• Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    OLYMPIC STADIUM CONSTRUCTORS PRAISED FOR PERFORMANCE

    Stadium on time, under budget and with an exemplary safety record 

    The last piece of turf has been laid today on the Olympic Stadium’s field of play, marking the completion of construction on the flagship venue. 

    Construction started on the Olympic Stadium three years ago and has been completed “on time, under budget and with an exemplary safety record“. Over 240 UK businesses won contracts for construction of the Stadium and over 5250 people worked on the project. 

    ODA chairman John Armitt praised the design and construction team led by Sir Robert McAlpine saying:

    “The Olympic Stadium has been finished on time and under budget. To complete a complicated project such as this in less than three years is testament to the skill and professionalism of the UK construction industry. I would like to thank the Team Stadium consortium and all of the workers for their hard work and commitment.”

    Secretary of State for Culture, Olympics, Media and Sport Jeremy Hunt said:

    “The Olympic Stadium is the stunning centrepiece of the Olympic Park. Hundreds of businesses from across the UK have been involved in its creation. This is another landmark day for the London 2012 project and shows that Britain is at the forefront of the construction world.”

    Construction facts and figures
    • Construction started in May 2008 and has been completed in just under three years.
    • Design and construction team led by Sir Robert McAlpine
    • Over 5250 people have worked on the project over the past three years with the operatives workforce peaking at 650
    • Over 240 businesses, from Devon to Scotland, have worked on the construction of the Stadium.
    • More than 5,000 reinforced concrete columns were installed into the ground, up to 20m deep, to provide the foundations to support the Stadium structure
    • 112 steel rakers and 12,000 pre-cast concrete terracing units hold the spectator seating in place
    • Roof compression truss is made up of 28 steel sections, each one is 15m high by 30m long and weigh 85 tonne. A 1,350-tonne super lift crane was assembled in the field of play to lift them into place between January and July in 2009.
    • Cable net roof provides the correct conditions for athletes on the field of play and covering two-thirds of spectators. The roof is covered by 112 panels of white material, totalling 25,000 m². The fabric was fitted by a team of 23 expert abseilers.
    • Stadium is lit by 532 individual floodlights housed in 14 towers. The top of the towers reach 70m above the field of play.
    • 14 lighting tower weigh 34 tonnes each and are 28m high. They were lifted into place by a 650 tonne crane over a period of 14 days in March 2010.
    • 700 rooms and spaces within the Stadium, including changing rooms and toilets. The fit-out work has required15,000sqm of plasterboard, 140,000 blocks to create walls, 11km of pipes for drainage, 338km of power cables plus 33km of other data systems cabling and 12km of ventilation ducts.
    • Turf for the field of play was grown in Scunthorpe and was laid over a period of three days in March 2011.
    • Track will be laid later this year to allow for LOCOG to carry out temporary overlay work which may need cranes and so could damage the track if it was laid now.
    • Black and white spectator seats were designed in the UK and manufactured in a factory in Luton. They were fitted between May and December 2010.
    • Toilets for spectators are spread out across 32 separate buildings on the podium level and are all now functional.

    Latest Construction Health and Safety News

    HSE ENFORCEMENT DATABASE LATEST UPDATE

    hselogo1View current online register of HSE prosecutions and enforcement notices

    Read the rest of this article »

    Posted on 31st October 2019

    DEVELOPER AND DIRECTOR PUT PUBLIC AT RISK

    Demolition undertaken without surveys and effective safety precautions

    Read the rest of this article »

    Posted on 28th October 2019

    SELECTED NEWS POSTED RECENTLY ON TWITTER

    Posted on 28th October 2019

    BY-PASSING MACHINE INTERLOCK FINED £1.275 MILLION

    Trapped key safety system failed to prevent access to conveyor danger

    Read the rest of this article »

    Posted on 24th October 2019

    HSE LOSES PATIENCE WITH ERRANT CONTRACTOR

    Roofing firm fined £30,000 over failure to manage work at height risks

    Read the rest of this article »

    Posted on 24th October 2019

    TRUSS ERECTION LACKED INTERNAL FALL PROTECTION

    Carpenter fell and injured whilst falling with roof truss

    Read the rest of this article »

    Posted on 24th October 2019

    WORKMAN FELL HEAD FIRST THROUGH ROOFLIGHT

    Fragile roof dangers not assessed and properly controlled

    Read the rest of this article »

    Posted on 24th October 2019

    STRUCTURAL SAFETY BODY LATEST NEWSLETTER

    CROSS publishes reports and expert comment on a range of issues

    Read the rest of this article »

    Posted on 18th October 2019

    HSE RISK REDUCTION THROUGH DESIGN AWARD

    Regulator seeks to promote hazard avoidance and risk minimisation

    Read the rest of this article »

    Posted on 18th October 2019

    CLIENT AND CONTRACTOR FINED OVER ASBESTOS RISK

    Checks for presence of asbestos not undertaken prior to refurbishment

    Read the rest of this article »

    Posted on 18th October 2019

    DIRECTOR PROSECUTED AND JAILED AS EMPLOYEE

    Workman fatally injured when crushed between bucket and wall

    Read the rest of this article »

    Posted on 18th October 2019

    BUILDING MATERIALS FIRM FINED OVER FATALITY

    Failure to effectively isolated power to machinery caused death of engineer

    Read the rest of this article »

    Posted on 10th October 2019

    CUSTOM AND PRACTICE CAUSED EXPLOSION DEATHS

    Electrical accumulator explosion claims the lives of two engineers

    Read the rest of this article »

    Posted on 10th October 2019

    REBAR FELL DURING TANDEM FLT LIFTING OP

    Workman seriously injured during improperly planned and executed lift

    Read the rest of this article »

    Posted on 10th October 2019

    FIRM FINED AFTER FINGER OF TRAINEE SEVERED

    Young worker injured hand working on unguarded rip saw

    Read the rest of this article »

    Posted on 8th October 2019

    WORKMAN FELL THROUGH ROOF OPENING

    Contractor failed to provide collective edge protection or fall arrest

    Read the rest of this article »

    Posted on 7th October 2019

    DRIVER UNDER TRAINING CRUSHED BY TELEHANDLER

    Court sentences company director to unpaid work community order

    Read the rest of this article »

    Posted on 30th September 2019

    DIRECTOR IN DOCK OVER FRAGILE ROOF RISK

    Roofing contractor and director failed to plan and manage falls risk

    Read the rest of this article »

    Posted on 30th September 2019

    HSE START PROJECT HEALTH RISK INTERVENTIONS

    Regulator set to check health risks assessed and controls in place

    Read the rest of this article »

    Posted on 30th September 2019

    AIF NATIONAL WORKING AT HEIGHT CONFERENCE

    HSE Construction Head to speak at Access Industry Forum conference

    Read the rest of this article »

    Posted on 23rd September 2019

    NEW HSE HAVS CALCULATOR TO HELP CONTROL RISK

    New calculator includes “cautious estimates” for common tools

    Read the rest of this article »

    Posted on 23rd September 2019

    JAIL TERM FOR DIRECTOR OVER LORRY CRANE DEFECTS

    Operator impaled on dangerous and uninspected lifting appliance

    Read the rest of this article »

    Posted on 23rd September 2019

    STEEL PIPE FALL TRIGGERS FREAK CAUSE OF DEATH

    Wooden bearer sent flying by pipe struck workman on head

    Read the rest of this article »

    Posted on 16th September 2019

    FATAL FALL FROM INSECURE SCAFFOLD LADDER

    Scaffold erected by unqualified and incompetent person

    Read the rest of this article »

    Posted on 16th September 2019

    FIRMS FAILED TO MONITOR SAFE SYSTEM OF WORK

    Principal Contractor and specialist fined over fall through roof mesh

    Read the rest of this article »

    Posted on 12th September 2019
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    2 Responses to “OLYMPIC STADIUM CONSTRUCTORS PRAISED FOR PERFORMANCE”

    1. HSE SEEK TO SPREAD OLYMPICS BEST PRACTICE | PP Construction Safety News Desk Says:

      […] Waterman will describe how ”outstanding health and safety performance has been achieved” and provide an insight into the future for the industry and […]

    2. OLYMPICS BUILD TEAM SHARE HEALTH AND SAFETY LEGACY | PP Construction Safety News Desk Says:

      […] targets and milestones, including those concerning health and safety, and the project safety record is described as […]