• Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    OLYMPIC STADIUM CONSTRUCTORS PRAISED FOR PERFORMANCE

    Stadium on time, under budget and with an exemplary safety record 

    The last piece of turf has been laid today on the Olympic Stadium’s field of play, marking the completion of construction on the flagship venue. 

    Construction started on the Olympic Stadium three years ago and has been completed “on time, under budget and with an exemplary safety record“. Over 240 UK businesses won contracts for construction of the Stadium and over 5250 people worked on the project. 

    ODA chairman John Armitt praised the design and construction team led by Sir Robert McAlpine saying:

    “The Olympic Stadium has been finished on time and under budget. To complete a complicated project such as this in less than three years is testament to the skill and professionalism of the UK construction industry. I would like to thank the Team Stadium consortium and all of the workers for their hard work and commitment.”

    Secretary of State for Culture, Olympics, Media and Sport Jeremy Hunt said:

    “The Olympic Stadium is the stunning centrepiece of the Olympic Park. Hundreds of businesses from across the UK have been involved in its creation. This is another landmark day for the London 2012 project and shows that Britain is at the forefront of the construction world.”

    Construction facts and figures
    • Construction started in May 2008 and has been completed in just under three years.
    • Design and construction team led by Sir Robert McAlpine
    • Over 5250 people have worked on the project over the past three years with the operatives workforce peaking at 650
    • Over 240 businesses, from Devon to Scotland, have worked on the construction of the Stadium.
    • More than 5,000 reinforced concrete columns were installed into the ground, up to 20m deep, to provide the foundations to support the Stadium structure
    • 112 steel rakers and 12,000 pre-cast concrete terracing units hold the spectator seating in place
    • Roof compression truss is made up of 28 steel sections, each one is 15m high by 30m long and weigh 85 tonne. A 1,350-tonne super lift crane was assembled in the field of play to lift them into place between January and July in 2009.
    • Cable net roof provides the correct conditions for athletes on the field of play and covering two-thirds of spectators. The roof is covered by 112 panels of white material, totalling 25,000 m². The fabric was fitted by a team of 23 expert abseilers.
    • Stadium is lit by 532 individual floodlights housed in 14 towers. The top of the towers reach 70m above the field of play.
    • 14 lighting tower weigh 34 tonnes each and are 28m high. They were lifted into place by a 650 tonne crane over a period of 14 days in March 2010.
    • 700 rooms and spaces within the Stadium, including changing rooms and toilets. The fit-out work has required15,000sqm of plasterboard, 140,000 blocks to create walls, 11km of pipes for drainage, 338km of power cables plus 33km of other data systems cabling and 12km of ventilation ducts.
    • Turf for the field of play was grown in Scunthorpe and was laid over a period of three days in March 2011.
    • Track will be laid later this year to allow for LOCOG to carry out temporary overlay work which may need cranes and so could damage the track if it was laid now.
    • Black and white spectator seats were designed in the UK and manufactured in a factory in Luton. They were fitted between May and December 2010.
    • Toilets for spectators are spread out across 32 separate buildings on the podium level and are all now functional.

    Latest Construction Health and Safety News

    CONTRACTS MANAGER HANDED TWO YEAR PRISON TERM

    Safety fall arrest netting would have saved life of deceased workman

    Read the rest of this article »

    Posted on 15th January 2020

    WORKER FATALLY INJURED BY CONCRETE BEAM

    Lifting operation not properly planned, managed and supervised

    Read the rest of this article »

    Posted on 15th January 2020

    TREE FELLING OPERATIONS LACKED DEFINED COMMS

    Workman struck by falling tree inside “normal” exclusion zone

    Read the rest of this article »

    Posted on 14th January 2020

    CONTRACTOR ARRESTED OVER WELFARE FAILINGS

    Recalcitrant sole trader failed to attend court hearing

    Read the rest of this article »

    Posted on 14th January 2020

    MAJOR DEMOLITION CONTRACTOR FINED £500,000

    Collapse of concrete slab caused death of worker and excavator fall

    Read the rest of this article »

    Posted on 14th January 2020

    FALL FROM LADDER WHILST CARRYING BUCKET

    Contractor failed to provide basic safe lifting aids

    Read the rest of this article »

    Posted on 14th January 2020

    FAILURE TO COMPLY WITH HSE NOTICE PROVES COSTLY

    Director given suspended jail term and company fined £60,000

    Read the rest of this article »

    Posted on 14th January 2020

    DEVELOPER FAILED TO PLAN AND CHECK COMPETENCE

    Fall caused by ad-hoc working methods and lack of monitoring

    Read the rest of this article »

    Posted on 14th January 2020

    CYLINDER LEAK TEST CAUSED FATAL INJURIES

    Corrosion inhibitor triggered failure and shrapnel ejection

    Read the rest of this article »

    Posted on 14th January 2020

    FESTIVE GREETINGS TO ALL OUR READERS

    Read the rest of this article »

    Posted on 20th December 2019

    JAIL TERM FOLLOWS ROUTINE HSE SPOT CHECK

    Director of a roofing firm handed a suspended prison sentence

    Read the rest of this article »

    Posted on 19th December 2019

    TEENAGER FELL 3M DURING BLOCK AND BEAM WORK

    Workers uninstructed and left to devise own safe system of work

    Read the rest of this article »

    Posted on 19th December 2019

    PARCEL CARRIER FINED HEAVILY OVER FLT INCIDENT

    Reversing fork lift lacked segregation from pedestrians

    Read the rest of this article »

    Posted on 18th December 2019

    CONTRACTOR FINED OVER FLOOR OPENING FALL

    Thorough risk assessment and edge protection were both inadequate

    Read the rest of this article »

    Posted on 18th December 2019

    THREE WORKERS “CARRIED ALONG” IN SEWER INCIDENT

    Mentally affected and one man treated for long-term traumatic stress

    Read the rest of this article »

    Posted on 11th December 2019

    SOLAR FIRM AND DIRECTOR SENTENCED OVER DEATH

    Brother of business owner died in fall during panel installation

    Read the rest of this article »

    Posted on 10th December 2019

    DIRECTOR AND COMPANY FINED FOR ASBESTOS RISK

    HSE refurbishment campaign inspection revealed asbestos offences

    Read the rest of this article »

    Posted on 10th December 2019

    BULK BAG COLLAPSE CAUSED BY UNSAFE STACKING

    Bulk bag collapsed onto workman when struck by fork lift

    Read the rest of this article »

    Posted on 9th December 2019

    INTERLOCKED GUARD NOT WORKING TO ISOLATE POWER

    Two workmen seriously injured when plant started unexpectedly

    Read the rest of this article »

    Posted on 9th December 2019

    STREET FURNITURE RISK TO PUBLIC FINED £1.4M

    Council prosecuted following injury to child playing on hinged bollard

    Read the rest of this article »

    Posted on 9th December 2019

    WORKMEN SUFFER SERIOUS BURNS FROM CABLE STRIKE

    Assessment and system of work failed to appreciate electrical risk

    Read the rest of this article »

    Posted on 29th November 2019

    LADDERS WERE INAPPROPRIATE FOR WORK ON ROOF

    Workman paralysed after falling whilst installing roof ladder

    Read the rest of this article »

    Posted on 28th November 2019

    FIRM FAILED TO MANAGE EXHAUST VENTILATION

    HSE enforcement notices on wood dust and welding fume ignored

    Read the rest of this article »

    Posted on 27th November 2019

    RECALCITRANT DIRECTOR BARRED FROM OFFICE

    Dangerous telehandler used despite earlier fatality and enforcement

    Read the rest of this article »

    Posted on 25th November 2019

    DIRECTOR HID UNSAFE WORKING PRACTICES FROM HSE

    Workers exposed to sprayed paints containing asthma causing isocyantes

    Read the rest of this article »

    Posted on 25th November 2019
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    2 Responses to “OLYMPIC STADIUM CONSTRUCTORS PRAISED FOR PERFORMANCE”

    1. HSE SEEK TO SPREAD OLYMPICS BEST PRACTICE | PP Construction Safety News Desk Says:

      […] Waterman will describe how ”outstanding health and safety performance has been achieved” and provide an insight into the future for the industry and […]

    2. OLYMPICS BUILD TEAM SHARE HEALTH AND SAFETY LEGACY | PP Construction Safety News Desk Says:

      […] targets and milestones, including those concerning health and safety, and the project safety record is described as […]