Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    HSE RAISE THE PROFILE ON SAFETY OF TEMPORARY WORKS

    New guidance to HSE Inspectors on temporary works management published

    A number of recent construction sector fatalities and incidents have related to ‘temporary works’.

    HSE Construction Division has now raised the priority it gives to temporary works management in order to highlight and better control the risks associated with temporary works on construction sites.

    The aim is to:

    • Awareness – promote awareness and knowledge of the importance of managing temporary works;
    • Arrangements – improve contractors’ management arrangements of temporary works; and 
    • Competence – increase the competence of those engaged in temporary works management and design.
    Inspectors expect to see ‘appropriate’ arrangements

    The published HSE Guidance for Inspectors The management of temporary works in the construction industry SIM 02/2010/04 requires a focus on ensuring that “appropriate temporary works management arrangements and procedures have been adopted commensurate with the scale and complexity of the project and the construction risks involved”.

    It is expected that medium to large projects, and those with complex and/or high risk temporary works, will have formal management procedures in place specifically following the recommendations in BS5975.

    For smaller contractors and smaller simpler, projects, HSE will be looking for the principles of BS5975 to be in place. The extent to which procedures should be formalised will depend on the degree of risk rather than size of project.

    HSE wants to see good management of temporary works. BS5975 is an established standard representing good practice, but it also provides a useful yardstick for checking that essential elements of a management system are in place.

    Definition of ‘Temporary Works’

    “Temporary works” is a widely used expression in the construction industry for an “engineered solution” used to support or protect an existing structure or the permanent works during construction, or to support an item of plant or equipment, or the vertical sides or side-slopes of an excavation, or to provide access. The construction of most types of permanent works will require the use of some form of temporary works.

    Temporary works is defined in BS5975: 2008 Code of practice for temporary works procedures and the permissible stress design of falsework as “(those) parts of the works that allow or enable construction of, protect, support or provide access to, the permanent works and which might or might not remain in place at the completion of the works”.

    Examples of temporary works include, but are not limited to:

    1. Earthworks – trenches, excavations, temporary slopes and stockpiles.
    2. Structures – formwork, falsework, propping, façade retention, needling, shoring, edge protection, scaffolding, temporary bridges, site hoarding and signage, site fencing, cofferdams.
    3. Equipment/plant foundations – tower crane bases, supports, anchors and ties for construction hoists and mast climbing work platforms (MCWPs), groundworks to provide suitable locations for plant erection, e.g. mobile cranes and piling rigs.
    Comment

    Further advice and support may be found through the Temporary Works Forum (TWf). Forum sponsers include a number of major UK contactors.

    The TWf aims to encourage open discussion of any matter related to Temporary Works. The group is open to anyone, individual or corporate working within the industry and sharing this intent.

    Latest Construction Health and Safety News

    SOLVENT IGNITED DURING FLOOR CLEANING WORKS

    Flammable solvent fire fought with water spreading fire further

    Read the rest of this article »

    Posted on 13th February 2019

    INEVITABLE COLLAPSE OF SCAFFOLD ON TO SCHOOL

    Scaffold not designed or installed to withstand foreseeable loads

    Read the rest of this article »

    Posted on 13th February 2019

    HSE ENFORCEMENT WEEKLY UPDATE 13th FEB 2019

    hselogo1Latest online register of prosecutions and enforcement notices

    Read the rest of this article »

    Posted on 13th February 2019

    OIL DRUM EXPLODED DURING HOT CUTTING WORK

    Firm fined £400k after drum lid ejected causing loss of leg

    Read the rest of this article »

    Posted on 12th February 2019

    ROOFLIGHT FALL ON NUCLEAR POWER SITE

    Energy generating company and maintenance contractor fined

    Read the rest of this article »

    Posted on 12th February 2019

    DIRECTOR PROSECUTED AFTER 6METRE ROOF FALL

    Untrained worker fell through rooflight in fragile asbestos roof

    Read the rest of this article »

    Posted on 12th February 2019

    HSE ALERT: MILD STEEL WELDING CANCER RISK

    HSE announces enforcement action change based on new cancer evidence

    Read the rest of this article »

    Posted on 11th February 2019

    LORRY MOUNTED LIFTING OPERATION PROVED FATAL

    Steel staircase toppled from vehicle after sling snagged

    Read the rest of this article »

    Posted on 7th February 2019

    DIRECTOR AND BUSINESS IN COURT OVER DEATH

    Scaffold not priced for on domestic roof-line refurbishment work

    Read the rest of this article »

    Posted on 6th February 2019

    FRAGILE ROOFLIGHT HAZARD PROTECTION MISSING

    Two businesses prosecuted after a worker fell through a fragile rooflight

    Read the rest of this article »

    Posted on 5th February 2019

    STRUCTURAL SAFETY BODY LATEST NEWSLETTER

    CROSS publishes reports and expert comment on a range of issues

    Read the rest of this article »

    Posted on 4th February 2019

    FINGERS CRUSHED BY METAL FOLDING MACHINE

    Steel cladding firm fined £600k over failure guard access to danger

    Read the rest of this article »

    Posted on 4th February 2019

    ASBESTOS ILLEGALLY REMOVED AFTER SURVEY

    Surveyor pricing asbestos work found contractor jumped the gun

    Read the rest of this article »

    Posted on 4th February 2019

    SITE DUMPER PRECAUTIONS FAILED TO PREVENT DEATH

    Contractor fined £600k for poor management of vehicle/people interface

    Read the rest of this article »

    Posted on 4th February 2019

    BUILDER EXPOSED RESIDENTS TO POISONING HAZARD

    Prison term for builder who put three at risk from carbon monoxide

    Read the rest of this article »

    Posted on 4th February 2019

    POOR SEPARATION OF VEHICLES AND PEDESTRIANS

    Logistics company fined £150,000 after driver suffers serious injuries

    Read the rest of this article »

    Posted on 4th February 2019

    £1MILLION FINE OVER VEHICLE RISK MANAGEMENT

    Death of workman exposed uncontrolled vehicle manoeuvring

    Read the rest of this article »

    Posted on 25th January 2019

    ACCREDITATION IS ONLY ONE WAY TO CONFIDENCE

    HSE publishes guidance on demonstrating CDM 2015 competence

    Read the rest of this article »

    Posted on 24th January 2019

    PRECAUTIONS ON PAPER LACKING IN PRACTICE

    Fatal fall through opening in concrete slab during work with breaker

    Read the rest of this article »

    Posted on 24th January 2019

    HSE TARGETS HEALTH ON LONDON PROJECTS

    Regulator starts inspection ‘blitz’ on construction sites

    Read the rest of this article »

    Posted on 23rd January 2019

    WORKMAN FELL FROM UNSECURED LADDER

    Industrial cladding company failed to assess and control WAH

    Read the rest of this article »

    Posted on 18th January 2019

    SCAFFOLDER FELL THROUGH FRAGILE ROOFLIGHT

    Fall through roof leaves workman with life-changing injuries

    Read the rest of this article »

    Posted on 18th January 2019

    ARM DRAGGED INTO CONVEYOR BELT DANGER

    Workman seriously injured on first day at work in quarry

    Read the rest of this article »

    Posted on 16th January 2019

    ROOF TRUSSES TOPPLED TRAPPING WORKMAN

    Principal contractor failed to plan, manage and monitor project

    Read the rest of this article »

    Posted on 16th January 2019

    SCAFFOLDING AWARENESS TRAINING FOR ALL

    CISRS set to target painters, bricklayers, electricians and plumbers

    Read the rest of this article »

    Posted on 16th January 2019
    Ethentic Ethentic Higher Safety Higher Safety Chipmunk Data Chipmunk Data
  • Higher Safety Higher Safety Chipmunk Data Chipmunk Data Ethentic Ethentic

    9 Responses to “HSE RAISE THE PROFILE ON SAFETY OF TEMPORARY WORKS”

    1. HSE CONSTRUCTION SECTOR PRIORITIES 2011 AND BEYOND | PP Construction Safety News Desk Says:

      […] Works – promoting awareness and knowledge of the importance of managing temporary works effectively and ensure that adequate management arrangements are in […]

    2. TEMPORARY WORKS NOT PROPERLY DESIGNED FOR SAFETY | PP Construction Safety News Desk Says:

      […] HSE Inspector Viv Neaverson said: “This prosecution arises as a result of Bridgford’s failing in their duty as the company responsible for the temporary works. […]

    3. MAJOR CONTRACTOR PROSECUTED OVER TEMPORARY WORKS COLLAPSE | PP Construction Safety News Desk Says:

      […] that concrete was being pumped onto the third floor of the building on 19 September 2007 when the temporary works suddenly collapsed. Injuries to the workers on site included cement burns to their skin and […]

    4. CONCRETE UNIT COLLAPSE SPARKED BY DESIGN COMMS FAILURE | PP Construction Safety News Desk Says:

      […] HSE advises that British Standard, (BS 5975:2008 – Code of Practice for Temporary Works Procedures and the Permissible Stress Design of Falsework) published since the incident, clarifies how the temporary works should be managed on such a project and focuses on the competence of all parties. […]

    5. MAJOR CONTRACTOR FAILED ON TEMPORARY WORKS SAFETY | PP Construction Safety News Desk Says:

      […] Speaking after the hearing, HSE Principal Inspector Andrew Kingscott said: “The two workers were fortunate not to have been seriously injured in this incident, which was entirely preventable had Balfour Beatty followed the proper temporary works procedure. […]

    6. SAFETY EVENT TRIGGERED BY SITE DEATHS AND INJURY | PP Construction Safety News Desk Says:

      […] either a morning or afternoon session covering asbestos, working at height, respiratory risks and temporary works. For further information call: 0151 951 4012 or contact […]

    7. HSE PRIORITIES FOR CONSTRUCTION SECTOR 2013-14 | PP Construction Safety News Desk Says:

      […] Works – managing temporary works through adequate management […]

    8. FREE WWT TRAINING EVENT ON TW AND BEHAVIOUR | PP Construction Safety News Desk Says:

      […] Temporary Works […]

    9. TEMPORARY WORKS COORDINATOR TRAINING | PP Construction Safety News Desk Says:

      […] Following a number of construction sector deaths and incidents related to ‘temporary works’ HSE has raised the priority it gives to temporary works management. […]