Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    OLYMPIC STADIUM CONSTRUCTORS PRAISED FOR PERFORMANCE

    Stadium on time, under budget and with an exemplary safety record 

    The last piece of turf has been laid today on the Olympic Stadium’s field of play, marking the completion of construction on the flagship venue. 

    Construction started on the Olympic Stadium three years ago and has been completed “on time, under budget and with an exemplary safety record“. Over 240 UK businesses won contracts for construction of the Stadium and over 5250 people worked on the project. 

    ODA chairman John Armitt praised the design and construction team led by Sir Robert McAlpine saying:

    “The Olympic Stadium has been finished on time and under budget. To complete a complicated project such as this in less than three years is testament to the skill and professionalism of the UK construction industry. I would like to thank the Team Stadium consortium and all of the workers for their hard work and commitment.”

    Secretary of State for Culture, Olympics, Media and Sport Jeremy Hunt said:

    “The Olympic Stadium is the stunning centrepiece of the Olympic Park. Hundreds of businesses from across the UK have been involved in its creation. This is another landmark day for the London 2012 project and shows that Britain is at the forefront of the construction world.”

    Construction facts and figures
    • Construction started in May 2008 and has been completed in just under three years.
    • Design and construction team led by Sir Robert McAlpine
    • Over 5250 people have worked on the project over the past three years with the operatives workforce peaking at 650
    • Over 240 businesses, from Devon to Scotland, have worked on the construction of the Stadium.
    • More than 5,000 reinforced concrete columns were installed into the ground, up to 20m deep, to provide the foundations to support the Stadium structure
    • 112 steel rakers and 12,000 pre-cast concrete terracing units hold the spectator seating in place
    • Roof compression truss is made up of 28 steel sections, each one is 15m high by 30m long and weigh 85 tonne. A 1,350-tonne super lift crane was assembled in the field of play to lift them into place between January and July in 2009.
    • Cable net roof provides the correct conditions for athletes on the field of play and covering two-thirds of spectators. The roof is covered by 112 panels of white material, totalling 25,000 m². The fabric was fitted by a team of 23 expert abseilers.
    • Stadium is lit by 532 individual floodlights housed in 14 towers. The top of the towers reach 70m above the field of play.
    • 14 lighting tower weigh 34 tonnes each and are 28m high. They were lifted into place by a 650 tonne crane over a period of 14 days in March 2010.
    • 700 rooms and spaces within the Stadium, including changing rooms and toilets. The fit-out work has required15,000sqm of plasterboard, 140,000 blocks to create walls, 11km of pipes for drainage, 338km of power cables plus 33km of other data systems cabling and 12km of ventilation ducts.
    • Turf for the field of play was grown in Scunthorpe and was laid over a period of three days in March 2011.
    • Track will be laid later this year to allow for LOCOG to carry out temporary overlay work which may need cranes and so could damage the track if it was laid now.
    • Black and white spectator seats were designed in the UK and manufactured in a factory in Luton. They were fitted between May and December 2010.
    • Toilets for spectators are spread out across 32 separate buildings on the podium level and are all now functional.

    Latest Construction Health and Safety News

    MAJOR FM FIRM FAILED TO MAINTAIN BACK-UP POWER

    Power loss at laboratory site created potential risk from biological agents

    Read the rest of this article »

    Posted on 18th November 2018

    IGNORING HSE PROHIBITIONS COST FIRM £250,000

    CDM 2015 and work at height requirements repeatedly breached

    Read the rest of this article »

    Posted on 16th November 2018

    ROOF COLLAPSED UNDER EXCESS LOADING

    Director and company fined over roof design failures

    Read the rest of this article »

    Posted on 11th November 2018

    FORK LIFT OVERTURNED IN SCAFFOLDING YARD

    Untrained operator suffered life changing crush injuries

    Read the rest of this article »

    Posted on 10th November 2018

    STRUCTURAL SAFETY ALERT: EFFECTS OF SCALE

    SCOSS issues alert after concerns disclosed over ‘large structures’

    Read the rest of this article »

    Posted on 7th November 2018

    ASBESTOS EXPOSED BY UNTRAINED WORKERS

    Contractor failed to act properly despite HSE intervention

    Read the rest of this article »

    Posted on 7th November 2018

    GAS MAIN STRIKE REPAIR CAUSED SEVERE BURNS

    Contractor excavator damage to gas pipe ends in £1.2m fine

    Read the rest of this article »

    Posted on 7th November 2018

    REBAR FELL FROM FLT IN UNSAFE LIFTING OPERATION

    Multiple fractures caused by inappropriate use of fork lift

    Read the rest of this article »

    Posted on 7th November 2018

    HSE ENFORCEMENT WEEKLY UPDATE 7th NOV 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 7th November 2018

    POORLY PLANNED LIFT DISMANTLE INJURED WORKMAN

    Counterweight or suspension rope struck worker in lift shaft

    Read the rest of this article »

    Posted on 1st November 2018

    CONSTRUCTION INJURY AND ILL-HEALTH 2017/18

    hselogo1Fatal injury rate in long term decline whilst ill-health trend flat lining

    Read the rest of this article »

    Posted on 1st November 2018

    DUMPER DRIVEN INTO OPEN UNGUARDED EXCAVATION

    Contractor fined over absence of suitable excavation / dumper precautions

    Read the rest of this article »

    Posted on 1st November 2018

    DEATH FAILED TO TRIGGER PREVENTIVE ACTION

    Prison term for director whilst his company ordered to pay £3/4m

    Read the rest of this article »

    Posted on 29th October 2018

    FAILURE TO MAINTAIN GUARDS PROVES COSTLY

    Woodworking machinery defective despite previous HSE advice

    Read the rest of this article »

    Posted on 26th October 2018

    CISRS LAUNCH SYSTEM SCAFFOLD INSPECTION COURSES

    Training courses prompted by growing use of system scaffolding

    Read the rest of this article »

    Posted on 25th October 2018

    HSE INSPECTS CLADDING REMOVAL AND REPLACEMENT

    hselogo1Advice to Inspectors published on fire risk during work on tall buildings

    Read the rest of this article »

    Posted on 25th October 2018

    HIGHWAYS, RAIL AND WATER HEALTH & SAFETY HUBS

    Websites provide useful information, alerts and tools

    Read the rest of this article »

    Posted on 24th October 2018

    ELIMINATING CONCRETE DRILLING VIBRATION HAZARD

    Cutting specialist innovation avoids vibration exposure management

    Read the rest of this article »

    Posted on 24th October 2018

    NEW MEWP WORK AT HEIGHT RESCUE GUIDANCE

    Industry body publishes simple guidance on MEWP stranding actions

    Read the rest of this article »

    Posted on 24th October 2018

    HSE PUBLISH RIDDOR DATA VISUALISATION TOOL

    hselogo1Construction injury records made more relevant and easily used

    Read the rest of this article »

    Posted on 24th October 2018

    COUNCIL OVERLOOKED ICE RINK SLIPPING RISK

    Obvious risk of employees falling on ice rink was left uncontrolled

    Read the rest of this article »

    Posted on 22nd October 2018

    STRUCTURAL SAFETY BODY LATEST NEWSLETTER

    CROSS publishes reports and expert comment on a range of issues

    Read the rest of this article »

    Posted on 22nd October 2018

    YOUNG WORKER FELL FROM PETROL STATION CANOPY

    Steel fabricator after young construction worker falls on first day at work

    Read the rest of this article »

    Posted on 18th October 2018

    FIRM FINED OVER FAILURE AT ASSESS VIBRATION RISK

    Vibration regulations not acted upon until seven years in operation

    Read the rest of this article »

    Posted on 18th October 2018

    FAILURE TO ISOLATE LEAVES WORKMAN PARALYSED

    Conveyor guards removed before power source isolated

    Read the rest of this article »

    Posted on 16th October 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    2 Responses to “OLYMPIC STADIUM CONSTRUCTORS PRAISED FOR PERFORMANCE”

    1. HSE SEEK TO SPREAD OLYMPICS BEST PRACTICE | PP Construction Safety News Desk Says:

      […] Waterman will describe how ”outstanding health and safety performance has been achieved” and provide an insight into the future for the industry and […]

    2. OLYMPICS BUILD TEAM SHARE HEALTH AND SAFETY LEGACY | PP Construction Safety News Desk Says:

      […] targets and milestones, including those concerning health and safety, and the project safety record is described as […]