Turner Access Higher Safety Total Access
Total Access Ethentic Chipmunk Data
Chipmunk Data Turner Access Ethentic

OLYMPIC STADIUM CONSTRUCTORS PRAISED FOR PERFORMANCE

Stadium on time, under budget and with an exemplary safety record 

The last piece of turf has been laid today on the Olympic Stadium’s field of play, marking the completion of construction on the flagship venue. 

Construction started on the Olympic Stadium three years ago and has been completed “on time, under budget and with an exemplary safety record“. Over 240 UK businesses won contracts for construction of the Stadium and over 5250 people worked on the project. 

ODA chairman John Armitt praised the design and construction team led by Sir Robert McAlpine saying:

“The Olympic Stadium has been finished on time and under budget. To complete a complicated project such as this in less than three years is testament to the skill and professionalism of the UK construction industry. I would like to thank the Team Stadium consortium and all of the workers for their hard work and commitment.”

Secretary of State for Culture, Olympics, Media and Sport Jeremy Hunt said:

“The Olympic Stadium is the stunning centrepiece of the Olympic Park. Hundreds of businesses from across the UK have been involved in its creation. This is another landmark day for the London 2012 project and shows that Britain is at the forefront of the construction world.”

Construction facts and figures
  • Construction started in May 2008 and has been completed in just under three years.
  • Design and construction team led by Sir Robert McAlpine
  • Over 5250 people have worked on the project over the past three years with the operatives workforce peaking at 650
  • Over 240 businesses, from Devon to Scotland, have worked on the construction of the Stadium.
  • More than 5,000 reinforced concrete columns were installed into the ground, up to 20m deep, to provide the foundations to support the Stadium structure
  • 112 steel rakers and 12,000 pre-cast concrete terracing units hold the spectator seating in place
  • Roof compression truss is made up of 28 steel sections, each one is 15m high by 30m long and weigh 85 tonne. A 1,350-tonne super lift crane was assembled in the field of play to lift them into place between January and July in 2009.
  • Cable net roof provides the correct conditions for athletes on the field of play and covering two-thirds of spectators. The roof is covered by 112 panels of white material, totalling 25,000 m². The fabric was fitted by a team of 23 expert abseilers.
  • Stadium is lit by 532 individual floodlights housed in 14 towers. The top of the towers reach 70m above the field of play.
  • 14 lighting tower weigh 34 tonnes each and are 28m high. They were lifted into place by a 650 tonne crane over a period of 14 days in March 2010.
  • 700 rooms and spaces within the Stadium, including changing rooms and toilets. The fit-out work has required15,000sqm of plasterboard, 140,000 blocks to create walls, 11km of pipes for drainage, 338km of power cables plus 33km of other data systems cabling and 12km of ventilation ducts.
  • Turf for the field of play was grown in Scunthorpe and was laid over a period of three days in March 2011.
  • Track will be laid later this year to allow for LOCOG to carry out temporary overlay work which may need cranes and so could damage the track if it was laid now.
  • Black and white spectator seats were designed in the UK and manufactured in a factory in Luton. They were fitted between May and December 2010.
  • Toilets for spectators are spread out across 32 separate buildings on the podium level and are all now functional.

Latest Construction Health and Safety News

FIRMS FINED £2M OVER FALLING PIPE FATALITY

Incorrect stacking of pipes triggered fall and crushing of workman

Read the rest of this article »

Posted on 20th April 2018

DOMESTIC PROJECT PC HANDED JAIL TERM

Workman fell from unprotected roof edge on dormer extension

Read the rest of this article »

Posted on 20th April 2018

MAJOR CONTRACTOR ERRED ON FRAGILE ROOF RISK

Firms fine £965,000 after painter fell through waiting room roof

Read the rest of this article »

Posted on 19th April 2018

HSE ENFORCEMENT UPDATE 19th APRIL 2018

hselogo1Prosecutions and enforcement notices update and analysis

Read the rest of this article »

Posted on 19th April 2018

STRUCTURAL SAFETY BODY LATEST NEWSLETTER

CROSS publishes reports and expert comment on a range of issues

Read the rest of this article »

Posted on 18th April 2018

NEW BIM SPEC FOR SHARING H&S INFORMATION

Specification for sharing health and safety info during construction projects

Read the rest of this article »

Posted on 17th April 2018

MANAGERS FORGED ASBESTOS DOCUMENTATION

Removal licence obtained using fake training and medical certificates

Read the rest of this article »

Posted on 17th April 2018

FINE OVER INCORRECT AND MISLEADING SURVEY

Specialist asbestos company failed to detect AIB on demolition project

Read the rest of this article »

Posted on 17th April 2018

IGNORING HSE ADVICE PENALISED BY LARGE FINE

Contractor fined over £50k for persistent WAH and welfare failings

Read the rest of this article »

Posted on 17th April 2018

PRISON OVER BASEMENT EXCAVATION AND COLLAPSE

Building contractor jailed after house collapsed in Brighton

Read the rest of this article »

Posted on 17th April 2018

DEFEATING POWER INTERLOCK CAUSED FLASHOVER

Systems for managing electrical safety found to be inadequate

Read the rest of this article »

Posted on 17th April 2018

LADDER SAFETY FAILURES ATTRACT MASSIVE FINE

National window firm left workers to ‘own devices’

Read the rest of this article »

Posted on 12th April 2018

FALLING MATERIAL STRUCK WORKMAN IN EXCAVATION

Risks of working in and near excavations highlighted by incident

Read the rest of this article »

Posted on 4th April 2018

HSE ENFORCEMENT WEEKLY UPDATE 4th APRIL 2018

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 4th April 2018

HOUSING ASSOCIATION FAILED ON VIBRATION RISK

Assessment, management and health surveillance all found wanting

Read the rest of this article »

Posted on 3rd April 2018

OCCUPIER AND CONTRACTOR FINED OVER FALL

Employee assisting contractor fell through roof during re-roofing project

Read the rest of this article »

Posted on 3rd April 2018

HSE FEARFUL OF GROWING ’BLUE TAPE’ BURDEN

hselogo1ISO 45001 could generate fresh business to business demands

Read the rest of this article »

Posted on 3rd April 2018

HSE ENFORCEMENT WEEKLY UPDATE 21st MAR 2018

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 28th March 2018

INCIDENTS: PASSER-BY STRUCK BY BRICKS

Pack of bricks appear to have fallen from crane

Read the rest of this article »

Posted on 28th March 2018

HSE RECONSIDER HOW TO INFLUENCE SMALLER FIRMS

hselogo1Regulator advice and messages are failing to chime with the SME businesses

Read the rest of this article »

Posted on 27th March 2018

DANGEROUS REMOVAL OF ASBESTOS CEMENT

Workers smashed asbestos sheets with crowbars whilst at risk of falling

Read the rest of this article »

Posted on 27th March 2018

HSE LAUNCH CONIAN SHARING AND SUPPORT PLATFORM

hselogo1New HSE web community now open to the public

Read the rest of this article »

Posted on 27th March 2018

FIRM FAILING ON HAVS SURVEILLANCE FINED £50,000

Door manufacturer failed to manage sanding and buffing tool vibration

Read the rest of this article »

Posted on 27th March 2018

PRE-CAST FIRM FINED OVER FINGER AMPUTATION

Lack of guarding and training triggered table saw injury

Read the rest of this article »

Posted on 26th March 2018

HSE STRIKE BEFORE A FALL ON SOLAR PANEL PROJECT

Director and company pay price for lack of fall prevention precautions

Read the rest of this article »

Posted on 26th March 2018
Turner Access Chipmunk Data
Total Access Ethentic
Higher Safety Turner Access

2 Responses to “OLYMPIC STADIUM CONSTRUCTORS PRAISED FOR PERFORMANCE”

  1. HSE SEEK TO SPREAD OLYMPICS BEST PRACTICE | PP Construction Safety News Desk Says:

    […] Waterman will describe how ”outstanding health and safety performance has been achieved” and provide an insight into the future for the industry and […]

  2. OLYMPICS BUILD TEAM SHARE HEALTH AND SAFETY LEGACY | PP Construction Safety News Desk Says:

    […] targets and milestones, including those concerning health and safety, and the project safety record is described as […]