Turner Access Higher Safety Total Access
Total Access Ethentic Chipmunk Data
Chipmunk Data Turner Access Ethentic

HSE RAISE THE PROFILE ON SAFETY OF TEMPORARY WORKS

New guidance to HSE Inspectors on temporary works management published

A number of recent construction sector fatalities and incidents have related to ‘temporary works’.

HSE Construction Division has now raised the priority it gives to temporary works management in order to highlight and better control the risks associated with temporary works on construction sites.

The aim is to:

  • Awareness – promote awareness and knowledge of the importance of managing temporary works;
  • Arrangements – improve contractors’ management arrangements of temporary works; and 
  • Competence – increase the competence of those engaged in temporary works management and design.
Inspectors expect to see ‘appropriate’ arrangements

The published HSE Guidance for Inspectors The management of temporary works in the construction industry SIM 02/2010/04 requires a focus on ensuring that “appropriate temporary works management arrangements and procedures have been adopted commensurate with the scale and complexity of the project and the construction risks involved”.

It is expected that medium to large projects, and those with complex and/or high risk temporary works, will have formal management procedures in place specifically following the recommendations in BS5975.

For smaller contractors and smaller simpler, projects, HSE will be looking for the principles of BS5975 to be in place. The extent to which procedures should be formalised will depend on the degree of risk rather than size of project.

HSE wants to see good management of temporary works. BS5975 is an established standard representing good practice, but it also provides a useful yardstick for checking that essential elements of a management system are in place.

Definition of ‘Temporary Works’

“Temporary works” is a widely used expression in the construction industry for an “engineered solution” used to support or protect an existing structure or the permanent works during construction, or to support an item of plant or equipment, or the vertical sides or side-slopes of an excavation, or to provide access. The construction of most types of permanent works will require the use of some form of temporary works.

Temporary works is defined in BS5975: 2008 Code of practice for temporary works procedures and the permissible stress design of falsework as “(those) parts of the works that allow or enable construction of, protect, support or provide access to, the permanent works and which might or might not remain in place at the completion of the works”.

Examples of temporary works include, but are not limited to:

  1. Earthworks – trenches, excavations, temporary slopes and stockpiles.
  2. Structures – formwork, falsework, propping, façade retention, needling, shoring, edge protection, scaffolding, temporary bridges, site hoarding and signage, site fencing, cofferdams.
  3. Equipment/plant foundations – tower crane bases, supports, anchors and ties for construction hoists and mast climbing work platforms (MCWPs), groundworks to provide suitable locations for plant erection, e.g. mobile cranes and piling rigs.
Comment

Further advice and support may be found through the Temporary Works Forum (TWf). Forum sponsers include a number of major UK contactors.

The TWf aims to encourage open discussion of any matter related to Temporary Works. The group is open to anyone, individual or corporate working within the industry and sharing this intent.

Latest Construction Health and Safety News

UPDATED SCAFFOLDING DESIGN E-GUIDE RELEASED

NASC launches enhanced TG20:13 eGuide scaffold design tool

Read the rest of this article »

Posted on 14th August 2017

NASC LAUNCH FREE TO DOWNLOAD GUIDANCE

Access and scaffolding guides now open to members and non-members

Read the rest of this article »

Posted on 14th August 2017

HSE ENFORCEMENT WEEKLY UPDATE 9th AUGUST 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 11th August 2017

NEW GUIDANCE ON UNINTENDED PLANT MOVEMENT

Industry Plant Safety Group highlights hazards and key control measures

Read the rest of this article »

Posted on 11th August 2017

SCAFFOLD COLLAPSE CAUSED BY LACK OF TIES

Falling structure narrowly misses passerby and lands on parked cars

Read the rest of this article »

Posted on 11th August 2017

HSE ENFORCEMENT WEEKLY UPDATE 2nd AUG 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 2nd August 2017

TRAINING IN CIRCULAR SAW USE FOUND WANTING

Joinery firm failures end in serious hand injury and £230,000 fine

Read the rest of this article »

Posted on 31st July 2017

HSE ENFORCEMENT WEEKLY UPDATE 26th JULY 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 31st July 2017

WALL COLLAPSE CLAIMED LIFE OF WORKMAN

Failed to identify risks associated with free standing walls

Read the rest of this article »

Posted on 31st July 2017

WORKMAN FELL DURING WELDING WORK AT HEIGHT

Ladder access to water tank top was insecure and slipped when used

Read the rest of this article »

Posted on 31st July 2017

CCTV INSTALLER FELL BETWEEN FLOOR JOISTS

Principal Contractor and CCTV specialist failed to plan and manage risk

Read the rest of this article »

Posted on 31st July 2017

FACTORY APPRENTICE FELL DURING GUTTER CLEANING

Young workman stepped back and fell 9m through fragile rooflight

Read the rest of this article »

Posted on 31st July 2017

CROSS RAIL JV CONTRACTORS FINED OVER FATALITY

Firm prosecuted after concrete fall death and two other tunnel incidents

Read the rest of this article »

Posted on 31st July 2017

CONTRACTORS FAILED TO REVIEW ASBESTOS SURVEY

Major companies fined £1,000,000 plus over asbestos risk during refurb

Read the rest of this article »

Posted on 31st July 2017

MAJOR CONTRACTORS LAUNCH H&S ALERT SYSTEM

Build UK members share information for effective prevention of harm

Read the rest of this article »

Posted on 19th July 2017

HSE ENFORCEMENT WEEKLY UPDATE 19th JULY 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 19th July 2017

STRUCTURAL SAFETY BODY LATEST NEWSLETTER

SCOSS publishes reports and expert comment on a range of issues

Read the rest of this article »

Posted on 18th July 2017

SAFE SYSTEM DEVISED BUT NOT IMPLEMENTED

Workman injured by goods falling from double-decked trailer

Read the rest of this article »

Posted on 18th July 2017

PREVENTION PLANNING REQUIRED FOR FRAGILE RISK

Fall arrest safety netting not used to mitigate fall consequences

Read the rest of this article »

Posted on 17th July 2017

MANAGEMENT OF FORMWORK NOT UP TO THE MARK

Erector fell 3m after access scaffold board failed under load

Read the rest of this article »

Posted on 17th July 2017

VIBRATION UNCONTROLLED & WORKERS UNINFORMED

Engineering firm fined £120,000 over hand-arm vibration risk

Read the rest of this article »

Posted on 14th July 2017

HSE ENFORCEMENT WEEKLY UPDATE 12th JULY 2017

hselogo1Prosecutions and enforcement notices weekly update and analysis

Read the rest of this article »

Posted on 12th July 2017

SCAFFOLDER WAS UNTRAINED AND UNSUPERVISED

Contractor and director failed to train injured workman to CISRC scheme

Read the rest of this article »

Posted on 10th July 2017

WORKPLACE MANSLAUGHTER OUTCOMES SET TO RISE

Guidelines target gross negligence with serious disregard and cost-cutting

Read the rest of this article »

Posted on 7th July 2017

WORKMAN BURNT CLEANING WITH FLAMMABLE LIQUIDS

Flammable substance and unprotected electrical equipment trigger flash fire

Read the rest of this article »

Posted on 7th July 2017
Turner Access Chipmunk Data
Total Access Ethentic
Higher Safety Turner Access

9 Responses to “HSE RAISE THE PROFILE ON SAFETY OF TEMPORARY WORKS”

  1. HSE CONSTRUCTION SECTOR PRIORITIES 2011 AND BEYOND | PP Construction Safety News Desk Says:

    […] Works – promoting awareness and knowledge of the importance of managing temporary works effectively and ensure that adequate management arrangements are in […]

  2. TEMPORARY WORKS NOT PROPERLY DESIGNED FOR SAFETY | PP Construction Safety News Desk Says:

    […] HSE Inspector Viv Neaverson said: “This prosecution arises as a result of Bridgford’s failing in their duty as the company responsible for the temporary works. […]

  3. MAJOR CONTRACTOR PROSECUTED OVER TEMPORARY WORKS COLLAPSE | PP Construction Safety News Desk Says:

    […] that concrete was being pumped onto the third floor of the building on 19 September 2007 when the temporary works suddenly collapsed. Injuries to the workers on site included cement burns to their skin and […]

  4. CONCRETE UNIT COLLAPSE SPARKED BY DESIGN COMMS FAILURE | PP Construction Safety News Desk Says:

    […] HSE advises that British Standard, (BS 5975:2008 – Code of Practice for Temporary Works Procedures and the Permissible Stress Design of Falsework) published since the incident, clarifies how the temporary works should be managed on such a project and focuses on the competence of all parties. […]

  5. MAJOR CONTRACTOR FAILED ON TEMPORARY WORKS SAFETY | PP Construction Safety News Desk Says:

    […] Speaking after the hearing, HSE Principal Inspector Andrew Kingscott said: “The two workers were fortunate not to have been seriously injured in this incident, which was entirely preventable had Balfour Beatty followed the proper temporary works procedure. […]

  6. SAFETY EVENT TRIGGERED BY SITE DEATHS AND INJURY | PP Construction Safety News Desk Says:

    […] either a morning or afternoon session covering asbestos, working at height, respiratory risks and temporary works. For further information call: 0151 951 4012 or contact […]

  7. HSE PRIORITIES FOR CONSTRUCTION SECTOR 2013-14 | PP Construction Safety News Desk Says:

    […] Works – managing temporary works through adequate management […]

  8. FREE WWT TRAINING EVENT ON TW AND BEHAVIOUR | PP Construction Safety News Desk Says:

    […] Temporary Works […]

  9. TEMPORARY WORKS COORDINATOR TRAINING | PP Construction Safety News Desk Says:

    […] Following a number of construction sector deaths and incidents related to ‘temporary works’ HSE has raised the priority it gives to temporary works management. […]