Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    HSE RAISE THE PROFILE ON SAFETY OF TEMPORARY WORKS

    New guidance to HSE Inspectors on temporary works management published

    A number of recent construction sector fatalities and incidents have related to ‘temporary works’.

    HSE Construction Division has now raised the priority it gives to temporary works management in order to highlight and better control the risks associated with temporary works on construction sites.

    The aim is to:

    • Awareness – promote awareness and knowledge of the importance of managing temporary works;
    • Arrangements – improve contractors’ management arrangements of temporary works; and 
    • Competence – increase the competence of those engaged in temporary works management and design.
    Inspectors expect to see ‘appropriate’ arrangements

    The published HSE Guidance for Inspectors The management of temporary works in the construction industry SIM 02/2010/04 requires a focus on ensuring that “appropriate temporary works management arrangements and procedures have been adopted commensurate with the scale and complexity of the project and the construction risks involved”.

    It is expected that medium to large projects, and those with complex and/or high risk temporary works, will have formal management procedures in place specifically following the recommendations in BS5975.

    For smaller contractors and smaller simpler, projects, HSE will be looking for the principles of BS5975 to be in place. The extent to which procedures should be formalised will depend on the degree of risk rather than size of project.

    HSE wants to see good management of temporary works. BS5975 is an established standard representing good practice, but it also provides a useful yardstick for checking that essential elements of a management system are in place.

    Definition of ‘Temporary Works’

    “Temporary works” is a widely used expression in the construction industry for an “engineered solution” used to support or protect an existing structure or the permanent works during construction, or to support an item of plant or equipment, or the vertical sides or side-slopes of an excavation, or to provide access. The construction of most types of permanent works will require the use of some form of temporary works.

    Temporary works is defined in BS5975: 2008 Code of practice for temporary works procedures and the permissible stress design of falsework as “(those) parts of the works that allow or enable construction of, protect, support or provide access to, the permanent works and which might or might not remain in place at the completion of the works”.

    Examples of temporary works include, but are not limited to:

    1. Earthworks – trenches, excavations, temporary slopes and stockpiles.
    2. Structures – formwork, falsework, propping, façade retention, needling, shoring, edge protection, scaffolding, temporary bridges, site hoarding and signage, site fencing, cofferdams.
    3. Equipment/plant foundations – tower crane bases, supports, anchors and ties for construction hoists and mast climbing work platforms (MCWPs), groundworks to provide suitable locations for plant erection, e.g. mobile cranes and piling rigs.
    Comment

    Further advice and support may be found through the Temporary Works Forum (TWf). Forum sponsers include a number of major UK contactors.

    The TWf aims to encourage open discussion of any matter related to Temporary Works. The group is open to anyone, individual or corporate working within the industry and sharing this intent.

    Latest Construction Health and Safety News

    HSE SAFETY ALERT: TOWER CRANE BRAKES

    Collapse of tower crane jib in high winds prompts HSE warning

    Read the rest of this article »

    Posted on 11th December 2018

    VISITING ENGINEER CRUSHED BY SCAFFOLD TUBES

    Principal contractor “signed off” contractor storage arrangements

    Read the rest of this article »

    Posted on 11th December 2018

    CONCRETE EJECTED BY PUMPING UNIT CLAIMED LIFE

    Company and director failed to train and supervise pumping operations

    Read the rest of this article »

    Posted on 5th December 2018

    HSE ENFORCEMENT WEEKLY UPDATE 5th DEC 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 5th December 2018

    REFRESHED GUIDANCE ON FITNESS TO OPERATE PLANT

    Construction plant medical fitness Good Practice Guide

    Read the rest of this article »

    Posted on 4th December 2018

    MAJOR CONTRACTOR & LUL USED UNSAFE SYSTEM

    Work method to eliminate moving vehicle hazard not adopted

    Read the rest of this article »

    Posted on 4th December 2018

    OVERTURNING LORRY CAUSED DEATH OF DRIVER

    Groundworks project stockpiling arrangements not properly managed

    Read the rest of this article »

    Posted on 3rd December 2018

    FORTH BRIDGE LIFTING OPERATION NOT PLANNED

    Major project PC failed to plan, supervise and carry out lift safely

    Read the rest of this article »

    Posted on 3rd December 2018

    DEVELOPER FAILED ON ASBESTOS ASSESSMENT

    HSE inspection revealed refurb works without asbestos survey

    Read the rest of this article »

    Posted on 28th November 2018

    POST DRIVER HAMMER CRUSHED HAND OF WORKMAN

    Unsafe system of work for vehicle crash barrier installation

    Read the rest of this article »

    Posted on 28th November 2018

    WORKER FELL FROM LOFT THROUGH CEILING

    Major house builder lacked understanding of loft fragile surfaces risk

    Read the rest of this article »

    Posted on 28th November 2018

    NEW SITE DUMPER SAFETY GUIDANCE ISSUED

    Construction plant sector concerns prompts CPA consults on draft

    Read the rest of this article »

    Posted on 28th November 2018

    CCTV INSTALLER FELL THROUGH FRAGILE ROOFLIGHT

    Contractor failed to properly plan and control the risks

    Read the rest of this article »

    Posted on 28th November 2018

    VISITOR DIED FALLING INTO CONCEALED BASEMENT

    Contractor failed to protect basement void on domestic project

    Read the rest of this article »

    Posted on 28th November 2018

    RACKING FALL REVEALED UNSAFE SYSTEM OF WORK

    European firm fined £300,000 after UK sub-contractor employee fell

    Read the rest of this article »

    Posted on 18th November 2018

    FAILURE TO ACT ON VIBRATION AND SILICA HAZARDS

    Worker health put at risk during stripping of furnace lining

    Read the rest of this article »

    Posted on 18th November 2018

    MAJOR FM FIRM FAILED TO MAINTAIN BACK-UP POWER

    Power loss at laboratory site created potential risk from biological agents

    Read the rest of this article »

    Posted on 18th November 2018

    IGNORING HSE PROHIBITIONS COST FIRM £250,000

    CDM 2015 and work at height requirements repeatedly breached

    Read the rest of this article »

    Posted on 16th November 2018

    ROOF COLLAPSED UNDER EXCESS LOADING

    Director and company fined over roof design failures

    Read the rest of this article »

    Posted on 11th November 2018

    FORK LIFT OVERTURNED IN SCAFFOLDING YARD

    Untrained operator suffered life changing crush injuries

    Read the rest of this article »

    Posted on 10th November 2018

    STRUCTURAL SAFETY ALERT: EFFECTS OF SCALE

    SCOSS issues alert after concerns disclosed over ‘large structures’

    Read the rest of this article »

    Posted on 7th November 2018

    ASBESTOS EXPOSED BY UNTRAINED WORKERS

    Contractor failed to act properly despite HSE intervention

    Read the rest of this article »

    Posted on 7th November 2018

    GAS MAIN STRIKE REPAIR CAUSED SEVERE BURNS

    Contractor excavator damage to gas pipe ends in £1.2m fine

    Read the rest of this article »

    Posted on 7th November 2018

    REBAR FELL FROM FLT IN UNSAFE LIFTING OPERATION

    Multiple fractures caused by inappropriate use of fork lift

    Read the rest of this article »

    Posted on 7th November 2018

    POORLY PLANNED LIFT DISMANTLE INJURED WORKMAN

    Counterweight or suspension rope struck worker in lift shaft

    Read the rest of this article »

    Posted on 1st November 2018
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    9 Responses to “HSE RAISE THE PROFILE ON SAFETY OF TEMPORARY WORKS”

    1. HSE CONSTRUCTION SECTOR PRIORITIES 2011 AND BEYOND | PP Construction Safety News Desk Says:

      […] Works – promoting awareness and knowledge of the importance of managing temporary works effectively and ensure that adequate management arrangements are in […]

    2. TEMPORARY WORKS NOT PROPERLY DESIGNED FOR SAFETY | PP Construction Safety News Desk Says:

      […] HSE Inspector Viv Neaverson said: “This prosecution arises as a result of Bridgford’s failing in their duty as the company responsible for the temporary works. […]

    3. MAJOR CONTRACTOR PROSECUTED OVER TEMPORARY WORKS COLLAPSE | PP Construction Safety News Desk Says:

      […] that concrete was being pumped onto the third floor of the building on 19 September 2007 when the temporary works suddenly collapsed. Injuries to the workers on site included cement burns to their skin and […]

    4. CONCRETE UNIT COLLAPSE SPARKED BY DESIGN COMMS FAILURE | PP Construction Safety News Desk Says:

      […] HSE advises that British Standard, (BS 5975:2008 – Code of Practice for Temporary Works Procedures and the Permissible Stress Design of Falsework) published since the incident, clarifies how the temporary works should be managed on such a project and focuses on the competence of all parties. […]

    5. MAJOR CONTRACTOR FAILED ON TEMPORARY WORKS SAFETY | PP Construction Safety News Desk Says:

      […] Speaking after the hearing, HSE Principal Inspector Andrew Kingscott said: “The two workers were fortunate not to have been seriously injured in this incident, which was entirely preventable had Balfour Beatty followed the proper temporary works procedure. […]

    6. SAFETY EVENT TRIGGERED BY SITE DEATHS AND INJURY | PP Construction Safety News Desk Says:

      […] either a morning or afternoon session covering asbestos, working at height, respiratory risks and temporary works. For further information call: 0151 951 4012 or contact […]

    7. HSE PRIORITIES FOR CONSTRUCTION SECTOR 2013-14 | PP Construction Safety News Desk Says:

      […] Works – managing temporary works through adequate management […]

    8. FREE WWT TRAINING EVENT ON TW AND BEHAVIOUR | PP Construction Safety News Desk Says:

      […] Temporary Works […]

    9. TEMPORARY WORKS COORDINATOR TRAINING | PP Construction Safety News Desk Says:

      […] Following a number of construction sector deaths and incidents related to ‘temporary works’ HSE has raised the priority it gives to temporary works management. […]