Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    OLYMPIC STADIUM CONSTRUCTORS PRAISED FOR PERFORMANCE

    Stadium on time, under budget and with an exemplary safety record 

    The last piece of turf has been laid today on the Olympic Stadium’s field of play, marking the completion of construction on the flagship venue. 

    Construction started on the Olympic Stadium three years ago and has been completed “on time, under budget and with an exemplary safety record“. Over 240 UK businesses won contracts for construction of the Stadium and over 5250 people worked on the project. 

    ODA chairman John Armitt praised the design and construction team led by Sir Robert McAlpine saying:

    “The Olympic Stadium has been finished on time and under budget. To complete a complicated project such as this in less than three years is testament to the skill and professionalism of the UK construction industry. I would like to thank the Team Stadium consortium and all of the workers for their hard work and commitment.”

    Secretary of State for Culture, Olympics, Media and Sport Jeremy Hunt said:

    “The Olympic Stadium is the stunning centrepiece of the Olympic Park. Hundreds of businesses from across the UK have been involved in its creation. This is another landmark day for the London 2012 project and shows that Britain is at the forefront of the construction world.”

    Construction facts and figures
    • Construction started in May 2008 and has been completed in just under three years.
    • Design and construction team led by Sir Robert McAlpine
    • Over 5250 people have worked on the project over the past three years with the operatives workforce peaking at 650
    • Over 240 businesses, from Devon to Scotland, have worked on the construction of the Stadium.
    • More than 5,000 reinforced concrete columns were installed into the ground, up to 20m deep, to provide the foundations to support the Stadium structure
    • 112 steel rakers and 12,000 pre-cast concrete terracing units hold the spectator seating in place
    • Roof compression truss is made up of 28 steel sections, each one is 15m high by 30m long and weigh 85 tonne. A 1,350-tonne super lift crane was assembled in the field of play to lift them into place between January and July in 2009.
    • Cable net roof provides the correct conditions for athletes on the field of play and covering two-thirds of spectators. The roof is covered by 112 panels of white material, totalling 25,000 m². The fabric was fitted by a team of 23 expert abseilers.
    • Stadium is lit by 532 individual floodlights housed in 14 towers. The top of the towers reach 70m above the field of play.
    • 14 lighting tower weigh 34 tonnes each and are 28m high. They were lifted into place by a 650 tonne crane over a period of 14 days in March 2010.
    • 700 rooms and spaces within the Stadium, including changing rooms and toilets. The fit-out work has required15,000sqm of plasterboard, 140,000 blocks to create walls, 11km of pipes for drainage, 338km of power cables plus 33km of other data systems cabling and 12km of ventilation ducts.
    • Turf for the field of play was grown in Scunthorpe and was laid over a period of three days in March 2011.
    • Track will be laid later this year to allow for LOCOG to carry out temporary overlay work which may need cranes and so could damage the track if it was laid now.
    • Black and white spectator seats were designed in the UK and manufactured in a factory in Luton. They were fitted between May and December 2010.
    • Toilets for spectators are spread out across 32 separate buildings on the podium level and are all now functional.

    Latest Construction Health and Safety News

    HSE CONSTRUCTION DUST CONTROL ‘BLITZ’ STARTS

    Regulator inspections will check health taken as seriously as safety

    Read the rest of this article »

    Posted on 20th September 2018

    FLOOR CONSTRUCTION SYSTEM OF WORK UNSAFE

    Welder fell 3m from mezzanine area through purlin openings

    Read the rest of this article »

    Posted on 20th September 2018

    WORKER SUFFERS FATAL BURNS IN OXYGEN RICH AREA

    Sparks from angle grinder ignited clothing of workman in confined space

    Read the rest of this article »

    Posted on 19th September 2018

    RIBA PUBLISH DRAFT POST GRENFELL FIRE SAFETY PLAN

    Architects institute consults on ‘golden thread of fire safety information’

    Read the rest of this article »

    Posted on 19th September 2018

    MAJOR UK CONTRACTORS HIT BY MAJOR FINES

    Firms ordered to pay over £3m after foot trapped in rotating ‘screw’

    Read the rest of this article »

    Posted on 19th September 2018

    HSE ENFORCEMENT WEEKLY UPDATE 19th SEPT 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 19th September 2018

    DRIVER DIED TRAPPED BETWEEN TRAILER AND VEHICLE

    Firm fined £1.5 million over failure to assess coupling operations

    Read the rest of this article »

    Posted on 14th September 2018

    ACTUAL SYSTEM OF WORK WAS OPPOSITE OF RAMS

    Workman fell 4m through fragile asbestos roof sheet

    Read the rest of this article »

    Posted on 13th September 2018

    CDM PRINCIPAL DESIGNER FUNCTION MISUNDERSTOOD?

    Consultants claim CDM 2015 design risk management has ‘gone backwards’

    Read the rest of this article »

    Posted on 8th September 2018

    RISK ASSESSED PRECAUTIONS NOT IMPLEMENTED

    Action not paperwork essential to prevent fall during lifting operation

    Read the rest of this article »

    Posted on 7th September 2018

    CROSSRAIL PUBLISH BEST PRACTICE H&S GUIDES

    Sharing major project best practice can leave a lasting legacy

    Read the rest of this article »

    Posted on 5th September 2018

    SCHOOL STAFF LACKED ASBESTOS AWARENESS TRAINING

    Council fined £200k over asbestos flue and gasket rope failures

    Read the rest of this article »

    Posted on 5th September 2018

    INCIDENT: MEWP OVERTURN IN CITY CENTRE

    Images show aftermath of mobile elevating platform collapse

    Read the rest of this article »

    Posted on 5th September 2018

    SAFETY ALERT: DEFECTIVE SCAFFOLD COUPLER

    National Access and Scaffolding Confederation issues warning

    Read the rest of this article »

    Posted on 31st August 2018

    DEMOLISHING INTERNAL WALL REVEALED ASBESTOS

    Firm lacked survey and asbestos management plan for premises

    Read the rest of this article »

    Posted on 31st August 2018

    NEW HEALTH AND SAFETY TEST FOR ARCHITECTS

    RIBA raise the bar for members on design risk management and ‘life safety’

    Read the rest of this article »

    Posted on 31st August 2018

    POWER BUSINESSES FAILED ON LIFTING OPERATION

    Panel fell on workman during turbine maintenance project

    Read the rest of this article »

    Posted on 31st August 2018

    MAJOR INFRASTRUCTURE FIRM COMMITS TO ZERO HARM

    Behaviours to deliver zero lost time injury incident rate by 2021

    Read the rest of this article »

    Posted on 31st August 2018

    MANAGING TOWER CRANE FALLING OBJECT RISK

    CPA issues new technical information note

    Read the rest of this article »

    Posted on 31st August 2018

    POST EXPLOSION ASBESTOS WORK WAS UNSAFE

    Asbestos cement panels removed and cut with power tools

    Read the rest of this article »

    Posted on 31st August 2018

    FALL THROUGH UNFLOORED FACTORY ROOF SPACE

    Non-routine tasks require assessment and clear risk controls

    Read the rest of this article »

    Posted on 31st August 2018

    SEVENTH LONDON CYCLIST DEATH DURING 2018

    Building products vehicle involved in death of Queens doctor

    Read the rest of this article »

    Posted on 17th August 2018

    MAJOR CONTRACTOR FAILED TO SUPERVISE LIFT

    Errors whilst lifting pre-cast concrete blocks fined £600,000

    Read the rest of this article »

    Posted on 14th August 2018

    FIRM FINED £400,000 OVER VIBRATING TOOLS RISK

    Hand-held orbital sanders, rivet guns, grinders and drills caused harm

    Read the rest of this article »

    Posted on 14th August 2018

    OVERHEAD POWER AND EARTHING OF SCAFFOLDS

    NASC combines updates advice on scaffold electrical risks

    Read the rest of this article »

    Posted on 9th August 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    2 Responses to “OLYMPIC STADIUM CONSTRUCTORS PRAISED FOR PERFORMANCE”

    1. HSE SEEK TO SPREAD OLYMPICS BEST PRACTICE | PP Construction Safety News Desk Says:

      […] Waterman will describe how ”outstanding health and safety performance has been achieved” and provide an insight into the future for the industry and […]

    2. OLYMPICS BUILD TEAM SHARE HEALTH AND SAFETY LEGACY | PP Construction Safety News Desk Says:

      […] targets and milestones, including those concerning health and safety, and the project safety record is described as […]