• Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data

    MAJOR CLIENT PROSECUTED FOR CDM-C ROLE FAILURE

    Workman suffered serious leg injuries during manual handling of prefab wall

    BAE Systems Properties Ltd, of Farnborough, Hampshire has been fined £8,000 with costs of £6,110 after failing to ensure that a design for construction could be built without risks to the health and safety of those carrying out the building work.

    The company assumed the role of CDM-Coordinator involving the duty to oversee designer compliance. However, the company failed to take all reasonable steps to check that designers had complied with their duties contrary to CDM 2007 Regulation 20(2)(c).

    The principal contractor, Emcor Facilities Services Ltd, was also prosecuted regarding failures in planning the operation and manual handling contrary to CDM Regulation 22(1)(a). The company was fined £15,000 and ordered to pay costs of £6,110.

    BS Interiors (South) Ltd, of Portsmouth, also pleaded guilty to breaching the Manual Handling Regulation 1992 – Reg 4. The company was fined £1,500.

    Structure trapped workman during manual handling op

    The offences came to light after an electrician suffered serious leg injuries when he became trapped under a prefabricated wall on the BAE Systems site in Portsmouth on 20 August 2008.

    Emcor Facilities Services Ltd and BS Interiors (South) Ltd decided to erect the 10.4 metre long, 2.8 metre high wall on the floor due to the design of the building. Seven workers including the injured man proceeded to manually lift the 1,136 kilogram structure. When lifting operation was aborted the workman was trapped beneath the wall.

    He suffered injury to his left foot and was hospitalised for two weeks. Two years after the accident he is unable to work full-time and still suffers pain and disability.

    Case illustrates importance of planning

    HM Specialist Inspector in Occupational Health, Anne Bartlett said:

    “This case illustrates the importance of identifying hazards at the planning stage. This is the key aim of the CDM Regulations 2007.

    If a proper risk assessment had been carried out, those involved would have realise that manual handing of the wall would have created a real and obvious risk to those present. It defies common sense and was extremely foolhardy.

    As a result for this failure Mr Cox sustained serious injuries that will affect him for the rest of his life, but which could so easily have been avoided.”

    Comment

    This is an unusual and interesting prosecution. There have been very few prosecutions of CDM-Coordinators.

    It appears that BAE Systems Properties Ltd ommitted to appoint a coordinator and therefore assumed the duties by virtue of CDM Regulation 14(4) under which the client is deemed to have been appointed as the CDM co-ordinator for any period for which no person has been so appointed.

    The client must appoint a CDM-C as early as possible and no later than after initial design work is completed. ‘Initial design work’ includes feasibility studies and any work necessary to identify the client requirements or possible constraints on the development.

    Latest Construction Health and Safety News

    HSE ENFORCEMENT WEEKLY UPDATE 13th JUNE 2018

    hselogo1Prosecutions and enforcement notices register latest version

    Read the rest of this article »

    Posted on 13th June 2018

    DIRECTOR FAILED COMPLY WITH HSE PROHIBITION

    Precautions not taken to prevent excavation collapse and falling

    Read the rest of this article »

    Posted on 11th June 2018

    SCAFFOLD NOT TO INDUSTRY STANDARD OR DESIGN

    Specialist and contractor in court over unsafe work at height

    Read the rest of this article »

    Posted on 7th June 2018

    ROAD WORKER RUN OVER BY ROAD ROLLER

    Reversing alarm not working and warning light not fitted

    Read the rest of this article »

    Posted on 5th June 2018

    CLIENT AND SURVEYOR FINED OVER ASBESTOS SURVEY

    Refurbishment and demolition asbestos survey proved inadequate

    Read the rest of this article »

    Posted on 5th June 2018

    FATALITY: ROAD WORKER DRAGGED ALONG ROAD

    Night shift worker loses life when struck by road sweeping vehicle

    Read the rest of this article »

    Posted on 3rd June 2018

    CDM PRINCIPAL DESIGNERS AVOID HSE ENFORCEMENT

    Regulator enforcement database reveals few notices involve CDM PDs

    Read the rest of this article »

    Posted on 3rd June 2018

    PROPERTY MANAGERS FINED WITH CONTRACTOR

    Defendants failed to check for asbestos during soffit replacement works

    Read the rest of this article »

    Posted on 29th May 2018

    EXCAVATION CAUSED RETAINING WALL COLLAPSE

    Precautions not taken to secure stability of free-standing wall

    Read the rest of this article »

    Posted on 29th May 2018

    OVERHEAD CABLE STRIKE FIRM FINED £500,000+

    Inadequate system caused risk of harm despite lack of worker injury

    Read the rest of this article »

    Posted on 29th May 2018

    CDM 2015 PRINCIPAL DESIGNER FINED OVER FIRE RISK

    PD and PC failed to comply with CDM 2015 responsibilities

    Read the rest of this article »

    Posted on 23rd May 2018

    SENTENCING GUIDELINES UNDER THE MICROSCOPE

    Lawyer argues guidelines undermine reduction in ‘regulatory burden’

    Read the rest of this article »

    Posted on 23rd May 2018

    PANEL STRUCK WORKMAN DURING LIFTING OPERATION

    Third party contractor falls victim of poor lift planning

    Read the rest of this article »

    Posted on 21st May 2018

    DIRECTOR LED HAZARDOUS WORK AT HEIGHT

    Three occasions when work lacked suitable and sufficient precautions

    Read the rest of this article »

    Posted on 21st May 2018

    RISK ASSESSED BUT CONTROLS FOUND WANTING

    Joiner fell through unprotected opening on roof of new building

    Read the rest of this article »

    Posted on 21st May 2018

    RIBA CRITICAL OF HACKITT REVIEW FINAL REPORT

    High rise residential review dismissed as “major missed opportunity”

    Read the rest of this article »

    Posted on 21st May 2018

    CONSTRUCTION SECTOR DEATHS: THE ‘BIG THREE’

    HSE in-year fatalities for 2017/18 may indicate upward trend

    Read the rest of this article »

    Posted on 16th May 2018

    SCAFFOLDING SITE ACCIDENTS AT RECORD LOW

    NASC Annual Report reveals all time low in 2017 incidents

    Read the rest of this article »

    Posted on 14th May 2018

    DUMPER TRUCK HAND-BRAKE NOT MAINTAINED

    Workman injured when pinned against stack of concrete blocks

    Read the rest of this article »

    Posted on 14th May 2018

    SPARE POWER INTERLOCK KEY CAUSED DEATH

    Dangerous machinery safety precautions defeated for maintenance tasks

    Read the rest of this article »

    Posted on 10th May 2018

    COLLAPSED CAR PARK WAS UNDER REPAIR

    Rusted steel supports triggered collapse of fascia and floor

    Read the rest of this article »

    Posted on 8th May 2018

    DUMPER OVERTURN CAUSED FATAL INJURIES

    Precautions during spoil heap creation were inadequate

    Read the rest of this article »

    Posted on 8th May 2018

    HARDWOOD DUST CONTROL NOT MAINTAINED

    Manufacturer failed to examine and test local extraction system

    Read the rest of this article »

    Posted on 8th May 2018

    SCAFFOLD CONTRACTOR OVERLOOKED MAJOR HAZARD

    Well-known risk unidentified during scaffold erection project

    Read the rest of this article »

    Posted on 8th May 2018

    THREE FIRMS FINED £1/2M FOR FRAGILE RISK FAILURES

    Fall through rooflight hazard poorly planned and managed

    Read the rest of this article »

    Posted on 2nd May 2018
    Total Access Total Access Ethentic Ethentic
    Higher Safety Higher Safety Chipmunk Data Chipmunk Data