

    Fragile rooflight fractured when workman ‘misplaced footing’

    Read the rest of this article »

    Posted on 21st June 2018

    YOUNG WORKER POSED SPECIAL RISK TO CONTROL

    Conviction highlights duty to young persons and the vulnerable

    Read the rest of this article »

    Posted on 21st June 2018

    TOWER DEFECTS AND UNSAFE SYSTEM CAUSED DEATH

    Maintenance supervisor fell to his death through roof opening

    Read the rest of this article »

    Posted on 21st June 2018
    Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • 2 Responses to “OLYMPIC STADIUM CONSTRUCTORS PRAISED FOR PERFORMANCE”

    1. HSE SEEK TO SPREAD OLYMPICS BEST PRACTICE | PP Construction Safety News Desk Says:

      […] Waterman will describe how ”outstanding health and safety performance has been achieved” and provide an insight into the future for the industry and […]

    2. OLYMPICS BUILD TEAM SHARE HEALTH AND SAFETY LEGACY | PP Construction Safety News Desk Says:

      […] targets and milestones, including those concerning health and safety, and the project safety record is described as […]